  8970   Tue Aug 6 10:06:29 2013 SteveUpdateVACPumpdown is at 500Torr The pumpdown has started at 8:38am
Manasa was here to confirm good alignment
of the IFO
 befPd.png 
  8973   Tue Aug 6 16:45:31 2013 SteveUpdateVACPumpdown is completed IFO  P1=1mT PSL shutter is opened
 
 8hrPd76.png1mT.png 
  8976   Wed Aug 7 10:51:49 2013 SteveUpdateVACPumpdown at 26hrs Cold cathode gauge CC1 -h (horizontal)
just coming on 9.2e-5 Torr
P2 is the fore line pressure of the
 26hr.png14datm.png 
  8978   Wed Aug 7 15:36:29 2013 SteveUpdateVACTP2 drypump replaced 
 TP2's fore line - dry pump
replaced at performance level 600 mTorr after
 forelinesPs.jpg 
  8984   Thu Aug 8 07:57:23 2013 SteveUpdateVACpumpdown at 48 hrs

    

       
            
 48hrsPd76.png 
  8985   Thu Aug 8 10:31:28 2013 SteveUpdateVACfew reminders of this vent 1, Vacuum envelope grounds must be
connected all times!  After door removal
reconnect both cables immediately.
 GROUND!.jpgbad_Folding.jpgtoomuchred.jpgBETTERholder.jpg 
  9011   Wed Aug 14 08:24:20 2013 SteveUpdateVACpumpdown at day 8 
 
 pd76md8.png 
  9017   Fri Aug 16 09:35:18 2013 SteveUpdateVACVacuum Normal state recognition is back

    

       
            
 VacuumNormal.pngvacValvesDisabled.jpg 
  9029   Mon Aug 19 11:12:54 2013 SteveUpdateVACRGA scan at day 13 
 
 rgaScan13d.png 
  9084   Wed Aug 28 11:23:41 2013 SteveUpdateVACcrane repair sheduled

    

       
            
  
  9085   Wed Aug 28 15:41:42 2013 SteveUpdateVACRGA scan at day 23 Valve configuration: Vacuum Normal
pd76-m-d23
 
 pd75md23.png 
  9111   Thu Sep 5 10:47:58 2013 SteveUpdateVACvertex crane folding issue 
 [Fred Goldbar, Mike Gerfen,
Dennis Coyne and Steve]
 5mmLess.jpg 
  9115   Fri Sep 6 09:27:10 2013 SteveUpdateVAC31 days after pumpdown

    

       
            
 day31vac.png 
  9117   Mon Sep 9 15:33:06 2013 SteveUpdateVACvertex crane repair is scheduled

    

       
            
  
  9119   Tue Sep 10 09:18:22 2013 SteveUpdateVACdry pump is getting loud 
 TP3 foreline's dry pump is
getting noisier and noisier.  Turbo
  
  9120   Tue Sep 10 15:43:01 2013 SteveUpdateVACTP3' dry pump is replaced

    

       
            
  
  9129   Mon Sep 16 10:57:11 2013 SteveUpdateVACRGA scan at day 41

    

       
            
 pd76m41dRGA.pngpd76m41d.png 
  9139   Wed Sep 18 14:57:12 2013 SteveUpdateVACvertex crane folding arm removed The folding beam removed as shown.
Two man supporting it while I hammering it
out. Pin was dry and it gulled into supporting
 manPower.jpgrotatingHinge.jpgsupportingHinge.jpggullingPin.jpg 
  9146   Fri Sep 20 16:37:30 2013 SteveUpdateVACvertex crane folding arm is back on

    

       
            
 bushingBottom.jpgfoldingI.jpgnoLoadGap.jpgtrollyway.jpgtrollySee.jpg 
  9173   Mon Sep 30 08:53:22 2013 SteveUpdateVACvertex crane repair schedule has changed

    

       
            
  
  9185   Wed Oct 2 14:25:39 2013 SteveUpdateVACvertex crane is still out of order 
The smoke alarms were turned off
and surrounding areas were covered with plastic.
 grindingIbeam.jpgcableMoved.jpg500lbs@end.jpg 
  9223   Wed Oct 9 11:48:10 2013 SteveUpdateVACRGA scan at day 65 
 Valve configuration: Vacuum
Normal
 scanRGApd76m65d.pngpd76m65d.png 
  9359   Thu Nov 7 11:19:04 2013 SteveUpdateVACcrane work POSTPONED to Monday

    

       
            
  
  9372   Wed Nov 13 08:46:03 2013 SteveUpdateVACvertex crane repair completed

    

       
            
