  15465   Thu Jul 9 18:00:35 2020 JonConfigurationVACUPS replacements

Chub has placed the order for two new UPS units (115V for TP2/3 and a 220V version for TP1).

They will arrive within the next two weeks.

Quote:

​I looked into how the new UPS devices suggested by Chub would communicate with the vac interlocks. There are several possible ways, listed in order of preference:

  • Python interlock service directly queries the UPS via a USB link using the (unofficial) tripplite package. Direct communication would be ideal because it avoids introducing a dependency on third-party software outside the monitoring/control capability of the interlock manager. However the documentation warns this package does not work for all models...
  • Configure Tripp Lite's proprietary software (PowerAlert Local) to send SYSLOG event messages (UDP packets) to a socket monitored by the Python interlock manager.
  • Configure the proprietary software to execute a custom script upon an event occurring. The script would, e.g., set an EPICS flag channel which the interlock manager is continually monitoring.

I recommend we proceed with ordering the Tripp Lite 36HW20 for TP1 and Tripp Lite 1AYA6 for TP2 and TP3 (and other 120V electronics). As far as I can tell, the only difference between the two 120V options is that the 6FXN4 model is TAA-compliant.

  15510   Sat Aug 8 07:36:52 2020 Sanika KhadkikarConfigurationCalibration-RepairBS Seismometer - Multi-channel calibration

Summary : 

I have been working on analyzing the seismic data obtained from the 3 seismometers present in the lab. I noticed while looking at the combined time series and the gain plots of the 3 seismometers that there is some error in the calibration of the BS seismometer. The EX and the EY seismometers seem to be well-calibrated as opposed to the BS seismometer.

The calibration factors have been determined to be :

BS-X Channel: \small {\color{Blue} 2.030 \pm 0.079 }

BS-Y Channel: \small {\color{Blue} 2.840 \pm 0.177 }

BS-Z Channel: \small {\color{Blue} 1.397 \pm 0.182 }


Details :

The seismometers each have 3 channels i.e X, Y, and Z for measuring the displacements in all the 3 directions. The X channels of the three seismometers should more or less be coherent in the absence of any seismic excitation with the gain amongst all the similar channels being 1. So is the case with the Y and Z channels. After analyzing multiple datasets, it was observed that the values of all the three channels of the BS seismometer differed very significantly from their corresponding channels in the EX and the EY seismometers and they were not calibrated in the region that they were found to be coherent as well. 


Method :

Note: All the frequency domain plots that have been calculated are for a sampling rate of 32 Hz. The plots were found to be extremely coherent in a certain frequency range i.e ~0.1 Hz to 2 Hz so this frequency range is used to understand the relative calibration errors. The spread around the function is because of the error caused by coherence values differing from unity and the averages performed for the Welch function. 9 averages have been performed for the following analysis keeping in mind the needed frequency resolution(~0.01Hz) and the accuracy of the power calculated at every frequency. 

  1. I first analyzed the regions in which the similar channels were found to be coherent to have a proper gain analysis. The EY seismometer was found to be the most stable one so it has been used as a reference. I saw the coherence between similar channels of the 2 seismometers and the bode plots together. A transfer function estimator was used to analyze the relative calibration in between all 3 pairs of seismometers. In the given frequency range EX and EY have a gain of 1 so their relative calibration is proper. The relative calibration in between the BS and the EY seismometers is not proper as the resultant gain is not 1. The attached plots show the discrepancies clearly : 
  • BS-X & EY-X Transfer Function : Attachment #1
  • BS-Y & EY-Y Transfer Function : Attachment #2

          The gain in the given frequency range is ~3. The phase plotting also shows a 180-degree phase as opposed to 0 so a negative sign would also be required in the calibration factor. Thus the calibration factor for the Y channel of the BS seismometer should be around ~3. 

  • BS-Z & EY-Z Transfer Function : Attachment #3

The mean value of the gain in the given frequency range is the desired calibration factor and the error would be the mean of the error for the gain dataset chosen which is caused due to factors mentioned above.

Note: The standard error envelope plotted in the attached graphs is calculated as follows :

         1. Divide the data into n segments according to the resolution wanted for the Welch averaging to be performed later. 

         2. Calculate PSD for every segment (no averaging).

         3. Calculate the standard error for every value in the data segment by looking at distribution formed by the n number values we obtain by taking that respective value from every segment.

Discussions :

The BS seismometer is a different model than the EX and the EY seismometers which might be a major cause as to why we need special calibration for the BS seismometer while EX and EY are fine. The sign flip in the BS-Y seismometer may cause a lot of errors in future data acquisitions. The time series plots in Attachment #4 shows an evident DC offset present in the data. All of the information mentioned above indicates that there is some electrical or mechanical defect present in the seismometer and may require a reset. Kindly let me know if and when the seismometer is reset so that I can calibrate it again. 

  15526   Fri Aug 14 10:10:56 2020 JonConfigurationVACVacuum repairs today

The vac system is going down now for planned repairs [ELOG 15499]. It will likely take most of the day. Will advise when it's back up.

  15527   Sat Aug 15 02:02:13 2020 JonConfigurationVACVacuum repairs today

Vacuum work is completed. The TP2 and TP3 interlocks have been overhauled as proposed in ELOG 15499 and seem to be performing reliably. We're now back in the nominal system state, with TP2 again backing for TP1 and TP3 pumping the annuli. I'll post the full implementation details in the morning.

