  995   Fri Sep 26 00:19:54 2008 JenneUpdatePSLFilter-action with the PMCWritten, but not posted on 24Sept2008:

 
  
  3707   Wed Oct 13 17:12:33 2010 josephb, yutaUpdateCDSFilter name length problem found and fixedThe missing filter files for ULPOS, URPOS,
and so forth for the mode cleaner optics
was due to the length of the names of the
  
  3802   Thu Oct 28 02:01:51 2010 KevinUpdatePSLFilter for 2W Laser[Rana and Kevin]
I made a low pass filter for the
piezo driver for the 2W laser that is now
 tf.PDFoutside.jpginside.jpg 
  5730   Mon Oct 24 19:48:16 2011 MirkoUpdateAdaptive FilteringFilter execution timeToyed around some more with the adaptive
filters.
Execution time:
nTaps   
  
  7099   Tue Aug 7 00:22:10 2012 JenneUpdateASSFilter banks working

    

       
            
  
  7092   Mon Aug 6 17:15:15 2012 JenneUpdateASSFilter banks not workingI was trying to load some filters into
the ASS so that I can try it out, but for
some reason the filter banks aren't working
  
  5128   Fri Aug 5 20:44:26 2011 jamieMetaphysicsTreasureFilm crew here Monday morningJust a reminder that a film crew will
be here Monday morning, filming Christian
Ott for some Discovery channel show.
  
  10474   Tue Sep 9 00:34:34 2014 JenneUpdateLSCFiguring out where to do DARM->AS55This afternoon, after Q and Manasa finished
recovering from the activities of the morning,
I aligned the IFO, and went to the Yend to
  
  10478   Tue Sep 9 14:25:46 2014 jamieUpdateLSCFiguring out where to do DARM->AS55

    

       
            
  
  14703   Wed Jun 26 20:45:03 2019 gautamUpdateCamerasField of view optionsFor the beam spot position tracking, I
am wondering if there is any benefit to going
for a wider field of view and getting the
  
  10860   Wed Jan 7 02:54:09 2015 JenneUpdateLSCFiddling with DARM filtersOne of the things that we had talked about
last night was the totally tiny amount of
phase margin that we have in the CARM and
 DARM_design_orig.pdf 
  296   Mon Feb 4 22:01:57 2008 JohnSummaryLSCFibres auxiliary locking - FibersI managed to couple ~75% of the light transmitted
from the y arm, through the fibre, back to
the SP table. I hoped that this would be
  
  272   Sat Jan 26 02:08:53 2008 JohnOmnistructureLSCFibresThere is now a fibre running from the SP table
to the ISCT at the Y-end. In the coming days
I will try to mode match the beam from this
  
  315   Wed Feb 13 20:37:11 2008 JohnUpdateLSCFibre locking - FiberSam and I observed fringes in the light reflected
from the Y arm. These fringes are due to
the sidebands and not the carrier. To improve
  
  8183   Wed Feb 27 14:39:59 2013 AnnalisaUpdateLSCFibre laid for RFPD audio [Annalisa, Jenne, Rana, Steve]
We installed the fibres on cable
trays the 1Y2 and the Control Room.
  
  3859   Thu Nov 4 03:13:46 2010 SureshUpdateLockingFibre coupling 1064nm light at the south-end table[Kiwamu,
Suresh]
We
  
  3865   Thu Nov 4 19:00:57 2010 SureshUpdateLockingFibre coupling 1064nm light at the south-end tableThe Fluke
Visual Fault locator (Visifault) arrived
and I used it to couple 1064nm light into
  
  4882   Sat Jun 25 00:00:28 2011 SonaliUpdateGreen LockingFibre Coupling. What I did today.
1. I tried to align the IR input
beam by aligning the two mirrors, to couple
 Fibre_coupling_successful_24_june.jpgBeam_output_on_screen.jpg 
  13753   Fri Apr 13 17:56:26 2018 gautamUpdateALSFibers switched outI swapped the EX fiber for the PSL fiber
in the polarization monitoring setup. There
is a lot more power in this fiber, and one
  
  13754   Sat Apr 14 14:42:09 2018 gautamUpdateALSFibers switched outIt looks like the drift in polarization
content in the PSL pickoff is actually much
higher than that in the EX pickoff. Note
 PSLdrift.png 
  13757   Tue Apr 17 14:08:29 2018 gautamUpdateALSFibers switched outA follow-up on the discussion from today's
lunch meeting - Rana pointed out that rotation
of the fiber in the mount by ~5degrees cannot
 PSL_fluctuations.png 
  13773   Fri Apr 20 00:26:34 2018 gautamUpdateALSFibers switched outSummary:

  
  3594   Wed Sep 22 16:35:45 2010 josephbUpdateCDSFibers pulled, new FB install tomorrow[Aidan, Tara, Joe]
We pulled out what used to be the
LSC/ASC fiber from the 1Y3 arm rack, and
  
  20   Fri Oct 26 21:48:40 2007 waldmanConfigurationOMCFiber to 056I set up a 700 mW NPRO in Rana's lab and launched
it onto a 50m fiber.  I got a few mW onto
the fiber,  enough to see with a card before
  
  11013   Thu Feb 12 12:16:04 2015 manasaUpdateGeneralFiber shielding[Steve, Manasa]

The fibers around the PSL table
were shielded to avoid any tampering.
  
