  3448   Fri Aug 20 15:49:14 2010 steveUpdatePEMgrouting is done

The preparation for pouring concrete is continuing. The grout forms were removed. Half inch ribbed steel bars were epoxied into our 4" thick floor.

The concrete holding sides- forms are cut to size. They will be installed on Monday morning and pouring concrete should follow.

We can be planning for cleaning up on Tuesday

 

Atm1, epoxy used bars

Atm2, south west tripod feet grouted

Atm3, ribbed bars are getting ready

Attachment 1: P1060699.JPG
P1060699.JPG
Attachment 2: P1060700.JPG
P1060700.JPG
Attachment 3: P1060704.JPG
P1060704.JPG
  3449   Fri Aug 20 16:17:35 2010 steveUpdatePEMPEM-count channels are not working

C1: PEM-count channels are dead since August 12, 2010

  3455   Mon Aug 23 08:28:27 2010 steveUpdateSUSETMY sus damping restored
  3462   Tue Aug 24 11:23:32 2010 steveUpdatePEMtripod leg installation completed

Bertine Robby, Bertin and Jerry completed the installation by pouring concrete yesterday and cleaning up today.

Atm1-2, steel bars, grouted feet and side forms are ready

Atm3,    bounding agent is applied for better bounding

Atm4,    pumping concrete

Atm5,    shaker is used to fill-all

Atm6,    late after noon the forms- sides were removed,     NOTE: actual table to concrete distance is 12.75"

Atm7,    construction people left and the tile man is on the way

 

The tile patching should complete today so tomorrow we can remove plastic covers.

 

Attachment 1: P1060731.JPG
P1060731.JPG
Attachment 2: P1060719.JPG
P1060719.JPG
Attachment 3: P1060736.JPG
P1060736.JPG
Attachment 4: P1060738.JPG
P1060738.JPG
Attachment 5: P1060742.JPG
P1060742.JPG
Attachment 6: P1060757.JPG
P1060757.JPG
Attachment 7: P1060755.JPG
P1060755.JPG
  3472   Wed Aug 25 16:13:32 2010 steveSummaryPEMPSL optical table is back into operation at 32.75" level

The tile work was done yesterday after noon.

This morning Mike Gerfen and me lowered the enclosure frame to normal height.

Keven- janitor and I removed plastic covers from chambers, racks, SP, MC2 and clean tool boxes.

 

The afternoon Jenne, Kiwamu, Joe and Aiden cleaned the enclosure inside out. The particle count measured zero inside the enclosure with HEPAs on when the covers were

removed. The MOPA and all other components were happy to see us in excellent condition.

This table height is very user friendly!

 

Safety grounds were reconnected.

 

Atm1, new tiles around the concrete slab

Atm2, frame lowered with low cross bars reinstalled

Atm3, the enclosure frame's north west foot is connected to ground

Atm4, PSL optical table is connected to ground at the north east corner through 1 Mohm

Atm5, PSL optical table level at a stimulating, back-friendly height

Attachment 1: P1060764.JPG
P1060764.JPG
Attachment 2: P1060768.JPG
P1060768.JPG
Attachment 3: P1060777.JPG
P1060777.JPG
Attachment 4: P1060776.JPG
P1060776.JPG
Attachment 5: P1060780.JPG
P1060780.JPG
  3477   Fri Aug 27 11:27:33 2010 steveUpdatePEMcrane safety document

I posted the crane safety document on the 40m wiki, vacuum page as 26 August 2010

Please add your comments and corrections.

 

The South End Crane will be balanced on Tuesday,  31 August 2010

This will mean that the back door of the south arm will be open on and off. Air quality will bad.

Please plan accordingly.

  3493   Tue Aug 31 10:44:17 2010 steveUpdatePEMconcrete sealed

The PSL -leg concrete was sealed with a single coat of SCOFIELD Cureseal-S to minimize shedding of particles.

The optical table was covered  and optics were removed from the shelf. Accelerometers were turned off.