I did not get to setting up the new UPS units. That will have to be scheduled for another day.

Quote:

The vac system is going down now for planned repairs [ELOG 15499]. It will likely take most of the day. Will advise when it's back up.

  15528   Sat Aug 15 15:12:22 2020 JonConfigurationVACOverhaul of small turbo pump interlocks

Summary

Yesterday I completed the switchover of small turbo pump interlocks as proposed in ELOG 15499. This overhaul altogether eliminates the dependency on RS232 readbacks, which had become unreliable (glitchy) in both controllers. In their place, the V4(5) valve-close interlocks are now predicated on an analog controller output whose voltage goes high when the rotation speed is >= 80% of the nominal setpoint. The critical speed is 52.8 krpm for TP2 and 40 krpm for TP3. There already exist hardware interlocks of V4(5) using the same signals, which I have also tested.

Interlock signal

Unlike the TP1 controller, which exposes simple relays whose open/closed states are sensed by Acromags, what the TP2(3) controllers output is an energized 24V signal for controlling such a relay (output circuit pictured below). I hadn't appreciated this difference and it cost me time yesterday. The ultimate solution was to route the signals through a set of new 24V Phoenix Contact relays installed inside the Acromag chassis. However, this required removing the chassis from the rack and bringing it to the electronics bench (rather than doing the work in situ, as I had planned). The relays are mounted to the second DIN rail opposite the Acromags. Each TP2(3) signal controls the state of a relay, which in turn is sensed using an Acromag XT1111.

Signal routing

The TP2(3) "normal-speed" signals are already in use by hardware interlocks of V4(5). Each signal is routed into the main AC relay box, where it controls an "interrupter" relay through which the Acromag control signal for the main V4(5) relay is passed. These signals are now shared with the digital controls system using a passive DB15 Y-splitter. The signal routing is shown below.

Interlock conditions

The new turbo-pump-related interlock conditions and their channel predicates are listed below. The full up-to-date channel list and wiring assignments for c1vac are maintained here.

Channel Type New? Interlock-triggering condition
C1:Vac-TP1_norm BI No Rotation speed < 90% nominal setpoint (29 krpm)
C1:Vac-TP1_fail BI No Critical fault occurrence
C1:Vac-TP1_current AI No Current draw > 4 A
C1:Vac-TP2_norm BI Yes Rotation speed < 80% nominal setpoint (52.8 krpm)
C1:Vac-TP3_norm BI Yes Rotation speed < 80% nominal setpoint (40 krpm)

There are two new channels, both of which provide a binary indication of whether the pump speed is outside its nominal range. I did not have enough 24V relays to also add the C1:Vac-TP2(3)_fail channels listed in ELOG 15499. However, these signals are redundant with the existing interlocks, and the existing serial "Status" readback will already print failure messages to the MEDM screens. All of the TP2(3) serial readback channels remain, which monitor voltage, current, operational status, and temperature. The pump on/off and low-speed mode on/off controls remain implemented with serial signals as well.

The new analog readbacks have been added to the MEDM controls screens, circled below:

Other incidental repairs

  • I replaced the (dead) LED monitor at the vac controls console. In the process of finding a replacement, I came across another dead spare monitor as well. Both have been labeled "DEAD" and moved to Jordan's desk for disposal.
  • I found the current TP3 Varian V70D controller to be just as glitchy in the analog outputs as well. That likely indicates there is a problem with the microprocessor itself, not just the serial communications card as I thought might be the case. I replaced the controller with the spare unit which was mounted right next to it in the rack [ELOG 13143]. The new unit has not glitched since the time I installed it around 10 pm last night.
  15738   Fri Dec 18 22:59:12 2020 JonConfigurationCDSUpdated CDS upgrade plan

Attached is the layout for the "intermediate" CDS upgrade option, as was discussed on Wednesday. Under this plan:

  • Existing FEs stay where they are (they are not moved to a single rack)

  • Dolphin IPC remains PCIe Gen 1

  • RFM network is entirely replaced with Dolphin IPC

Please send me any omissions or corrections to the layout.

  15742   Mon Dec 21 09:28:50 2020 JamieConfigurationCDSUpdated CDS upgrade plan
Quote:

Attached is the layout for the "intermediate" CDS upgrade option, as was discussed on Wednesday. Under this plan:

  • Existing FEs stay where they are (they are not moved to a single rack)

  • Dolphin IPC remains PCIe Gen 1

  • RFM network is entirely replaced with Dolphin IPC

Please send me any omissions or corrections to the layout.

I just want to point out that if you move all the FEs to the same rack they can all be connected to the Dolphin switch via copper, and you would only have to string a single fiber to every IO rack, rather than the multiple now (for network, dolphin, timing, etc.).

  15746   Wed Dec 23 23:06:45 2020 gautamConfigurationCDSUpdated CDS upgrade plan
  1. The diagram should clearly show the host machines and the expansion chassis and the interconnects between them.
  2. We no longer have any Gentoo bootserver or diskless FEs.
  3. The "c1lsc" host is in 1X4 not 1Y3.
  4. The connection between c1lsc and Dolphin switch is copper not fiber. I don't know how many Gbps it is. But if the switch is 10 Gbps, are they really selling interface cables that have lower speed? The datasheet says 10 Gbps.
  5. The control room workstations - Debian10 (rossa) is the way forward I believe. it is true pianosa remains SL7 (and we should continue to keep it so until all other machines have been upgraded and tested on Debian 10).
  6. There is no "IOO/OAF". The host is called "c1ioo".
  7. The interconnect between Dolphin switch and c1ioo host is via fiber not copper.
  8. It'd be good to have an accurate diagram of the current situation as well (with the RFM network).
  9. I'm not sure if the 1Y1 rack can accommodate 2 FEs and 2 expansion chassis. Maybe if we clear everything else there out...
  10. There are 2 "2GB/s" Copper traces. I think the legend should make clear what's going on - i.e. which cables are ethernet (Cat 6? Cat 5? What's the speed limitation? The cable? Or the switch?), which are PCIe cables etc etc. 

