    Reply  Fri Nov 5 12:49:32 2021, rana, Update, SUS, Setting up suspension test model 
Please don't put it on c1sus2. Put it on the completely independent test stand as we discussed Wednesday. You must test the controller on
the simplant and verify that they thing is stable and works, before putting it in the 40m network.
Entry  Fri Nov 5 20:35:10 2021, Koji, Update, BHD, Feedthru / Optical Mounts P_20211105_200817.jpg
- New feedthrus [4xDB25 Qty 4 / 8xDB25 Qty 1] are placed on the wire shelf at the entrance -> Jordan, please clean them.

- There are plenty of 2" DLC mounts. There are also many 1.5" mounts but they are less useful.
  We need at least 3 1" moounts and 1 1" or 2" lens mount (and the lens). Let's purchase them on Thorlabs. I'll work
    Reply  Mon Nov 8 17:22:27 2021, Yehonathan, Update, BHD, SOS assembly Magnets_Positions.pngAdapters_Order.png
Big Gluing Day

Today I glued the magnet+dumbell assemblies on the optics adapters.

Unlike magnet gluing on a 3" optic where one can use a magnet gluing fixture, here I had to position the magnets manually. There is a complication
    Reply  Mon Nov 8 17:52:22 2021, Ian MacMillan, Update, SUS, Setting up suspension test model x1sus_cp.png
[Ian, Tega]

We combined a controler and a plant model into a single modle (See first attachment) called x1sus_cp.mdl in the userapps folder
of the cymac in c1sim. This model combines 2 blocks: the controler block which is used to control the current optics and is found
    Reply  Tue Nov 9 11:11:37 2021, Yehonathan, Update, BHD, SOS assembly 20211109_110408.jpg
The gluing was mostly successful. Only two magnets didn't stick (see attachment).
    Reply  Fri Nov 12 23:47:29 2021, Yehonathan, Update, BHD, SOS assembly 
{Tega, Yehonathan}

First attempt at the suspension of a Lambda Optic mirror

We found the box with the 2" Lambda Optic mirrors in the cleanroom. We choose to suspend a mirror with a ROC = 5m, probably LO1.
    Reply  Tue Nov 16 17:42:46 2021, Yehonathan, Update, BHD, SOS assembly 20211115_170320_HDR.jpg20211116_163846.jpgmagnet_height_check(1).pngside_blcok_touching_1.pngside_blcok_touching_2.png
{Tega, Yehonathan}

Another attempt at the suspension of a Lambda Optic mirror

The lambda mirror was removed from the adapter whose magnets were knocked off. We tried to mount the mirror on a different adapter but we knocked
    Reply  Tue Nov 16 18:28:53 2021, Koji, Update, BHD, SOS assembly D2100546_Wire_Block.pdfD2100546_Wire_Block.png
Yehonathan told me that the wires are touching between the clamps! I went back to the CAD and confirmed
it is really happening. Sad.

The distance of the wires at the upper clamp is 17.018mm.
    Reply  Wed Nov 17 07:32:48 2021, Chub, Update, General, wire clamp plate mod 
This will be difficult to modify with the magnets and dumbells in place.  Even if someone CAN clamp this piece into an endmill machine with the
magnets/dumbells in place, the vibration of the cutting operation may be enough to break them off.
    Reply  Wed Nov 17 11:53:27 2021, Koji, Update, General, wire clamp plate mod 
Of course, we remove the magnet-dumbbell for machining. After that the part will be cleaned/baked again. And Yehonathan is going to glue the magnet-dumbbell
again.
    Reply  Wed Nov 17 17:37:53 2021, Anchal, Update, General, Placed Nodus and fb1 on UPS power 
Today I placed nodus and fb1 on UPS battery backed supply. Now power glitches should not hurt our cds system.
    Reply  Thu Nov 18 15:16:10 2021, Anchal, Update, General, Moved Chiara to 1X7 above nodus powered with same UPS 
[Anchal, Paco]

We moved chiara to 1X7 above nodus and powered with same UPS from a battery backed port. The UPS is at 40% load capacity. The nameserver and
nfs came back online automatically on boot up.
    Reply  Mon Nov 22 17:42:19 2021, Anchal, Update, General, Connected Megatron to battery backed ports of another UPS 
[Anchal, Paco]

I used the UPS that was providing battery backup for chiara earlier (a APS Back-UPS Pro 1000), to provide battery backup to Megatron. This completes
UPS backup to all important computers in the lab. Note that this UPS nominally consumes 36% of UPS capacity in power delivery but at start-up, Megatron
Entry  Tue Nov 23 18:02:05 2021, Anchal, Update, IMC, MC autolocker shifted to python3 script running in docker 
I finished copying over the current autolocker bash script functionality into a python script
which runs using a simple configuration yaml file. To run this script, one
needs to ssh into optimus and :
    Reply  Wed Nov 24 14:15:15 2021, Yehonathan, Update, BHD, SOS assembly 
Late update. We got 2 modified side blocks from Jordan a few days ago. Yesterday, I glued a side magnet to one of the modified side blocks.