Attachment 1: P1060787.JPG
P1060787.JPG
  3495   Tue Aug 31 13:31:00 2010 steveUpdatePEMroom temp lowered

I lowered room 101 thermostat setting from 74F to 72F

  3496   Tue Aug 31 14:47:53 2010 steveConfigurationPEMtoilet upgrade

Our toilets were replaced by a green Gerber 1.6 gpf ( 6 lpf ) last week.

Attachment 1: toil-n.JPG
toil-n.JPG
  3505   Wed Sep 1 10:54:15 2010 steveUpdatePEM more crane balancing

Crane balancing at the south end is continuing today.

  3513   Thu Sep 2 14:11:17 2010 steveSummaryPEMsouth end crane balancing is completed

The crane I -beam now leveled at all degrees of rotation.  The lower hinge was moved southward  about 1/4 of an inch.  Performance was tested at 2000 lbs

 

Atm1, work in progress

Atm2, load test at 1 Ton

Atm3, service report

Attachment 1: P1060798.JPG
P1060798.JPG
Attachment 2: P1060800.JPG
P1060800.JPG
Attachment 3: P1060804.JPG
P1060804.JPG
  3514   Thu Sep 2 16:41:32 2010 steveConfigurationSAFETYlaser is ON: safety glasses required!

I hooked up interlock to the Innolight 2W 1064 nm in the enclosure. The manual shutter  is closed on this unit.

SAFETY GLASSES REQUIRED !

  3547   Wed Sep 8 16:17:58 2010 steveUpdatePEMparticle counter problem

I played with the particle counter this morning. Now it's running and reading the correct numbers on the old COCHECKLIST.adl medm screen.

However, it can not be seen with dataviewer.

Koji just rebooted the frame builder and the problem was solved.

  3549   Thu Sep 9 08:23:45 2010 steveUpdateSAFETYmain laser turned off

Innolight 2W 1064nm main laser was turned off for more enclosure related work.

The electrician re rooting the power- conduit to the interlock under the floor and bring it through the new concrete tunnel.

Emergency laser power shut off switch was tested at entry door 104M.  It worked fine.

 

No laser glasses required. Laser will be turned back on around 11 am today.

  3550   Thu Sep 9 11:17:15 2010 steveUpdateSAFETYmain laser is back ON

Quote:

Innolight 2W 1064nm main laser was turned off for more enclosure related work.

The electrician re rooting the power- conduit to the interlock under the floor and bring it through the new concrete tunnel.

Emergency laser power shut off switch was tested at entry door 104M.  It worked fine.

 

No laser glasses required. Laser will be turned back on around 11 am today.

Atm1,   AC power line to enclosure and interlock  was extended.

Atm2,   24V line to interlock rerouted

Atm3,   job is completed

 

SAFETY GLASSES REQUIRED !  SAFETY GLASSES REQUIRED!

 

 The laser is turned on. Injection current set to 0.871A.

Actually some one turned the  laser  off last night and did  not enter it into the elog ! Burned toast award is granted !

Please  come forward voluntarily.

Attachment 1: P1060813.JPG
P1060813.JPG
Attachment 2: P1060814.JPG
P1060814.JPG
Attachment 3: P1060816.JPG
P1060816.JPG
  3551   Thu Sep 9 11:31:54 2010 steveUpdatePEMaccelerometer cable connection

I turned off/on the power to the accelerometers in order to re rout their connections. I found cable connector body-nut  #3 loose to Accelerometer 2X This connector should be checked for solid performance.

  3585   Fri Sep 17 17:35:35 2010 steveUpdatePEMcleaned up at 1Y1 PSL rack

Cleaned up cables on the top and bottom. Vacuumed both areas. We still have some remaining shading from the MOPA umbilical and more unknown BNC cables hanging around.

  3591   Mon Sep 20 17:10:10 2010 steveConfigurationPSL enclosure beam guides to IFO are installed

The PSL out  2" OD beam guide tube was cut  1.5" shorter to 13.5"

The 10" OD  0.25" wall Al tube was replaced by a  lighter, not anodized and thinner  wall 0.094" tube of 15.5" lenght, that is 0.75" shorter.

The new position of the PSL table made these cuts necessary.