I don't have omnigraffle - what about uploading the source doc in a format that the excellent (and free) draw.io can handle? I think we can do a much better job of making this diagram reflect reality. There should also be a corresponding diagram for the Acromag system (but that doesn't have to be tied to this task). Megatron (scripts machine) and nodus should be added to that diagram as well.

Please send me any omissions or corrections to the layout.

  15771   Tue Jan 19 14:05:25 2021 JonConfigurationCDSUpdated CDS upgrade plan

I've produced updated diagrams of the CDS layout, taking the comments in 15476 into account. I've also converted the 40m's diagrams from Omnigraffle ($150/license) to the free, cloud-based platform draw.io. I had never heard of draw.io, but I found that it has most all the same functionality. It also integrates nicely with Google Drive.

Attachment 1: The planned CDS upgrade (2 new FEs, fully replace RFM network with Gen 1 Dolphin IPC)
Attachment 2: The current 40m CDS topology

The most up-to-date diagrams are hosted at the following links:

Please send me any further corrections or omissions. Anyone logged in with LIGO.ORG credentials can also directly edit the diagrams.

  15772   Tue Jan 19 15:43:24 2021 gautamConfigurationCDSUpdated CDS upgrade plan

Not sure if 1Y1 can accommodate both c1sus2 and c1bhd as well as the various electronics chassis that will have to be installed. There may need to be some distribution between 1Y1 and 1Y3. Does Koji's new wiring also specify which racks hold which chassis?

Some minor improvements to the diagram:

  1. The GPS receiver in 1X7 should be added. All the timing in the lab is synced to the 1pps from this.
  2. We should add hyperlinks to the various parts datasheets (e.g. Dolphin switch, RFM switch, etc etc) so that the diagram will be truly informative and self-contained.
  3. Megatron and nodus, but especially chiara (NFS server), should be added to the diagram. 
  15921   Mon Mar 15 20:40:01 2021 ranaConfigurationComputersinstalled QTgrace on donatella for dataviewer

I installed QTgrace using yum on donatella.angel Both Grace and XMgrace are broken due to some boring fight between the Fedora package maintainers and the (non existent) Grace support team. So I have symlinked it:

controls@donatella|bin> sudo mv xmgrace xmgrace_bak
controls@donatella|bin> sudo ln -s qtgrace xmgrace
controls@donatella|bin> pwd
/usr/bin

I checked that dataviewer works now for realtime and playback.cool Although the middle click paste on the mouse doesn't work yet.angry

  15928   Wed Mar 17 09:05:01 2021 Paco, AnchalConfigurationComputers40m Control Room Changes
  • Switched positions of allegra and donatella.
  • While doing so, the hdmi cable previously used by donatella snapped. We replaced this cable by another unused cable we found connected only on one end to rossa. We should get more HDMI cables if that cable was in use for some other purpose.
  • Paco bought a bluetooth speaker/mic that is placed infront of allegra and it's usb adapter is connected to iMac's keyboard in the bottom. With the new camera installed, the 40m video call environment is now complete.
  • Again, we have placed allegra's monitor for place holder but it is not working and we need new monitors for it in future whenever it is going to be used.
  16027   Wed Apr 14 13:16:20 2021 AnchalConfigurationComputers40m Control Room Changes
  • I have confirmed that the old two monitors' backlighting is not working. One can see the impression of the display without any brightness on them. Both old monitors are on the shelf behind.
  • Today we got a monitor and mouse from Mike. I had to change /etc/default/grub GRUB_GFXMODE to 1920x1200@30 on allegra for it to work with the(any) monitor.
  • Allegra is Debian 10 with latest cds-workstation installed on it. It is a good test station to migrate our existing scripts to start using updated cds-workstation configuration.
Quote:
  • Again, we have placed allegra's monitor for place holder but it is not working and we need new monitors for it in future whenever it is going to be used.

 

  16163   Wed May 26 11:45:57 2021 Anchal, PacoConfigurationIMCMC2 analog camera

[Anchal, Paco]

We went near the MC2 area and opened the lid to inspect the GigE and analog video monitors for MC2. Looked like whatever image is coming through the viewport is split into the GigE (for beam tracking) and the analog monitor. We hooked the monitor found on the floor nearby and tweaked the analog video camera around to get a feel for how the "ghost" image of the transmission moves around. It looks like in order to try and remove this "extra spots" we would need to tweak the beam tracking BS. We will consult the beam tracking authorities and return to this.

  16302   Thu Aug 26 10:30:14 2021 JamieConfigurationCDSfront end time synchronization fixed?

I've been looking at why the front end NTP time synchronization did not seem to be working.  I think it might not have been working because the NTP server the front ends were point to, fb1, was not actually responding to synchronization requests.

I cleaned up some things on fb1 and the front ends, which I think unstuck things.

