  14158   Mon Aug 13 17:20:07 2018 aaronConfigurationUpgradeParts list for BHDI've attached the diagram of what I
mean.

There are a couple caveats and
 BHD_layout.pdf 
  14311   Tue Nov 20 17:38:13 2018 ranaUpdateUpgradeNew Coffee MachineRana, Aaron, Gautam

The
  
  14327   Sun Dec 2 16:08:44 2018 JonOmnistructureUpgradeFeedthroughs for Vacuum Acromag ChassisBelow is an inventory of the signal
feedthroughs that need to be installed on
the vacuum Acromag crate this week.
  
  14330   Tue Dec 4 10:38:12 2018 JonOmnistructureUpgradeUpdated Feedthrough List for Vacuum Acromag ChassisBased on new input from Chub, attached
is the revised list of signal cable
feedthroughs needed on the vacuum system
 acromag_chassis_feedthroughs.pdf 
  14348   Wed Dec 12 18:27:07 2018 JonOmnistructureUpgradeAnalog signals, A/D Acromag added to vacuum systemThere turned out to be a few analog signals
for the vacuum system after all. The TP2/3
foreline pressure gauges were never part
  
  14375   Thu Dec 20 21:29:41 2018 JonOmnistructureUpgradeVacuum Controls Switchover Completed[Jon, Chub, Koji, Gautam]

Summary

Today we carried
out the first pumpdown with the new vacuum
 40m_vacuum_acromag_channels.pdf 
  14384   Fri Jan 4 11:06:16 2019 JonOmnistructureUpgradeVac System PunchlistThe base Acromag vacuum system is running
and performing nicely. Here is a list of
remaining questions and to-do items we still
  
  14390   Tue Jan 8 19:13:39 2019 JonUpdateUpgradeReady for pumpdown tomorrowEverything is set for a second pumpdown
tomorrow. We'll plan to start pumping
after the 1pm meeting. Since the main volume
  
  14493   Thu Mar 21 18:36:59 2019 JonOmnistructureUpgradeVacuum Controls Switchover CompletedUpdated vac channel list is attached. There
are several new ADC channels.

 40m_Vacuum_Acromag_Channels_20190321.pdf 
  14495   Mon Mar 25 10:21:05 2019 JonUpdateUpgradec1susaux upgrade planNow that the Acromag upgrade of c1vac is
complete, the next system to be upgraded
will be c1susaux. We chose c1susaux because
 IMG_3136.jpgIMG_3138.jpgIMG_3137.jpg 
  14496   Tue Mar 26 04:25:13 2019 JohannesUpdateUpgradec1susaux upgrade plan


Quote:


  
  14497   Tue Mar 26 18:35:06 2019 JonUpdateUpgradeModbus IOC is running on c1susaux2Thanks to new
info from Johannes, I was able to finish
setting up the modbus IOC on c1susaux2.
  
  14500   Fri Mar 29 11:43:15 2019 JonUpdateUpgradeFound c1susaux database bugI found the current bias output channels,
C1:SUS-<OPTIC>_<DOF>BiasAdj,
were all pointed at C1:SUS-<OPTIC>_
  
  14590   Thu May 2 15:35:54 2019 JonOmnistructureUpgradec1susaux upgrade documentationFor future reference:


The updated list
of c1susaux channel wiring (includes the
  
  16942   Thu Jun 23 15:05:01 2022 Water MonitorUpdateUpgradeWater Bottle Refill22:05:02 UTC Jordan refilled his water
bottle at the water dispenser in the control
room.
  
  23   Mon Oct 29 09:16:31 2007 steveRoutineVACthe rga is backWe had no filament current since last power
glitch of Oct. 8, 2007
First I thought that the filament was lost,
 rgaisback.jpg 
  24   Mon Oct 29 09:46:50 2007 steveRoutineVACvac & pem trendPumpdown 64 pumped by maglev for 125 days
pd64-m-d125
 pd64md125.jpg 
  38   Wed Oct 31 10:31:23 2007 Andrey RodionovRoutineVACVenting is in progress
We (Steve, David, Andrey) started venting
the vacuum system at 9.50AM Wednesday morning.
  
  44   Thu Nov 1 09:17:27 2007 steveRoutineVACvent 64Yesterday before vent I could not lock  MC,
therfore I could not measure the 
transmitted power at MC2 
 vent64.jpg 
  64   Mon Nov 5 22:24:38 2007 Andrey, SteveOmnistructureVACPumping down goes smoothly
We (Steve and Andrey) started pumping down
at 3.25PM today. At 9 PM we turned off the
  
  65   Tue Nov 6 09:14:37 2007 steveSummaryVACpump down 658 hr plot,
precondition: 5 days at atm,
vent objective: drag wiping mc1, mc2 & mc3
 pd65.jpg 
  76   Wed Nov 7 09:38:01 2007 steveUpdateVACrga scanpd65-m-d2 at cc1 6e-6 torr  pd65d2.jpg 
  129   Wed Nov 28 08:47:29 2007 steveOmnistructureVACrga is out of orderThe rga is not working since Nov 10
The controller is broken.
pd65-m-d23
 pd65d23.jpg 
  139   Thu Nov 29 11:10:54 2007 robOmnistructureVACRGAlogger sleepingWithout the RGA controller responding, the
RGAlogger script just hangs.  Rather than
fix it, I just put it to sleep by commenting
  
  310   Tue Feb 12 13:53:27 2008 robOmnistructureVACReturn of the RGA
The new RGA head was installed a few days
ago.  I just ran the [B]RGAlogger[/B] script
 RGA-080212.png 
  322   Tue Feb 19 10:14:13 2008 steveUpdateVACrga logging needs helpThe rga head and controller are running fine,
but the data logging is not.
  