  3592   Tue Sep 21 15:33:02 2010 steveMetaphysicsTreasureWagonga alart

John Miller has arrived from Australia with 3 bags of  Wagonga Coffee. Trade bargaining has started on

250 mgs of Sumatran Mandehling, Timur and Papua New Guine.

Attachment 1: P1060866.JPG
P1060866.JPG
Attachment 2: P1060872.JPG
P1060872.JPG
  3605   Fri Sep 24 16:31:35 2010 steveConfigurationGeneralopen frame- rack is moved

The squeezing open frame rack was moved from the south side of the PSL enclosure to the north side of the SP table.

AC power breaker is PC-2  #1

 

Attachment 1: P1060881.JPG
P1060881.JPG
  3611   Mon Sep 27 08:59:50 2010 steveConfigurationVACslow vent has started

Blocked PSL output beam  into IFO

Checked: HV at IOO & OMC are off, jam nuts in position,

Closed V1 and VM3, opened VV1 to N2 regulator

We are venting at 1 Torr/min rate

  3616   Tue Sep 28 14:12:14 2010 steveUpdateGeneralvertex crane drive is out of order

The vertex crane drive is overheating, it stopped functioning. Service man will be here tomorrow morning.

I crane was just turned  on for for may be  about 5 minutes. The vertical drive was fine for a while, but the horizontal did not worked at all.

The crane is tagged out again and the controller box is cooling down.

  3624   Thu Sep 30 09:34:58 2010 steveUpdateGeneralvertex crane trolly drive fixed

Quote:

The vertex crane drive is overheating, it stopped functioning. Service man will be here tomorrow morning.

I crane was just turned  on for for may be  about 5 minutes. The vertical drive was fine for a while, but the horizontal did not worked at all.

The crane is tagged out again and the controller box is cooling down.

 Atm1, Vertex crane controller unit on horizontal I-beam.

            Module CCES-407 1HP 2.3A 460V/3 phase on the right was replaced. Speed was increased  to 30 Hz

Atm2, See burned insulation on black wire that was shorting to the large suppressor resistor on Atm3 One can see the pit marks on the right end of it.

        This large power dissipater resistor got hot as the malfunctioning controller 407 broke down.   Touching black power wire insulation melted and made a short.

          So the heat was created and finally the fuses were blown. The unnecessary large fuses were replaced by small ones.

Fortunately we had one spare controller on hand that made this repair to be done fast.

We used the new Crane Safety Check list  from LIGO-E1000379-v1 the first time yesterday before doors were removed.

Attachment 1: P1060891.JPG
P1060891.JPG
Attachment 2: P1060887.JPG
P1060887.JPG
Attachment 3: P1060889.JPG
P1060889.JPG
Attachment 4: P1060893.JPG
P1060893.JPG
  3626   Thu Sep 30 13:43:29 2010 steveUpdateSAFETYpropane gas smell in control room

The control room's north west corner smelled like propane gas  yesterday around 16:30

We all agreed that the smell was real and I called the safety office. I was told that they received 6 other calls from different parts of the campus.

The smell disappeared in about a half an hour.

  3637   Fri Oct 1 16:46:20 2010 steveBureaucracySAFETYYuta received 40m-101-safety training

Our visiting graduate student Yuta Michimura received 40m specific basic safety training today.

  3646   Tue Oct 5 09:26:04 2010 steveConfigurationPEMmoved accelerometers

Accelerometers xyz were moved from IOO-south/west  corner to under PSL table. They were turned off for ~20 minutes.

Guralp was also moved eastward about 2 ft. It is not leveled.

This is part of the preparation to remove access connector.

  3654   Tue Oct 5 17:39:21 2010 steveConfigurationVACwest access connector removed

Kiwamu, Koji, Yutah, Rana, Jan and Steve

We removed the west access connector this afternoon.

  3664   Thu Oct 7 08:39:39 2010 steveBureaucracySAFETYJoonho receives safety training

Our new undergrad Joonho Lee received 40m specific basic safety training yesterday.