On fb1:

  • stopped/disabled the default client (systemd-timesyncd), and properly installed the full NTP server (ntp)
  • the ntp server package for debian jessie is old-style sysVinit, not systemd.  In order to make it more integrated I copied the auto-generated service file to /etc/systemd/system/ntp.service, and added and "[install]" section that specifies that it should be available during the default "multi-user.target".
  • "enabled" the new service to auto-start at boot ("sudo systemctl enable ntp.service") 
  • made sure ntp was configured to serve the front end network ('broadcast 192.168.123.255') and then restarted the server ("sudo systemctl restart ntp.service")

For the front ends:

  • on fb1 I chroot'd into the front-end diskless root (/diskless/root) and manually specifed that systemd-timesyncd should start on boot by creating a symlink to the timesyncd service in the multi-user.target directory:
$ sudo chroot /diskless/root
$ cd /etc/systemd/system/multi-user.target.wants
$ ln -s /lib/systemd/system/systemd-timesyncd.service
  • on the front end itself (c1iscex as a test) I did a "systemctl daemon-reload" to force it to reload the systemd config, and then restarted the client ("systemctl restart systemd-timesyncd")
  • checked the NTP synchronization with timedatectl:
controls@c1iscex:~ 0$ timedatectl 
      Local time: Thu 2021-08-26 11:35:10 PDT
  Universal time: Thu 2021-08-26 18:35:10 UTC
        RTC time: Thu 2021-08-26 18:35:10
       Time zone: America/Los_Angeles (PDT, -0700)
     NTP enabled: yes
NTP synchronized: yes
 RTC in local TZ: no
      DST active: yes
 Last DST change: DST began at
                  Sun 2021-03-14 01:59:59 PST
                  Sun 2021-03-14 03:00:00 PDT
 Next DST change: DST ends (the clock jumps one hour backwards) at
                  Sun 2021-11-07 01:59:59 PDT
                  Sun 2021-11-07 01:00:00 PST
controls@c1iscex:~ 0$ 

Note that it is now reporting "NTP enabled: yes" (the service is enabled to start at boot) and "NTP synchronized: yes" (synchronization is happening), neither of which it was reporting previously.  I also note that the systemd-timesyncd client service is now loaded and enabled, is no longer reporting that it is in an "Idle" state and is in fact reporting that it synchronized to the proper server, and it is logging updates:

controls@c1iscex:~ 0$ sudo systemctl status systemd-timesyncd
â— systemd-timesyncd.service - Network Time Synchronization
   Loaded: loaded (/lib/systemd/system/systemd-timesyncd.service; enabled)
   Active: active (running) since Thu 2021-08-26 10:20:11 PDT; 1h 22min ago
     Docs: man:systemd-timesyncd.service(8)
 Main PID: 2918 (systemd-timesyn)
   Status: "Using Time Server 192.168.113.201:123 (ntpserver)."
   CGroup: /system.slice/systemd-timesyncd.service
           â””─2918 /lib/systemd/systemd-timesyncd

Aug 26 10:20:11 c1iscex systemd[1]: Started Network Time Synchronization.
Aug 26 10:20:11 c1iscex systemd-timesyncd[2918]: Using NTP server 192.168.113.201:123 (ntpserver).
Aug 26 10:20:11 c1iscex systemd-timesyncd[2918]: interval/delta/delay/jitter/drift 64s/+0.000s/0.000s/0.000s/+26ppm
Aug 26 10:21:15 c1iscex systemd-timesyncd[2918]: interval/delta/delay/jitter/drift 128s/-0.000s/0.000s/0.000s/+25ppm
Aug 26 10:23:23 c1iscex systemd-timesyncd[2918]: interval/delta/delay/jitter/drift 256s/+0.001s/0.000s/0.000s/+26ppm
Aug 26 10:27:40 c1iscex systemd-timesyncd[2918]: interval/delta/delay/jitter/drift 512s/+0.003s/0.000s/0.001s/+29ppm
Aug 26 10:36:12 c1iscex systemd-timesyncd[2918]: interval/delta/delay/jitter/drift 1024s/+0.008s/0.000s/0.003s/+33ppm
Aug 26 10:53:16 c1iscex systemd-timesyncd[2918]: interval/delta/delay/jitter/drift 2048s/-0.026s/0.000s/0.010s/+27ppm
Aug 26 11:27:24 c1iscex systemd-timesyncd[2918]: interval/delta/delay/jitter/drift 2048s/+0.009s/0.000s/0.011s/+29ppm
controls@c1iscex:~ 0$ 

So I think this means everything is working.

I then went ahead and reloaded and restarted the timesyncd services on the rest of the front ends.

We still need to confirm that everything comes up properly the next time we have an opportunity to reboot fb1 and the front ends (or the opportunity is forced upon us).

There was speculation that the NTP clients on the front ends (systemd-timesyncd) would not work on a read-only filesystem, but this doesn't seem to be true.  You can't trust everything you read on the internet.

  16614   Mon Jan 24 12:33:41 2022 ranaConfigurationWikiAIC Wiki: txz files allowed

I updated the mime.local.conf file for the AIC Wiki so as to allow attachments with the .txz format. THis should be persistent over upgrades, since its a local file.

  16874   Wed May 25 16:56:44 2022 PacoConfigurationBHDIFO recovery - IMC alignment

[Yuta, Paco]

We aligned IMC to recover the IFO progressively. First step was to center the MC REFL beamspot on the camera as well as the WFS DC. Then slide MC2 and MC3 together. Below are the alignment slider positions before/after.

