3156
|
Fri Jul 2 11:06:38 2010 |
josephb, kiwamu | Update | CDS | CDS and Green locking thoughts | Kiwamu and I went through and looked at
the spare channels available near the PSL
table and at the ends. |
|
3230
|
Thu Jul 15 16:57:31 2010 |
josephb, kiwamu | Update | CDS | The temporarily named c1scx machine getting ready to connect to IO chassis | This is the machine which will be the new
x end front end machine. Its IP is
192.168.113.86. |
|
3257
|
Wed Jul 21 12:20:29 2010 |
josephb, kiwamu | Update | Computers | Megatron temporarily disconnected, c1iscex firewalled, green FE test | We are moving towards a first test of getting
Kiwamu's green locking signals into the new
front end at the new X end, as well as sending |
|
3293
|
Mon Jul 26 14:24:46 2010 |
josephb, kiwamu | Update | CDS | RFM test take 1 | Kiwamu and I strung a temporary RFM fiber
from the c1iscex machine (in the new 1X9
rack) to the c1sus machine (in the new 1X4 |
|
3321
|
Thu Jul 29 15:35:21 2010 |
josephb, kiwamu | Update | CDS | Working out ADC/DAC/BO wiring | We are currently using the SUS wiring diagram
found on Ben Abbott's page (link here)
to determine the ADC/DAC/BO channel numbers |
|
3323
|
Thu Jul 29 17:12:48 2010 |
josephb, kiwamu | Update | CDS | Re:Working out ADC/DAC/BO wiring | We
have installed 4 BO boards, 3 DAC boards
and 1 ADC board for new C1SUS.
They |
|
3638
|
Fri Oct 1 18:19:24 2010 |
josephb, kiwamu | Update | CDS | c1sus work | The c1sus model was split into 2, so that
c1sus controls BS, PRM, SRM, ITMX, ITMY,
while c1mcs controls MC1, MC2, MC3. |
|
3639
|
Fri Oct 1 18:53:33 2010 |
josephb, kiwamu | Update | CDS | Things needing to be done next week | We realized we cannot build code with the
current RCG compiler on c1ioo or c1iscex,
since these are not Gentoo machines. |
|
4012
|
Mon Dec 6 11:53:20 2010 |
josephb, kiwamu | Summary | all down cond. | power outage | The monitors for allegra and rossa's seemed
to be in a weird state after the power outage.
I turned allegra and rossa on, but didn't |
|
4027
|
Wed Dec 8 14:46:19 2010 |
josephb, kiwamu | Update | CDS | Why the ETMX daq channels were not recorded last night | When adding
the ETMX DAQ channels using the daqconfig
gui (located in /opt/rtcds/caltech/c1/scripts/) |
|
4065
|
Thu Dec 16 15:10:18 2010 |
josephb, kiwamu | Update | CDS | ETMY working at the expense of ETMX | I acquired
a second full pair of Host interface board
cards (one for the computer and one for the |
|
4134
|
Tue Jan 11 13:32:52 2011 |
josephb, kiwamu | Update | CDS | Updated some DAQ channel names | [Joe,
Kiwamu]
We |
|
3155
|
Thu Jul 1 17:05:36 2010 |
josephb, kiwamu, steve | Update | CDS | New SUS Chassis in rack | Thanks to Steve's work on some L brackets,
and Kiwamu's lifting help, we now have a
new SUS IO chassis in the new 1X4 rack (formerly |
|
2267
|
Fri Nov 13 14:04:27 2009 |
josephb, koji | Update | Computers | Updated wiki with RCG instructions/tips | I've placed some notes pertaining to what
Koji and I have learned today about getting
the RCG code working on the 40m wiki at: |
|
2486
|
Fri Jan 8 10:38:35 2010 |
josephb, koji | Update | Computers | RFM and Megatron | Last night, we installed the VMI 5565 RFM
card into Megatron. After turning off
the watchdogs for the ETMY optic, we disconnected |
|
2539
|
Thu Jan 21 15:16:16 2010 |
josephb, koji | Summary | Computers | Megatron used to lock Y arm | We
succeeded in having a stable single arm (Y)
lock using Megatron to replace c1iscey.