Yuta and Joonho are scheduled to participate in the LIGO-laser safety tutelage with Peter K on Oct 12

  3670   Thu Oct 7 15:21:51 2010 steveUpdatePSLRF filter for PMC

We got two small RF filter for the PMC from Valera  They are made by http://www.larkengineering.com/   "MC35.5-3-AB" sma, 29300-01

Attachment 1: 35.5MHZ.pdf
35.5MHZ.pdf
  3676   Fri Oct 8 07:41:42 2010 steveConfigurationSAFETY2W laser shutter is closed

The 2 W Innolight shutter is closed and enclosure door removed. Beam path blocked. Do not change this condition.

  3677   Fri Oct 8 10:38:03 2010 steveConfigurationSAFETY2W laser shutter is closed

Quote:

The 2 W Innolight shutter is closed and enclosure door removed. Beam path blocked. Do not change this condition.

The PSL output beam guide was upgraded from 2" to 8" OD . It is green ready. Shutter is open.

Attachment 1: P1060905.JPG
P1060905.JPG
Attachment 2: P1060910.JPG
P1060910.JPG
  3682   Fri Oct 8 17:36:16 2010 steveFrogsPhotosvisiting undergrads

Prof Alan Weistein guided the 24 student through the 40m. His performance was rated as  an enthusiastic 9.5

Attachment 1: P1060916.JPG
P1060916.JPG
Attachment 2: P1060921.JPG
P1060921.JPG
Attachment 3: P1060922.JPG
P1060922.JPG
Attachment 4: P1060915.JPG
P1060915.JPG
  3688   Mon Oct 11 10:51:36 2010 steveUpdateSUSOSEMs, OSEMs, OSEMs...those lovely little OSEMs
Attachment 1: 40dll.jpg
40dll.jpg
  3698   Tue Oct 12 16:35:17 2010 steveConfigurationPSLPSL output monitor in place

Innolight PSL laser is set to @2.1A , ~1.6W output ! Please scan out when finished! 

The output monitoring pick up window W2-LW-2-2050-UV-1064-45S is in place. IOO_ANG_OPD and IOO_POS_QPD roughly aligned.

The PMC alignment and/ or mode matching is bad. PMC reflected is 50%, throughput 600mW

Remember to block PSL output ! into IFO

 

  3733   Mon Oct 18 09:01:48 2010 steveHowToGeneralHow not to

This BNC cable is crying for help. Please do not do this to me.  It should be reported  to the  abused center.Throw this cable into the garbage now.

Attachment 1: P1060926.JPG
P1060926.JPG
  3745   Wed Oct 20 16:41:41 2010 steveOmnistructureGeneral laser chiller leaving for MIT
Attachment 1: P1060929.JPG
P1060929.JPG
  3751   Thu Oct 21 10:44:56 2010 steveMetaphysicsTreasure1987 supernova tapes plus....?

I'm cleaning out to make room for our new optical cabinet. Are we keeping these? There are  ~20  pieces of 10" od 1" wide tapes and large number of cassettes.

AJW,  Zucker,  Stuart A and Koji were notified in this matter.

Alan suggested to save data of Bruce Allen paper of observation of binary neutron stars in the 40m on 1994 November 14-20 and save back up tapes of his period in the 40m.

Mike: reels are not readable any more, it is time to let go

Attachment 1: P1060932.JPG
P1060932.JPG
  3792   Wed Oct 27 09:02:29 2010 steveUpdateElectronicsHP4195A is NOT fixed

www.avalontest.com has fixed the 25MHz oscillation.  Contact: Jim Burnham 760-536-0191

Actually, NOT FIXED.

  3808   Thu Oct 28 09:16:17 2010 steveUpdatePEMwelding in the vertex area

Fire-smoke sensors in the vertex area #2-31, 2-30 east, 2-32 south/MC2 and 2-37 old control room area are turned off to accommodate the welding

activity of folding crane. These sensors will be reactivated at 3:30pm today.

Stay out of the 40m lab: IFO room till 6 pm today.

  3810   Thu Oct 28 13:01:34 2010 steveUpdatePEMcrane repair guys left for the day

Quote:

Fire-smoke sensors in the vertex area #2-31, 2-30 east, 2-32 south/MC2 and 2-37 old control room area are turned off to accommodate the welding

activity of folding crane. These sensors will be reactivated at 3:30pm today.