  MC1 (before --> after) MC2 (before --> after) MC3 (before --> after)
PIT -0.3398 --> -0.4768 4.1217 --> 4.0737 -1.9808 --> -1.9308
YAW -0.8947 --> -0.7557 -1.2350 --> -1.3350 1.5598 --> 1.5638
  16875   Wed May 25 17:34:47 2022 yutaConfigurationBHDIFO recovery - IFO alignment

IFO aligned to maximize flashings, except for GRY and LO-AS.

What we did:
 0. After recovering IMC, C1:IOO-MC_TRANS_SUM was ~1300 with C1:IOO-MC_RFPD_DCMON of ~0.11 (~10% better than what we had during vent). Xarm and Yarm was already flashing and could see the beam at AS and POP cameras.
 1. Aligned ETMX and ITMX to green X input beam to maximize C1:ALS-TRX_OUT, to ~0.19.
 2. Aligned TT2-PR3 to get C1:SUS-ETMX_TRX_OUT flashing at 0.09 at max
 3. Aligned ITMY to have nice POP blinking of MICH at POP camera
 4. Aligned ETMY-PR3 to have C1:SUS-ETMX_TRX_OUT flashing at 0.06 at max
 5. Misaligned ITMY (with +2 in C1:SUS-ITMY_PIT_COMM), and aligned PRM to have PRX (PRM-ITMX cavity) flashing at C1:LSC-ASDC_IN1 at ~20 (offset -70) at max
 6. Misaligned PRM, and aligned SRM to have SRX (SRM-ITMX cavity) flashing at C1:LSC-ASDC_IN1 at ~20 (offset -70) at max
 7. Restored all the alignment. ITMY didn't quite come back, so I need to tweak the alignement to maximize TRY flashing.

Result:
Current alignment is as attached. IR beam at AS, REFL, MCR and green beam at GTRX cameras all seem slightly to the left from monitors, but looks as it was before the pump down.yes GTRY is still clipped, but green Y locks stably. Oplevs were not so useful to recover the alignment. ETMX/Y oplevs did not drifted too much probably because we don't have in-vac steering mirrors.

Next:
 - Tweak alignment of green Y input to follow Yarm
 - Do LO-AS alignment
 - REFL DC is not receiving beam. Re-alignment necessary
 - Oplev centering
 - BHD PDs need to be replaced to lower gain PDs and need to be connected to CDS

  16877   Thu May 26 19:55:43 2022 yutaConfigurationBHDOplevs centered, BHD DCPDs are now online

[Paco, Yuta]

We have aligned the IFO (except for LO-AS and GRY), and centered all the oplevs.
We have also restored Gautam's in-air BHD DCPD setup and placed it to ITMY table.
BHD DC PD signals are now online at C1:XO4-MADC1_EPICS_CH4 and CH5. 

Oplevs:
 Aligned the IFO following the steps in elog 40m/16875.
 When we were woking on BHD DCPDs, we lost REFL beam on camera and both arms flashing. Alignment was restored mostly with TT2 pitch.
 We centered all the oplevs after the recovery (see attached).

BHD DCPDs:
 1. We removed a circuit box with M2 ISS photodetector readout board from AP table, in-air BHD photodiodes from optics graveyard. (see LIGO-E2000436 and elog 40m/15493 for wiring diagram)
 2. Taken out temporary two Thorlabs PDA100A used for aligning LO-AS during the vent from ITMY table, and placed the BHD setup in ITMY table (see attached and attached).
 3. DB9 cable (15ft+10ft) was connected from M2 ISS box to anti-aliasing chassis for ADC1 of C1X04 at 1Y2 rack (see attached).
 4. +/-18V power for M2 ISS box was supplied from 1Y1 rack.
 5. BHD DCPD signals are now available at C1:XO4-MADC1_EPICS_CH4 and CH5 (see attached).

Next:
 - Tweak alignment of green Y input to follow Yarm
 - Do LO-AS alignment
 - Centering of PDs everywhere with IFO aligned
 - Update RTS model for BHD

  16880   Fri May 27 17:45:53 2022 yutaConfigurationBHDBHD camera installed, GRY aligned

[JC, Paco, Yuta]

After the IFO recovery (elog 40m/16881), we installed an analog camera for BHD fringe using a BNC cable for old SRMF camera so that we can see it from the control room.
We also aligned AS-LO using LO1,LO2 and AS4.
We then aligned GRY injection to get maximum GTRY.

Maximum TEM00s right now are
 C1:SUS-ETMX_TRX_OUT_DQ ~0.1
 C1:SUS-ETMY_TRY_OUT_DQ ~0.05
 C1:ALS-TRX_OUT_DQ ~0.20
 C1:ALS-TRY_OUT_DQ ~0.18

  16886   Thu Jun 2 20:05:37 2022 yutaConfigurationPSLIMC input power recovered to 1W, some alignment works

[Paco, Yuta]

We have increased the output power from the PSL table to 951 mW (it was 96.7 mW).
IMC was recovered including WFS, and both arms are flashing nicely in IR.
We tweaked the alignment of GRX and GRY injection to align them with IR, but it was hard.
Right now IR beams are not centered on TMs. We should center them first.