  344   Thu Feb 28 13:04:59 2008 robUpdateVACrga logging working again[quote]The rga head and controller are running
fine, but the data logging is not.[/quote]
  
  351   Mon Mar 3 09:25:33 2008 steveUpdateVACrga scan logging is working now[quote][quote]The rga head and controller
are running fine, but the data logging is
not.[/quote]
 rgalogworks.jpgcc1.jpg 
  385   Thu Mar 20 15:28:20 2008 steveUpdateVACtp2 's drypump replacedThe fore pump of tp2 was replaced at fore
line pressure 998m Torr
  
  388   Fri Mar 21 09:02:03 2008 steveUpdateVACtp 2 failedSmall turbo #2 is the forepump of the maglev.
It failed last night, shut down the  maglev
and interlock closed V1
  
  389   Fri Mar 21 11:54:38 2008 robUpdateVACtp 2 failed[quote]Small turbo #2 is the forepump of the
maglev.
It failed last night, shut down the  maglev
  
  423   Thu Apr 17 15:00:59 2008 steveUpdateVACvac controller computer to be replacedNow that Rosalba is up and running someone
should step forward to volunteer for this
job.
  
  465   Mon May 5 15:53:14 2008 steveUpdateVACdrypump replaced & readbacks are outThe small turbo pump of the annulus system
is tp3
It's drypump was replaced at 1.4 Torr after
  
  790   Mon Aug 4 12:12:20 2008 steveConfigurationVACthe ifo is at atmThe 40m vac envelope was vented this morning.
P1 is at 760 Torr
 vent3h.jpgUntitled.png 
  843   Fri Aug 15 19:32:49 2008 steveConfigurationVACpumpdown completeI have just reached vacuum normal. The maglev
peaked at 49.8C body temp with aux fan on
at 3.2 Torr
 pdprm.jpg 
  845   Mon Aug 18 09:19:55 2008 steveSummaryVAC11 days at atmIt took 11 days to fix earth quake triggered
sus problems of ITMX, SRM and PRM
Only ITMX north and BSC north vac doors were
 ventprm.jpg 
  887   Tue Aug 26 15:06:16 2008 steveConfigurationVACrga scanPumpdown 66 PRM-maglev vac normal -day 11
short form: pd66PRM-m-d11
 RGA-0808260125.png 
  1071   Thu Oct 23 11:26:25 2008 steveBureaucracyVACoptosigma forks for vacuumNine short forks from OptoSigma were cleaned,
baked and measured by Bob T.
They passed the LIGO vac compatiblity test
  
  1085   Fri Oct 24 15:05:13 2008 steveUpdateVACrga is out of orderThe old Dycor  RGA is out of order.
I'm getting ready to purchase an SRS instrument.
  
  1134   Fri Nov 14 11:33:19 2008 steveUpdateVACSRS-RGA installedOld Dycor rga is removed and new SRS-RGA200
installed.
It is pumped down and ready for hooking up
  
  1186   Mon Dec 8 11:41:27 2008 YoichiSummaryVACThe rough pump for the TP2 replacedBob, Yoichi

The foreline pressure of the TP2 (the foreline
  
  1212   Thu Jan 1 01:15:45 2009 YoichiSummaryVACN2 line leak ?I've been replacing the N2 bottles recently.
I noticed that the consumption is too high.
I had to replace them every two days.
  
  1220   Fri Jan 9 16:52:18 2009 steveUpdateVACtp3 forline pump replacedAlberto took 40m vacuum 101 class as we replaced
the drypump at the annulus pump line.
  
  1226   Wed Jan 14 09:22:43 2009 steveHowToVACN2 supply pressure lowered for vac valves[quote]I've been replacing the N2 bottles
recently.
I noticed that the consumption is too high.
 n280d.jpg 
  1227   Wed Jan 14 10:59:06 2009 steveBureaucracyVACrga waiting to be "connected"We have no RGA data since old Dycor passed
away in the middle of Oct, 2008
New SRS-RGA200 was installed on the vac envelope
  
  1253   Mon Jan 26 14:51:54 2009 josephbConfigurationVAC We need a new RS-232 to Ethernet bridge in
order to interface properly with the new
RGA.  The RGA has a fixed baud rate of 28.8k,
  
  1448   Wed Apr 1 10:22:13 2009 steveUpdateVACRGA logging is workingThanks to Joe B who made the SRS RGA working
with linux
Last data file logged at 2008 Oct
 rga-090401.png 
  1452   Fri Apr 3 10:01:50 2009 steveUpdateVACrgascan with temp plotRga scan of day 231 since pumpdown pd66-m-d231
m stands for maglev pumping speed,
vacuum normal condition of valves,
 pd66tempow.jpgrga-090403scan.png 
  1459   Wed Apr 8 09:36:20 2009 steveConfigurationVAC valve condition changed to BG to calibrate the RGAVacuum
normal valve condition was changed to accommodate
SRS-RGA calibration.
  
  1462   Thu Apr 9 11:27:19 2009 steveUpdateVACvac gauge reading problemCold cathode gauge CC4  is reading
normal.
CC1 is glitching, it is probably
 vacgflsec.jpgvacgflmin.jpg 