  
  9424   Fri Nov 22 16:32:08 2013 SteveUpdateVACRGA scan at day 108

    

       
            
 RGAscanVacNormal108d.pngday108.pngpd76m110d.png 
  9467   Fri Dec 13 16:34:20 2013 SteveUpdateVACPS will be replaced next week

    

       
            
 hotPSvacRack.jpgfan1X8.jpg 
  9506   Fri Dec 20 20:04:01 2013 SteveUpdateVACpower supply replaced with a short vent

    

       
            
 4hrPumpdown.pngpumpdownAfterHickup.pngPSpumpdown.png 
  9508   Fri Dec 20 23:00:41 2013 KojiUpdateVACpower supply replaced with a short ventI'm leaving the 40m now. IFO is aligned. Everything
look good.
  
  9510   Sat Dec 21 10:53:35 2013 SteveUpdateVACpower supply replaced with a short vent-pumpdown completedThe recovery- pumpdown reached valve configuration 
vacuum normal at 20 hours, cc1 7.7e-6 Torr
 20hrsVacNormal.png 
  9514   Thu Jan 2 10:50:24 2014 SteveUpdateVAC vacuum monitor is still blank The date is correct on this monitor.
Last stored RGA scan data Dec 20,
2013
 Help.pngvacation.png20131220lastRGAscan.png 
  9515   Thu Jan 2 13:35:06 2014 KojiUpdateVAC vacuum monitor is still blankWe probably need to restart the machine,
but I didn't want to touch c1vac1 and c1vac2. 
  
  9516   Fri Jan 3 11:18:41 2014 SteveSummaryVACpower supply replaced with a short vent

    

       
            
 rebootVENT.png 
  9550   Mon Jan 13 16:50:55 2014 SteveUpdateVACMaglev controller needs service

    

       
            
  
  9562   Tue Jan 21 17:26:59 2014 JenneSummaryVACRebooted RGA computer and reset RGA settings[Jenne, Steve]
Steve noticed that the RGA was not
logging data and that not all the correct
  
  9565   Wed Jan 22 15:24:11 2014 SteveSummaryVACRga scan after reboot

    

       
            
 Rgascan169dwarmingup.pngBlankMedmMustBeFixed.png 
  9570   Thu Jan 23 08:04:04 2014 SteveUpdateVACvacuum control screen is blank 
There is 
 pd76m170d2dRgaOn.png 
  9571   Thu Jan 23 13:23:10 2014 SteveUpdateVAC40m IFO is at atmosphere

    

       
            
  
  9576   Mon Jan 27 09:08:00 2014 SteveUpdateVAC4 days at atmosphere 
 
 day4atm.pngvent76bgTp3d4.png 
  9581   Tue Jan 28 11:13:50 2014 KojiUpdateVAC vacuum monitor is still blank[Steve Koji]
We
pushed the reset button of c1vac1 and c1vac2
  
  9582   Tue Jan 28 16:26:40 2014 SteveUpdateVAC vacuum computers are back without safety

    

       
            
 c1vac1_vac2areback.png 
  9599   Wed Feb 5 08:14:59 2014 SteveUpdateVAC vacuum computers are back without safety

    

       
            
  
  9604   Wed Feb 5 19:36:50 2014 SteveUpdateVACpumpdown at 25 Torr

    

       
            
 pd77at3.5h.png 
  9605   Wed Feb 5 19:53:51 2014 SteveUpdateVACpumpdown stops for the day at 14 Torr 
 
 stopHere.png 
  9607   Thu Feb 6 11:14:07 2014 SteveUpdateVACpumpdown completed Pumpdown completed. IR shutter opened
at P1 1 mTorr  The block is still in
the beam path.
 pd77.png 
  9615   Mon Feb 10 09:45:53 2014 SteveUpdateVACvacuum normal is reached 


 pd77m5d.png13daysAtm.png 
  9622   Tue Feb 11 10:44:15 2014 SteveUpdateVACRGA scan at day 6 
 
 pd77m6d.png 
  9644   Tue Feb 18 10:38:55 2014 SteveUpdateVACRGA scan at day 13 All normal.
 
 pd77m13d.pngRGAscan13d.png 
  9703   Fri Mar 7 16:13:03 2014 SteveUpdateVACpumping speed is recovered

    

       
            
 pumpingSpeed.png 
  9723   Wed Mar 12 08:40:42 2014 SteveUpdateVACRGA scan at day 35 
 
 pd77m35d.png 
  9745   Mon Mar 24 10:41:46 2014 SteveUpdateVACRGA scan at day 50 
 
 pd77m50dRGA.png 