What we did:
Power increase and IMC recovery
 - Replaced a beam splitter which splits the beam into IMC REFL RF PD path and WFS path from R=98% to R=10% one. Reflection goes to RF PD.
 - Put a R=98% beam splitter back into WFS path.
 - We also tried to put a window in front of IMC REFL camera to recover the arrangement in 40m wiki, but the beam reflected from the window was too weak for us to align. So, we decided not to place a window in front of the camera.
 - Attached photos are the IMC REFL path before and after the work.
 - Measured the PSL output power as Koji did in elog 40m/16672. It was measured to be 96.7+/- 0.5 mW.
 - Rotated the HWP using the Universal Motion Controller (it was not possible for us to do it from the MEDM screen). The position was changed from 73.99 deg to 36.99 deg. Output power was measured to be 951 +/- 1 mW
 - IMC locked without any other changes.
 - Changed C1:IOO-WFS_TRIGGER_THRESH_ON to 5000 (was 500). IMC WFS also worked.
 - After running MC WFS relief script, WFS DC offsets and RF offsets are adjusted following the steps in elog 40m/16835. Below are the results.

C1:IOO-WFS1_SEG1_DC.AOFF => -0.0008882080010759334
C1:IOO-WFS1_SEG2_DC.AOFF => -0.0006527877490346629
C1:IOO-WFS1_SEG3_DC.AOFF => -0.0005847311617496113
C1:IOO-WFS1_SEG4_DC.AOFF => -0.0010395992663688955
C1:IOO-WFS2_SEG1_DC.AOFF => -0.0025944841559976334
C1:IOO-WFS2_SEG2_DC.AOFF => -0.003191715502180159
C1:IOO-WFS2_SEG3_DC.AOFF => -0.0036688060499727726
C1:IOO-WFS2_SEG4_DC.AOFF => -0.004011172490815322


IOO-WFS1_I1         :  +1977.7 ->    +2250 (Significant change)
IOO-WFS1_I2         :  +3785.8 ->  +3973.2
IOO-WFS1_I3         :  +2014.2 ->  +2277.7 (Significant change)
IOO-WFS1_I4         :  -208.83 ->  +430.96 (Significant change)
IOO-WFS1_Q1         :  +2379.5 ->  +1517.4 (Significant change)
IOO-WFS1_Q2         :  +2260.4 ->  +2172.6
IOO-WFS1_Q3         :  +588.86 ->  +978.98 (Significant change)
IOO-WFS1_Q4         :  +1654.8 ->  +195.38 (Significant change)
IOO-WFS2_I1         :  -1619.9 ->  -534.25 (Significant change)
IOO-WFS2_I2         :  +1610.4 ->  +1619.8
IOO-WFS2_I3         :  +1919.6 ->  +2179.8 (Significant change)
IOO-WFS2_I4         :    +1557 ->  +1426.6
IOO-WFS2_Q1         :   -62.58 ->  +345.56 (Significant change)
IOO-WFS2_Q2         :  +777.01 ->  +805.41
IOO-WFS2_Q3         :  -6183.6 ->  -5365.8 (Significant change)
IOO-WFS2_Q4         :  +4457.2 ->  +4397.


IFO Alignment
 - Aligned both arms using IR. Both arm flashes at the following, which is consistent with the power increase.
 C1:SUS-ETMX_TRX_OUT_DQ ~1.1
 C1:SUS-ETMY_TRY_OUT_DQ ~0.6
 - With this, we tried to tweak GRX and GRY injection. The following is after the work. We could increase GTRX to 0.204 when the Xarm is aligned to green. This suggests that GRX injection is not aligned nicely yet. But the beams are also not centered on TMs. We should center them first.
 C1:ALS-TRX_OUT_DQ ~0.13
 C1:ALS-TRY_OUT_DQ ~0.07
 - GTRX and GTRY cameras are adjusted to have nicer images. In GRX path, the second and last lens before the PD and CCD was pulled ~ 1 cm behind its original position and both beams realigned. Then, on GRY path, the beam was re-centered on the first and only lens, the whole assembly pushed forward by ~ 2 cm and the beams re-centered.

Next:
 - Center the IR beam on TMs (first by our eyeballs; better to use A2L after arm locking is recovered and coils are balanced)
 - Tweak GRX and GRY injection (restore GRY PZTs?)
 - Install ETMXT camera (if it is easy)
 - Lock Xarm and Yarm (C1:LSC-TRX/Y_OUT needs to be fixed for triggering. Can we use other PDs for triggering?)
 - MICH locking (REFL and AS PDs might need to be re-aligned; they are not receiving much light)
 - RTS model for BHD needs to be updated

  16887   Fri Jun 3 12:13:58 2022 PacoConfigurationCDSFix RFM channels

[Paco, Yuta]

We tried fixing the issue of LSC_TRY and LSC_TRX channels not working. We first did some investigation, and just like previously reported by Chris, narrowed down the issue to the RFM channels coming from c1iscex/c1iscey.

First attempt : FAIL

In our first attempt, we

  1. Tripped ETMX/ETMY watchdogs, ssh to c1iscex/c1iscey and restart the rtcds models.
  2. Since the last step didn't fix things, we decided to do the same thing on c1lsc, c1sus, c1ioo.
  3. After hard rebooting c1ioo and c1lsc (because they died during the stopping of rtcds models), and not experiencing any timing issues (nice), we still don't fix the issue.

Second attempt: Success

A second attempt just followed Koji's previous fix explained here. Basic difference with our first attempt was a hard reboot of c1iscex/c1iscey in addition to the rtcds model restarting. RFM channels were then clear of errors and we recovered our IR transmission channels in the LSC model.