  14503   Sun Mar 31 15:05:53 2019 gautamUpdateALSFiber beam-splitters not PMI looked into this a little more today.


Looking at the beat signal
between the PSL and EX beams from the
 IMG_7384.JPG 
  14643   Wed May 29 18:13:25 2019 gautamUpdateALSFiber beam-splitters are now PMTo maintain PM fibers all the way through
to the photodiode, I had ordered some PM
  
  10389   Thu Aug 14 18:10:46 2014 HarryUpdateGeneralFiber Temperature Effects SetupPurpose
We want to characterize the sort
of response the fibers have to temperature
 tempAffectsSetup.zip 
  10403   Fri Aug 15 17:24:44 2014 HarryUpdateGeneralFiber Temp. Earlier today Q and I somewhat resurrected
my old PER measurement setup so I could run
the temperature characterization experiment.
  
  10985   Fri Feb 6 18:06:18 2015 manasaUpdateGeneralFiber Optic module for FOLI pulled out the Fiber Optic Module for
FOL from the rack inside the PSL table enclosure
and modified it. The beat PDs were moved
 FOLfiberModule.png 
  10282   Mon Jul 28 17:25:32 2014 HarryUpdateGeneralFiber Mode With Collimators Purpose
We want a measurement of the fiber
modes at either end, with the collimators,
 end1Profiles.pngend2Profiles.pngFiberModeWCollimators.zip 
  10240   Sat Jul 19 01:59:34 2014 HarryUpdateGeneralFiber Mode MeasurementPurpose 
We wanted to measure the mode coming
out of the fibers, so we can later couple
 fiberModeMeasurement.pngfiberModeMeasurement1.pngfiberModeMeasurement1.zip 
  10244   Mon Jul 21 10:30:38 2014 HarryUpdateGeneralFiber Mode Measurement Purpose
The idea was to measure the profile
of the light coming out of the fiber, so
 fiberModeMeasurement.pngfiberModeFit2.pngfiberModeMeasurement2.zip 
  10249   Mon Jul 21 18:08:19 2014 HarryUpdateGeneralFiber Mode Measurement

    

       
            
 fiberModeMeasurement3.png 
  10255   Tue Jul 22 16:26:04 2014 HarryUpdateGeneralFiber Mode MeasurementI repeated this process once more, this
time using the computer controlled stage
that the beam profiler is designed to be
 fiberModeProfile3.pngfiberModeMeasurement4.zip 
  10218   Wed Jul 16 17:34:11 2014 HarryUpdateGeneralFiber Coupled Purpose
To couple the spare NPRO into our
Panda PM980 fibers, in order to carry out
 fiberTestCouplingSchematic.png 
  13333   Tue Sep 26 19:10:13 2017 gautamUpdateALSFiber ALS setup neatened[steve, gautam]

The Fiber ALS box has been installed
on the existing shelf on the PSL table. We
 IMG_7605.JPG 
  13254   Fri Aug 25 15:54:14 2017 gautamUpdateALSFiber ALS noise measurement[Kira, gautam]

Attachment #1 - Photo
of the revamped beat setup. The top panel
 IMG_7497.JPGFOL_schematic.pdf20170825_IR_ALS.pdf 
  13255   Fri Aug 25 17:11:07 2017 ranaUpdateALSFiber ALS noise measurementIs it better to mount the box in the PSL
under the existing shelf, or in a nearby
PSL rack?
  
  13257   Sun Aug 27 11:57:31 2017 ranaUpdateALSFiber ALS noise measurementIt seems like the main contribution to
the RMS comes from the high frequency bump.
When using the ALS loop to lock the arm to
  
  13266   Tue Aug 29 02:08:39 2017 gautamUpdateALSFiber ALS noise measurementI was having a chat with EricQ about this
today, just noting some points from our discussion
down here so that I remember to look into
  
  13288   Fri Sep 1 19:15:40 2017 gautamUpdateALSFiber ALS noise measurementSummary:

I
did some work today to see if I could use
 IR_ALS_noise.pdf 
  13502   Thu Jan 4 12:46:27 2018 gautamUpdateALSFiber ALS assayAttachment
#1 is the updated
 FiberALS.pdfFiberALS.svg.zip 
  13531   Thu Jan 11 14:22:40 2018 gautamUpdateALSFiber ALS assayI did a cursory check of the ALS signal
chain in preparation for commissioning the
IR ALS system. The main elements of this
  
  13534   Thu Jan 11 20:51:20 2018 gautamUpdateALSFiber ALS assayAfter labeling cables I would disconnect,
I pulled the box out of the LSC rack. Attachment
#1 is a picture of the insides of the box
 IMG_5112.JPG 
  13552   Tue Jan 16 21:50:53 2018 gautamUpdateALSFiber ALS assayWith Johannes' help, I re-installed
the box in the LSC electronics rack. In the
end, I couldn't find a good solution
  
  13557   Thu Jan 18 00:35:00 2018 gautamUpdateALSFiber ALS assaySummary:

I
am facing two problems:
 IR_ALS_20180118.pdfC2B4C1DD-6528-4067-9C13-6BD248629AD6.MOV 
  13559   Fri Jan 19 11:34:21 2018 gautamUpdateALSFiber ALS assayI swapped the inputs to the ZHL-3A at the
PSL table - so now the X beat RF signals
from the beat mouth are going through what
 IR_ALS_20180119.pdf 
  13562   Fri Jan 19 23:04:11 2018 gautamUpdateALSFiber ALS assay[rana, kevin, udit, gautam]

quick notes of some discussions
we had today:
  
  13571   Wed Jan 24 00:33:31 2018 gautamUpdateALSFiber ALS assayI did some work on the PSL table today.