I took the opportunity to reglue some magnets that were knocked off from the adapters. I did this for 2 adapters only since w need 4 shallow
adapters and we already had 2 complete ones.
Entry  Wed Nov 24 14:34:15 2021, Yehonathan, Update, BHD, Saving on SUSAUX slow channels 
Koji found out that the stock for BIO Acromag modules is very low and that the lead time for ordering new ones is ~ 1-year X-o.

We figure we might need to minimize the number of modules but still keep the Acromag chassis functional.

 
    Reply  Tue Nov 30 17:11:06 2021, Paco, Update, General, Moved white rack to 1X3.5 IMG_8749.JPGIMG_8750.JPG
[Paco, Ian, Tega]

We moved the white rack (formerly unused along the YARM) to a position between 1X3, and 1X4. For this task we temporarily removed the hepas near
the enclosures, but have since restored them.
    Reply  Wed Dec 1 12:57:08 2021, Yehonathan, Update, BHD, SOS assembly 7x
{Yehonathan, Tega}

We glued some magnets onto modified side blocks. We followed pretty much the same procedure form last time. The music wires were clamped on the
side blocks away from the optic adapter. The clamps were screwed down using the low profile screws the Jordan obtained from UC components to allow maximum
Entry  Mon Dec 6 14:26:52 2021, Koji, Update, VAC, Pumping down the RGA section 
Jordan reported that the RGA section needs to be pumped down to allow the analyzer to run at sufficiently low pressure (P<1e-4 torr).
The RGA section was pumped down with the TP2/TP3. The procedure is as listed below.
If the pressure go up to P>1e-4 torr, we need to keep the pump running until the scan is ready.
    Reply  Mon Dec 6 18:23:04 2021, Yehonathan, Update, BHD, SOS assembly signal-2021-12-06-165751_001.jpeg
I installed OSEMs on the LO1 SOS. To my surprise, the side magnet is not in the center of the side OSEM. It completely misses the LED as can be seen
in the attachment.

Looking at the CAD model, it turns out the position of the OSEM on the left side plate is different from the position of the OSEM on the right
    Reply  Tue Dec 7 13:12:50 2021, Koji, Update, VAC, Pumping down the RGA section 
So that Jordan can run the RGA scan this afternoon, I ran TP3 and started pumping down the RGA section.

Procedure:
- Same 1~4
    Reply  Wed Dec 8 10:14:43 2021, Jordan, Update, VAC, Pumping down the RGA section 40m_RGAVolume_12_8_21.PNG40m_RGAVolume_Torr_12_8_21.PNG
After an overnight pumpdown/RGA warm up, I took a 100 amu scan of the RGA volume and subsequent pumping line. Attached is a screenshot along with the
.txt file. Given the high argon peak (40) and the N2/O2 ratio, it looks like there is a decent sized air leak somehwere in the volume.

Are we interested in the hydrocarbon leak rates of this volume? That will require another scan with one of the calibrated leaks opened.
Entry  Thu Dec 9 00:32:56 2021, Tega, Update, CDS, New SUS medm screen update Screen_Shot_2021-12-09_at_12.29.30_AM.pngScreen_Shot_2021-12-09_at_12.42.35_AM.png
The new SUS screen can be reached via sitemap -> IFO SUS button -> NEW ETMX dropdown menu link. Please use and provide feedback. Not
sure exactly if we need/want the display screens after the IOP model on the right of the medm screen. I have not been able to locate the corresponding
channels but did not want to remove them until I was sure that we don't plan to add these features to our screens. When all bugs have been ironed
    Reply  Thu Dec 9 18:22:36 2021, Tega, Update, CDS, New SUS medm screen update Screen_Shot_2021-12-09_at_6.21.09_PM.png
Work on the medm screen for SUS RMS monitor is ongoing. The next step would be to incorporate this into the SUS medm screen, add
the BLRMS model to the SUS controller model, recompile, check that the channels are being correctly addressed, then load the appropriate bandpass and
lowpass filters.  
    Reply  Thu Dec 9 21:57:35 2021, Yehonathan, Update, BHD, SOS assembly balancingsos2.pngFreeSwingingSpectra.pdf
{Yehonathan, Tega}

We took the optic out of the SOS tower and removed the side blocks. We mounted new side blocks with wires already clamped in them in the reverse
order.
Entry  Fri Dec 10 15:59:23 2021, Paco, Update, BHD, Finished Coil driver (even serial number) units tests dc_fail.jpg
[Paco, Anchal]