Now |
|
3178
|
Thu Jul 8 15:19:27 2010 |
josephb, koji | Configuration | Computers | Added Zonet camera to IP table on linux1 | We gave the Zonet camera the IP 192.168.113.26
and the name Zonet1.
We did this by modifying the /var/named/chroot/var/named/113.168.192.in-addr.arpa.zone |
|
2255
|
Thu Nov 12 15:40:27 2009 |
josephb, koji, peter | Update | Computers | ETMY and Megatron test take 1 | We connected megatron to the IO chassis
which in turn was plugged into the rest of
the ITMY setup. We had manually turned |
|
1508
|
Thu Apr 23 13:55:43 2009 |
josephb, peter | Update | Computers | RCG example | We successfully compiled and installed
the Real time Code Generator "Hello
World" example (which is a skeleton |
|
3221
|
Wed Jul 14 18:09:50 2010 |
josephb, razib | Update | Phase Camera | Some cleanup behind 1Y2 rack of phasecamera electronics | We made an attempt at cleaning up the phase
camera setup electronics.
We have moved a portion of the electronics |
|
2607
|
Tue Feb 16 14:10:06 2010 |
josephb, rob, koji | Configuration | LSC | Arms and PRC not locking |
|
|
606
|
Mon Jun 30 16:00:02 2008 |
josephb, sam | Configuration | Computers | | Sam and I setup Cat6 cable from Megatron to
the 1Y6 Switch (131.215.113.252) and also
connected the 1Y6 Hub to the control room |
|
4561
|
Fri Apr 22 12:07:38 2011 |
josephb, steve | Update | CDS | Removed hanging D-sub to SCSI in 1X2 | Problem:
Way back, Jay had D-sub
to SCSI adapters made to adapt our existing
Sander box AA filters to the new SCSI based |
|
4590
|
Fri Apr 29 14:36:36 2011 |
josephb, steve | Update | CDS | Removed hanging D-sub to SCSI in 1X5 |
|
|
2940
|
Mon May 17 17:17:49 2010 |
josephb, steve, alberto, kiwamu | Update | CDS | New CDS computers now in racks. | We placed 3 new computers in the racks.
One in 1X4 (machine running SCX) and 2 in
1Y4 (LSC and SUS). These are 1U chassis, |
|
3906
|
Fri Nov 12 10:49:34 2010 |
josephb, valera | Update | CDS | Test of ADC noise | Test:
Look at the effects of the ADC voltage
range on the ADC noise floor. |
|
4317
|
Thu Feb 17 22:51:04 2011 |
josephb, valera | Summary | | dither alignment model | We made a model for the dither angular
stabilization system c1ass.mdl. The attached
file shows the diagram. |
|
4325
|
Fri Feb 18 17:52:25 2011 |
josephb, valera | Update | CDS | c1ass updated | We updated
the c1ass model to include the BS.
We removed the dither excitation of the PZTs. |
|
3652
|
Tue Oct 5 16:30:00 2010 |
josephb, yuta | HowTo | CDS | Screen settings and medm screens for new system | You can find the sitemap medm screen in
/opt/rtcds/caltech/c1/medm/master
The settings for the screens were |
|
3653
|
Tue Oct 5 16:58:41 2010 |
josephb, yuta | Update | CDS | c1sus front end status | We moved the filters for the mode cleaner
optics over from the C1SUS.txt file in /opt/rtcds/caltech/c1/chans/
to the C1MCS.txt file, and placed SUS_ on |
|
3658
|
Wed Oct 6 11:03:51 2010 |
josephb, yuta | HowTo | CDS | How to start diaggui for right now | I'm hoping to get a proper install this
week done, but for now, this a stop gap.
To start diagnostic test tools, go |
|
3662
|
Wed Oct 6 16:16:48 2010 |
josephb, yuta | Update | CDS | c1sus status | At the moment, c1sus and c1mcs on the c1sus
machine seem to be dead in the water.
At this point, it is unclear to me why. |
|
3666
|
Thu Oct 7 10:48:41 2010 |
josephb, yuta | Update | CDS | c1sus status | This
problem has been resolved.