Stay out of the 40m lab: IFO room till 6 pm today.

 The new cord wheel was to big. They be back tomorrow?

The lab is open.

  3832   Mon Nov 1 10:17:55 2010 steveUpdateGeneralbreakers relabelled

Pedro of the electrical shop helped to retrace wires from the racks to the breakers. Many wrong labels were replaced. These labels are  still representing                          the south arm as Y and  the east arm as X.

Racks: 1X1,2,3,4 and 1Y3,4,5,6,7 and 9 are connected through manual disconnect swithes to  AC power breaker PC-1 on the west wall of IFO room 104.

             This panel PC-1 is connected to T1 isolation transformer in room 101 Panel L - # 38, 40, 42

Racks: 1Y1 & 2  psl and mc are connected through manual disconnect switches to AC power breaker PC-2 just west of the psl enclosure.

             This panel is connected to T2 isolation transformer in room 101 Panel L - # 32, 34, 36

Attachment 1: P1060970.JPG
P1060970.JPG
Attachment 2: P1060972.JPG
P1060972.JPG
Attachment 3: P1060975.JPG
P1060975.JPG
  3833   Mon Nov 1 10:28:41 2010 steveBureaucracySAFETYSuresh received 40m safety training

Our new postdoc Suresh Doravari received 40m specific safety training last week.

  3854   Wed Nov 3 16:49:31 2010 steveUpdateGeneralstorage cabinet is in place

The south end of IFO room 104 was reshuffled. The flow bench was moved all the way to the south end to create more room for the crane reach. The old  large drawing cabinet  was moved under the vacuum tube.

The new clear view through  Acrylic-plexyglass cabinet is anchored. It has powder finished coating so it will not out-gas too much.The back side shelf mounting holes are sealed off with kapton tape. The doors still needs some gaskit seals.

Attachment 1: P1070018.JPG
P1070018.JPG
  3862   Thu Nov 4 17:24:49 2010 steveUpdateGeneralconflat flanges for MIT

8 pieces of 10" CF blanks were shipped to MIT

Attachment 1: P1070020.JPG
P1070020.JPG
  3864   Thu Nov 4 17:57:27 2010 steveUpdateGeneralBeamScanner is working again

Koji, Suresh and Steve,

The beam scanner is back from repair.  Koji and Suresh helped to move the I/O address jumpers on the interface card from default position  300 to 320

It is working again.

Attachment 1: P1070024.JPG
P1070024.JPG
  3867   Fri Nov 5 09:08:14 2010 steveUpdateSUSepoxy

Physical Electronics: Vac-Seal #288-6000 arriving Monday. Our last bag used last week had a p/n 1002003 with expiration date   .....2009 ? and it was stored in the

refrigerator all times. We are getting 68 small bags.

We should have precision gluing notes of epoxies/procedures used on our sus upgrade.

Attachment 1: 11081001.PDF
11081001.PDF
  3894   Thu Nov 11 11:08:26 2010 steveBureaucracyPEMAP table found open

Please remember to cover the optical tables !

  4059   Wed Dec 15 16:04:49 2010 steveConfigurationVACvacuum valves found in default condition

This condition is created when we run out of nitrogen that holds the valves in set positions. The Maglev and other turbos are still running in this configuration so one has to pay attention that the foreline valves are open.

Reset  error message on vacuum screen and opened V4 & V5 at 3pm today.

  4077   Mon Dec 20 16:57:58 2010 steveUpdateIOOchecking out & closing the vacuum chambers
  • Check EQ-stops
  • clamp down counter weights
  • check other components are clamped
  • remove all tools
  • check cabling is not is not shorting out seismic stack or blocking beam
  • confirm well centered spots on mirrors
  4083   Tue Dec 21 16:20:09 2010 steveConfigurationVACpumpdown has started

Slow pumpdown of rebuilt IFO-mark4 started at 3pm today.

We are at 680Torr at this minute with 1.5 Torr/min speed.