We have completed modifications and testing of the HAM Coil driver D1100687 units with serial numbers listed below. The DCC
tree reflects these changes and tests (Run/Acq modes transfer functions).
    Reply  Fri Dec 10 18:55:58 2021, Tega, Update, CDS, New SUS medm screen update BLRMS_ITMY_screenshot.png
Turns out the BLRMS monitoring channels for MC1, MC2, MC3, ITMY and SRM already exist in c1pem. So I modified the new SUS screen to display the BLRMS
info for the aforementioned optics. Next step is to add the BLRMS monitor for PRM, ITMX, ETMX and ETMY. This would require extending the number of inputs
for the "SUS" block in c1pem to accomodate the additional inputs from the remaining optics.
    Reply  Fri Dec 10 19:22:01 2021, Koji, Update, VAC, Pumping down the RGA section 
The scan result was ~x10 higher than the previously reported scan on 2020/9/15 (https://nodus.ligo.caltech.edu:8081/40m/15570),
which was sort of high from the reference taken on 2018/7/18.

This just could mean that the vacuum level at the RGA was x10 high.
Entry  Mon Dec 13 15:05:47 2021, Tega, Update, PEM, git repo for temp sensor and sus medm 
[temperature sensor]

git repo: https://git.ligo.org/40m/tempsensor.git

todo
    Reply  Tue Dec 14 11:33:29 2021, Tega, Update, PEM, git repo for temp sensor and sus medm 
[Temperature sensor]

Added new temp EPICs channels to database file (/cvs/cds/caltech/target/c1pem1/tempsensor/C1PEMaux.db)

Added new temp EPICs channels to slow channels ini file (/opt/rtcds/caltech/c1/chans/daq/C0EDCU.ini)
    Reply  Tue Dec 14 14:02:33 2021, Yehonathan, Update, BHD, SOS assembly magnetcentring.pngFreeSwingingSpectra.pdf
{Yehonathan, Paco}

I fixed the overall height of the adapter (attachment 1). I put an OSEM next to the side magnet. I positioned a camera in front of the SOS and
connected it to my laptop for live streaming. I painted a line indicating the height of the OSEM plates and a line in between with the mean height. I discarded
Entry  Tue Dec 14 19:29:42 2021, Paco, Update, BHD, 1Y0 rack work for LO1 
[Paco]

Two coil drivers have been installed on 1Y0 (slots 6, 7, for LO1 SOS). All connections have been made from the DAC, AI board, DAC adapter, Coil
driver, Sat Amp box. Then no SOS load installed, all return connections have been made from Sat Amp box, ADC adapter, AA board, and to ADC. We will continue
Entry  Wed Dec 15 13:57:59 2021, Paco, Update, Computers, upgraded ubuntu on zita 
[Paco]

Upgraded zita's ubuntu and restarted the striptool script.
Entry  Wed Dec 15 15:06:08 2021, Jordan, Update, VAC, Vacuum Feedthru Install 
Jordan, Chub

We installed the 4x DB25 feedthru flange on the North-West port of ITMX chamber this afternoon. It is ready to go.
    Reply  Wed Dec 15 22:09:53 2021, Yehonathan, Update, BHD, SOS assembly 
{Paco, Yehonathan, Anchal}

I cut the wires from the winches and removed the winch adapter plate. I engrave  'LO1' on the SOS tower. Me and Paco wrapped the
SOS with foil and transported it to Anchal who put it inside the ITMX chamber.
    Reply  Thu Dec 16 12:21:16 2021, Anchal, Update, BHD, Coil driver test failed for S2100619-v1 D1100687_S2100619-v1_TF_CH2_Not_Matching.pdf
Today I found one of the coil driver boards, S2100619 failed the test on CH2. There appears to be an
extra phase lag after 10 kHz and some resonant-like feature at 7 kHz. This of course is very high-frequency stuff and maybe we don't care about these
deviations. But it could mean something is off with the channel and could potentially lead to failure in the relevant frequency band in the future. I'll
Entry  Thu Dec 16 15:04:12 2021, Chub, Update, Electronics, ITMX feedthroughs and in-vac cables installed ITMX_feedthrough_install_12-16-21.jpg
The ITMX 10" flange with four DSUB-25 feedthroughs has been install with the cables connected at the in-vac side.  See photo; as requested,
LO1-1 and LO1-2 are connected to the top row of feedthroughs from left to right respectively and the opposite ends of the cables placed left to right on
the laser table.  PR2-1 and PR2-2 are connected to the lower row of feedthroughs from left to right respectively, with the opposite ends placed on
    Reply  Thu Dec 16 15:32:59 2021, Anchal, Update, BHD, Finished Coil driver (odd serial number) units tests 
We have completed modifications and testing of the HAM Coil driver D1100687 units with serial numbers listed below. The DCC
tree reflects these changes and tests (Run/Acq modes transfer functions).