  16893   Mon Jun 6 16:09:23 2022 ranaConfigurationDetCharSummary Pages: seis BLRMS

I updated the config file c1pem.ini in /users/public_html/detcharsummary/ConfigFiles, and commited it so I hope it works, but I did not have git push permissions. Does anyone know what is the idea here? Should we do our own personal git clone and modify that way or shoudl we do it with the control account.

Wiki needs to clear out all the outdated information on this workflow.

The changes are to make the y-scales useful. Currently, all of the past seis BLRMS plots are not so useful because the scales have not been set based on the actual signal levels. Let's see if this works, and we  can re-evaluate after a few weeks.

  16924   Thu Jun 16 18:23:15 2022 PacoConfigurationBHDRecovering LO beam in BHD DCPDs

[Paco, Yuta]

We recovered the LO beam on the BHD port. To do this, we first tried reverting to a previously "good" alignment but couldn't see LO beam hit the sensor. Then we checked the ITMY table and couldn't see LO beam either, even though the AS beam was coming out fine. The misalignment is likely due to recent changes in both injection alignment on TT1, TT2, PR2, PR3, as well as ITMX, ITMY. We remembered that LO path is quite constrained in the YAW direction, so we started a random search by steering LO1 YAW around by ~ 1000 counts in the negative direction at which point we saw the beam come out of the ITMY chamber yes


We proceeded to walk the LO1-LO2 in PIT mostly to try and offload the huge alignment offset from LO2 to LO1 but this resulted in the LO beam disappearing or become dimmer (from some clipping somewhere). This is WiP and we shall continue this alignment offload task at least tomorrow, but if we can't offload significantly we will have to move forward with this alignment. Attachment #1 shows the end result of today's alignment.

  16932   Tue Jun 21 14:17:50 2022 yutaConfigurationBHDBHD DCPDs re-routed to c1sus2

After discussing with Anchal, we decided to route BHD related PD signals directly to ADC of c1sus2, which handles our new suspensions including LO1, LO2, AS1, AS4, so that we can control them directly.
BHD related PD signals will be sent to c1lsc for DARM control.

Re-cabling was done, and now they are online at C1:X07-MADC1_EPICS_CH16 (DC PD A) and CH17 (DC PD B) with 15ft DB9 cable.
Here, DC PD A is the transmission of BHD BS for AS beam, and DC PD B is the reflection of BHD BS for AS beam (see attached photo).

  50   Thu Nov 1 19:53:02 2007 Andrey RodionovBureaucracyPhotosTobin's picture
  51   Thu Nov 1 19:53:34 2007 Andrey RodionovBureaucracyPhotosRobert's photo
  52   Thu Nov 1 19:54:22 2007 Andrey RodionovBureaucracyPhotosRana's photo
  53   Thu Nov 1 19:55:03 2007 Andrey RodionovBureaucracyPhotosAndrey's photo
  54   Thu Nov 1 19:55:59 2007 Andrey RodionovBureaucracyPhotosAndrey, Tobin, Robert - photo
  55   Thu Nov 1 19:58:07 2007 Andrey RodionovBureaucracyPhotosSteve and Tobin's picture
  57   Fri Nov 2 08:59:30 2007 steveBureaucracySAFETYthe laser is ON
The psl laser is back on !
  75   Wed Nov 7 02:14:08 2007 AndreyBureaucracyIOOMore information about MC2 ringdown
As Tobin wrote two hours ago, we (Andrey, Tobin, Robert) made a series of ringdown measurements for MC2
in the spirit of the measurement described by Rana -> see
entry from Mon Oct 29 23:47:29 2007, rana, Other, IOO, MC Ringdowns.

I attach here some pictures that we saw on the screen of the scope, but I need to admit that I am not experienced enough to present a nice fit to these data, although I attach fits that I am able to do today.

I definitely learned a lot of new Matlab functions from Tobin - thanks to him!, but I need to learn two more things:

Firstly, I do not know how to delete "flat" region (regions before the ringdown starts) in Matlab ->
I needed to delete the entries for times before the ringdown ("negative times") by hand in the text-file, which is extremely non-elegant method;

Secondly, I tried to approximate the ringdown curve by a function ydata=a*exp(b*xdata) but I am not exactly sure if this equation of the fitting curve is a good fit or if a better equation can be used.

It seems, in this situation it is better for me to ask more experienced "comrades" on November 7th.

P.S. It seems I really like the type of message "Bureaucracy" - I put it for every message. As Alain noted, maybe that is because some things are very bureacratized in the former USSR / Russia. By the way, when I was young, November 7th was one of two most important holidays in the USSR - I liked that holiday because I really liked military parades on the red square. I attach a couple of pictures. November 7 is the anniversary of the Revolution of 1917.
  113   Fri Nov 16 18:46:49 2007 steveBureaucracyPSL MOPA was turned off & on
The "Mohana" boys scouts and their parents visited the 40m lab today.
The laser was turned off for their safety.
It is back on !
  115   Mon Nov 19 14:32:10 2007 steveBureaucracySAFETYgrad student safety training
John Miller and Alberto Stochino has received the 40m safety bible.
They still have to read the laser operation manual and sign off on it.
  130   Wed Nov 28 12:43:53 2007 AndreyBureaucracy Here was the PDF-file of my presentation

I was making a report with powerpoint presentation during that Wednesday's 40-m meeting.

Here was the pdf-file, but LATER IN THE EVENING I CREATED A WIKI-40M-page describing the algorithm, and now the pdf-file is ON THAT WIKI-40M PAGE.


