    Reply  Tue Jun 23 15:19:42 2009, steve, Configuration, VAC, V1 is open V1_opennmag.jpg
    Reply  Wed Jun 24 09:21:19 2009, steve, Configuration, VAC, IFO RGA scan with Maglev & Cryo nmagd1ifo.jpgnmagCryopres.jpg
Entry  Wed Jun 24 17:08:16 2009, steve, Bureaucracy, SAFETY, surf student safety 
Entry  Thu Jun 25 10:28:58 2009, steve, HowTo, VAC, Cryopump is regenerated Creg.jpg
Entry  Thu Jul 2 17:37:36 2009, steve, Update, VAC, V1 interlock test 
Entry  Tue Jul 14 14:54:19 2009, steve, Configuration, Computers, fb40m2 in 1Y6 
Entry  Wed Jul 15 08:59:30 2009, steve, Update, Computers, fb40m  
Entry  Mon Jul 20 10:35:06 2009, steve, Update, VAC, UPS batteries replaced 
Entry  Tue Jul 21 18:46:47 2009, steve, Configuration, Computers, computers are down 
    Reply  Mon Jul 27 09:34:07 2009, steve, Summary, IOO, Aligning the mode cleaner 20dtrend.jpg
Entry  Wed Jul 29 11:15:06 2009, steve, Bureaucracy, SAFETY, Kevin receives safety training 
Entry  Wed Aug 5 07:33:04 2009, steve, DAQ, Computers, fb40m is down 
Entry  Wed Aug 5 16:33:50 2009, steve, Configuration, PSL, new PSL output iris psliris.png
Entry  Thu Aug 6 09:05:29 2009, steve, Update, VAC, large O-rings of vacuum envelope vacsor1.pngvacsor2.png
Entry  Fri Aug 7 09:50:57 2009, steve, Configuration, VAC, IFO pressure rose to 2.3 mTorr tp2fpfail.jpg
    Reply  Fri Aug 7 19:34:40 2009, steve, Summary, VAC, UPS failed 
    Reply  Fri Aug 7 19:55:08 2009, steve, Summary, VAC, opening V1 when PTP1 is broken 
    Reply  Thu Aug 20 09:16:32 2009, steve, HowTo, Photos, Control Room Workstation desks lowered to human height P1040788.pngP1040782.pngP1040786.pngP1040789.pngP1040785.png
    Reply  Mon Aug 24 16:48:57 2009, steve, HowTo, VAC, new UPS installed 
    Reply  Tue Aug 25 18:42:42 2009, steve, Update, PSL, reference cavity temp box temporarly out of order 
Entry  Wed Aug 26 14:45:14 2009, steve, Update, PSL, PSL-FSS_RCTEMP of 4 years refcavtemp.jpg
    Reply  Wed Aug 26 16:31:34 2009, steve, Update, PSL, reference cavity temp box temporarly out of order 
Entry  Thu Aug 27 16:14:28 2009, steve, Summary, OMC, burned photodiode 20090827_173252.jpg20090827_170802.jpg
Entry  Fri Aug 28 15:30:15 2009, steve, Configuration, General, POX rfpd removed 
Entry  Tue Sep 1 11:23:36 2009, steve, Update, General, electrical ground ground.JPG
    Reply  Tue Sep 1 13:52:06 2009, steve, Configuration, General, POX rfpd is back & needs alignment 
    Reply  Thu Sep 3 11:20:26 2009, steve, Update, General, electrical ground in place Gs-n.JPGnewground.JPG
Entry  Tue Sep 8 16:01:52 2009, steve, Configuration, VAC, RGA was separeted from IFO vm1closed.jpg
    Reply  Wed Sep 9 10:13:31 2009, steve, Bureaucracy, General, the use of FAX machine, scanner & toaster 
Entry  Tue Sep 15 15:46:05 2009, steve, Update, PEM, PEM and VAC 120dpem.jpg16dpem.jpg
Entry  Fri Sep 18 16:26:02 2009, steve, Summary, PSL, Neslab chiller is OK 
Entry  Thu Oct 1 08:37:43 2009, steve, Update, SUS, suspention damping restored and MZ HV stuck eq5oct1.jpg
Entry  Thu Oct 1 10:23:00 2009, steve, Update, PSL, MC2 damping restored again mc2again.jpg
Entry  Thu Oct 15 09:23:07 2009, steve, Summary, Locking, never had it so good 5hlock.jpg
Entry  Fri Oct 16 10:15:02 2009, steve, Update, IOO, IP ang & pos recentered ip4d.jpg
Entry  Mon Oct 19 11:00:52 2009, steve, HowTo, SAFETY, 40m safety training safety_10_2009.JPG
Entry  Tue Oct 20 10:46:18 2009, steve, Update, IOO, clipping IP-ANG beam at ETMX chamber PA200175.JPGPA200177.JPG
    Reply  Thu Oct 22 08:45:58 2009, steve, Update, IOO, IP ang & pos recentered pointing1000.jpg
Entry  Fri Oct 23 09:13:45 2009, steve, Summary, VAC, RGA scan pd66md435.jpgpd66d435ptt.jpg
Entry  Mon Oct 26 15:40:01 2009, steve, Update, PSL, laser power is down  laserpowerdown.jpg
Entry  Wed Oct 28 09:12:18 2009, steve, Update, PSL, PMC power on the rise? pmcprising.jpg
Entry  Wed Oct 28 14:39:10 2009, steve, Update, PEM, after the tour of the 40m  
    Reply  Fri Oct 30 09:24:45 2009, steve, HowTo, MOPA, how to squeeze more out of little 44to34.jpg
Entry  Fri Nov 6 07:55:59 2009, steve, Update, Computers, RFMnetwork is down 
Entry  Fri Nov 6 09:17:53 2009, steve, Omnistructure, PEM, PSL HEPAs turned on 
Entry  Mon Nov 9 08:43:16 2009, steve, Update, SUS, MC2 damping restored 
Entry  Wed Nov 11 09:48:04 2009, steve, Update, IOO, where is IOO-RFAMPD_DCMON ? rfampddc.jpg
Entry  Thu Nov 12 09:43:29 2009, steve, Update, PEM, construction has started at CES cuttingconcr.jpgcutcon1.JPGcutcon2.JPG
Entry  Mon Nov 16 09:37:41 2009, steve, Update, PEM, construction is getting noisier 4hces.pngP1050734.JPGP1050736.JPG
Entry  Thu Nov 19 09:25:19 2009, steve, Update, MOPA, water was added to the laser chiller htempwtr.png