SERIAL #
TEST
    Reply  Thu Dec 16 15:54:08 2021, Koji, Update, Electronics, ITMX feedthroughs and in-vac cables installed PXL_20211216_235056582.jpg
Thanks for the installation.

With regard to the connector convention, let's use the attached arrangement so that it will be consistent with the existing flange DSUB configuration.
Not a big deal.
    Reply  Thu Dec 16 17:41:12 2021, Koji, Update, BHD, Coil driver test failed for S2100619-v1 6x
Good catch. It turned out that the both + and - side of the output stages for CH2 were oscillating at ~600kHz. If I use a capacitance sticks to touch
arbitrarily around the components, it stops their oscillation and they stay calm.
It means that the phase margin becomes small while the circuit starts up.
    Reply  Thu Dec 16 17:57:17 2021, Anchal, Update, BHD, Finished Coil driver (odd serial number) units tests 
S2100619 was fixed by Koji and it passed the test after that.




Quote:



    Reply  Thu Dec 16 18:16:36 2021, Yehonathan, Update, BHD, SOS assembly chippedmirror.pngIMG_6311.JPGIMG_6310.JPGIMG_6309.JPG
Today I glued magnets onto the new 3/4" mirror adapters. I also took the opportunity to make some more side magnets assemblies.

Yesterday I mounted PR3/SR2 3/4" thick mirror onto one of the new adapter. There seem to be no issues for now.

I started the process of suspending AS1 (E2000226-A). The Lambda Optic mirror with the closest
Entry  Fri Dec 17 12:32:35 2021, Koji, Update, SUS, Remaining task for 2021 
Anything else? Feel free to edit this entry.

- SUS: AS1 hanging

- SUS: PR3/SR2/LO2 3/4" thick optic hanging
    Reply  Fri Dec 17 17:50:17 2021, Yehonathan, Update, BHD, SOS assembly AS1rollbalance.pngAS1Magnet_height.pngghostbeam.pnglambdaopticarrow.jpg
I threaded a new wire through a different side block with a magnet and clamped it under a microscope. It was hard, but eventually, I was able to do it
by holding the wire on both sides of the side block with weights.

The dented wire was discarded and the side block that was mounted on the AS1 adapter was put aside. I mounted the side block with the new wire
    Reply  Fri Dec 17 19:16:45 2021, Koji, Update, BHD, SOS assembly 
We @40m do the convention of the arrow at the thinnest side & pointing the HR side, but nobody says Lambda does the same.

We can just remount the mirror without breaking the wires and adjust the pitching if you do it carefully.

Does this mean that the LO1 also likely to have the wedge pointing up? Or did you rotate the mirror to have the wedge reflection to be as horizontal
    Reply  Fri Dec 17 19:19:42 2021, Koji, Update, SUS, Remaining task for 2021 PXL_20211218_030145356.MP.jpg
I had the fear that any mistake in the electronics chain could have been the show stopper.

So I quickly checked the signal assignments for the ADC and DAC chains.

I had initial confusion (see below), but it was confirmed that the electronics chains (at least for LO1)
    Reply  Fri Dec 17 22:16:07 2021, Yehonathan, Update, BHD, SOS assembly 
I specifically checked the specification before mounting the mirror. It says clearly "Arrow at
the thinnest location pointing towards Side 1". I guess they just ignored it.

As for LO1, I mounted it without noticing the location of the arrow. Later, I checked and the ghost beam was horizontal so I left it as it is.
    Reply  Sat Dec 18 00:56:14 2021, Koji, Update, BHD, SOS assembly 
Sad... We just need to check the wedge direction everytime, unfortunately.

Pencil: can you try to gently wipe it off with solvent & a swab? (IPA / Acetone)
If it does not come off in the end, it's all right to leave. Do we want to scribe the arrow mark? You need a diamond pen.
    Reply  Sun Dec 19 07:52:51 2021, Anchal, Update, SUS, Remaining task for 2021 
The I/O chassis reassigns the ADC and DAC indices on every power cycle. When we moved it, it must have changed it from the order we had. We were aware
of this fact and decided to reconnect the I/O chassis to AA/AI to relect the correct order. We forgot to do that but this is not an error, it is expected
behavior and can be solved easily.
    Reply  Mon Dec 20 13:52:01 2021, Koji, Update, BHD, SOS assembly 
LO1: No need to remove the pencil mark for the damping test. Until we see serious contamination on the LO1 optic, we don't need
to take the optic off from the mount and clean it. If there is a chance of rehanging (because of a broken wire/etc), we do wipe the pencil mark.

Other optics: wipe the pencil mark as much as possible.