NOTE ADDED AFTER THE PRESENTATION: I double checked, I am indeed taking the root-mean-square of a difference, as we discussed during my talk.

My slide #17 "Calculation of differential length" was wrong, but now I corrected it.
  135   Wed Nov 28 19:02:41 2007 AndreyBureaucracyWIKI-40M UpdateNew WIKI-40M page describing Matlab Suspension Modeling

I created the WIKI-40m page with some details about my today's talk on the 40-m lab meeting.

The address is:

http://lhocds.ligo-wa.caltech.edu:8000/40m/Modeling_of_suspensions

(or you can go to the main page, http://lhocds.ligo-wa.caltech.edu:8000/40m/ , and click on the link "Modeling of suspensions").

The WIKI-40m page describes my transfer functions and contains the pdf-file of my presentation.
  224   Thu Jan 3 12:38:49 2008 robBureaucracyTMISore throat

Quote:

I did not feel anything wrong yesterday, but unfortunately I have a very much sore throat today. I need to drink warm milk with honey and rinse my throat often today. So far I do not have other illness symptomes (no fever), so I hope that this small disease will not last for a long time, but I feel that it is better for me to cure my sore throat today at home (and probably it is safer for others in 40-m).

I took yesterday the book "Digital Signal Processing", so I have it for reading at home.

Hope to see you tomorrow.


I've added a new category--TMI--for entries along these lines.
  262   Thu Jan 24 22:52:18 2008 AndreyBureaucracyGeneralAnts around a dirty glass (David - please read!)

Dear coleagues,

there are rains outside these days, so ants tend to go inside our premises.

David was drinking some beverage from a glass earlier today (at 2PM) and left a dirty glass near the computer.

There are dozens, if not hundreds, of ants inside of that glass now.

Of course, I am washing this glass.

A.
  279   Mon Jan 28 12:42:48 2008 DmassBureaucracyTMICoffee
There is tea in the coffee carafe @ the 40m. It is sitting as though it were fresh coffee. There is also nothing on the post it.
  339   Fri Feb 22 21:19:38 2008 AndreyBureaucracyComputer Scripts / ProgramsMDV library does not work at "LINUX 2"

While working on Thursday evening with Matlab scripts "dttfft2" and "get_data", I noticed that mDV library does not work at computer "LINUX 2" (the third computer in the control-room if you enter it from the restroom). There are multiple error messages if we try to run "hello_world", "dttfft2" or "get_data". In order to take data from accelerometers, I changed the computer - I was working from "LINUX 3" computer, the most right computer in the control room, but for the future someone should resolve the issue at "LINUX 2". I am not experienced enough to revive the correct work of mDV directory at "LINUX 2".

Andrey.
  343   Thu Feb 28 12:31:33 2008 robBureaucracyComputer Scripts / ProgramsMDV library does not work at "LINUX 2"

Quote:

While working on Thursday evening with Matlab scripts "dttfft2" and "get_data", I noticed that mDV library does not work at computer "LINUX 2" (the third computer in the control-room if you enter it from the restroom). There are multiple error messages if we try to run "hello_world", "dttfft2" or "get_data". In order to take data from accelerometers, I changed the computer - I was working from "LINUX 3" computer, the most right computer in the control room, but for the future someone should resolve the issue at "LINUX 2". I am not experienced enough to revive the correct work of mDV directory at "LINUX 2".

Andrey.


This turned out to be due to /frames not being mounted on linux2, as a result of a reboot. The issue is discussed in entry 270. I remounted the /frames, and added a line to mdv_config.m to check whether the frames are mounted.
  382   Fri Mar 14 16:56:03 2008 DmassBureaucracyComputersNew 40m control machine.
I priced out a new control machine from Dell and had Steve buy it.

GigE cards (jumbo packet capable) will be coming seperately.

Specs:
Quad core (2+GHz)
4 Gigs @ 800MHz RAM
24" LCD
low end video card (Nvidia 8300 - analog + digital output for dual head config)

No floppy drive on this one (yet?)
  488   Tue May 20 09:28:42 2008 steveBureaucracySAFETYsafety traning for 40m
Tara Chalernsongsak, new gradstudent for K. Libbrecht was introduced to the basics of the 40m operations.
  491   Thu May 22 11:21:45 2008 steveBureaucracySAFETYearly surf sudent
Caltech under grad Eric Mintun received the 40m safety training.
Now he has to read and sign SOP of laser and ifo.
He'll be working with GigE cameras with Joe
  505   Thu May 29 16:49:49 2008 steveBureaucracyPhotosYoichi has arrived
Yoichi had his first 40m meeting. We welcomed him and Tobin, who is visiting, by sugar napoleons that
Bob made.
  511   Mon Jun 2 12:20:35 2008 josephbBureaucracyCamerasBeam scan has moved
The beamscan has been moved from the Rana lab back over to the 40m, to be used to calibrate the Prosilica cameras.
  523   Fri Jun 6 15:56:00 2008 steveBureaucracySAFETYYoichi received safety training
Yoichi Aso received 40m specific safety training.
  552   Mon Jun 23 15:22:04 2008 ranaBureaucracySAFETYLaser Safety Walkthrough today
  708   Mon Jul 21 15:52:22 2008 steveBureaucracySAFETYfire alarms test
The fire alarm test and evacuation drill was successfully completed at 13:45 Wednesday, July 16, 2008

Everybody was on time for the 40m meeting.