Apparently during one of Alex's debugging |
|
3668
|
Thu Oct 7 14:57:52 2010 |
josephb, yuta | Update | CDS | c1sus status | Around noon, Yuta and I were trying to
figure out why we were getting no signal
out to the mode cleaner coils. It turns |
|
3706
|
Wed Oct 13 17:04:34 2010 |
josephb, yuta | Update | CDS | burt restore now working with filter settings | Previously, burt restoring was not setting
filters on and off, which was required us
to constantly go through all the filter banks |
|
3707
|
Wed Oct 13 17:12:33 2010 |
josephb, yuta | Update | CDS | Filter name length problem found and fixed | The missing filter files for ULPOS, URPOS,
and so forth for the mode cleaner optics
was due to the length of the names of the |
|
3797
|
Wed Oct 27 15:38:19 2010 |
josephb, yuta | Update | CDS | IO chassis with bad timing was taken back to Downs | Problem:
The front end timing was not working
properly for 2 of the IO chassis. They |
|
3821
|
Fri Oct 29 11:25:15 2010 |
josephb, yuta | Summary | CDS | [EMERGENCY] accidentally deleted daqd | Problem:
Missing daqd file, i.e. the framebuilder
executable. |
|
3845
|
Tue Nov 2 13:51:40 2010 |
josephb, yuta | Update | CDS | RFM slowdown problem | Problem:
Each RFM memory location which needs
to be read by a front end model slows the |
|
3861
|
Thu Nov 4 15:27:33 2010 |
josephb, yuta | Update | CDS | c1ioo test points not working | Problem:
We can't access any of the c1ioo
computer testpoints. Dataviewer and |
|
3880
|
Mon Nov 8 14:30:15 2010 |
josephb, yuta | Update | CDS | Added LIGONDSIP setting to cshrc.40m | We added the following line to the cshrc.40m
file in the 64-bit linux and 32-bit linux
sections: |
|
3946
|
Thu Nov 18 14:05:06 2010 |
josephb, yuta | Update | CDS | c1sus is alive! | Problem:
We broke c1sus by moving ADC cards
around. |
|
3659
|
Wed Oct 6 12:00:23 2010 |
josephb, yuta, kiwamu | Update | CDS | Found and fixed filter sampling rate problem with suspensions | While we looking using dtt and going over
the basics of its operation, we discovered
that the filter sample rates for the suspensions |
|
3911
|
Fri Nov 12 20:40:51 2010 |
josephb, yuta, valera | Configuration | Electronics | AA voltage range | We changed the range of the two SUS AA
boards in the corner from +/-2 V to +/-10
V by changing the supply voltage from +/-5 |
|
1574
|
Mon May 11 12:25:03 2009 |
josephb,Alex | Update | Computers | fb40m down for patching | The 40m frame builder is currently being
patched to be able utilize the full 14 TB
of the new raid array (as opposed to being |
|
2212
|
Mon Nov 9 13:22:08 2009 |
josephb,alex | Update | Computers | Megatron update | Alex and I took a look at megatron this
morning, and it was in the same state I left
it on Friday, with file system errors. |
|
2967
|
Fri May 21 14:31:46 2010 |
josephb,alex | Update | CDS | New computer and IO chassis working in 1X4 | Alex brought over a ADC, DAC, and PCIe
card which goes into the computer and talk
to the IO chassis. We tried installing |
|
3034
|
Wed Jun 2 11:25:16 2010 |
josephb,alex | Update | CDS | CDS saga (aka the bad code saga) | Alex updated the awg.par file to handle
all the testpoints. Basically its very
similar to the testpoint.par, but the prognum |
|
3632
|
Fri Oct 1 10:56:30 2010 |
josephb,alex | Update | CDS | fb work continued | Alex fixed the time issue with the IRIG-B
signal being far off, apparently their IRIG-B
signal in downs seems to be different. |
|
2540
|
Thu Jan 21 17:23:30 2010 |
josephb,alex,koji | HowTo | Computers | RCG code fixes | In order to see the Contec DO-32L-PE
Digital output PCIe card with the new
controls, we had to add the CDO32 part to |
|