  9597   Tue Feb 4 17:40:19 2014 manasaUpdateGeneralReady for pump down??

    

       
            
  
  9596   Tue Feb 4 16:43:50 2014 manasaUpdateGeneralIFO alignment update[EricQ, Manasa]
We are close to the end of the vent
except for a couple of issues.
  
  9595   Tue Feb 4 01:02:03 2014 KojiUpdateGreen LockingETMX green powerManasa, Steve: Please revisit the Xend
oven temperature again.
 Screenshot-Untitled_Window.png 
  9594   Tue Feb 4 00:42:18 2014 KojiUpdateGeneralX arm aligned for IR/GRThe
X arm was also aligned for the IR by hand
and ASS. Also the X end green PZT was aligned
  
  9593   Mon Feb 3 23:31:33 2014 ManasaUpdateGeneralAlignment update / Y arm locked[EricQ, Manasa, Koji]
We measured the spot positions on
the MC mirrors and redid the MC alignment
  
  9592   Mon Feb 3 15:57:52 2014 SteveUpdateGreen LockingETMX green powerThere was 0.2 mW green at the X end.
The doubling oven temp was changed
from 37.5 to 36 degrees C
 ETMXgreen.jpgXgreenOven36C.jpg 
  9591   Mon Feb 3 10:17:14 2014 SteveUpdatePEMdusty surfacesPlease wet WIPE  AP-ISCT.jpgBSC-rim.jpgITMX-ISCT.jpg12daysAtm.png 
  9590   Fri Jan 31 19:29:36 2014 GabrieleSummaryLSCPRC and SRC lengths Today we measured the missing distance
to reconstruct SRC length.
I also changed the way the mirror
 map_jan31st.pdfsurvey_v3.zip 
  9589   Fri Jan 31 18:41:25 2014 manasaUpdateGeneralIFO alignment update[EricQ, Gabriele, Manasa]
We found we had lost the Y arm pointing
from yesterday. We tried to recover the pointing
  
  9588   Thu Jan 30 19:00:25 2014 GabrieleSummaryLSCPRC length changed [Manasa,
EricQ, Gabriele]
Today
 map_jan30.pdfsurvey_v3_jan30.m 
  9587   Thu Jan 30 11:59:03 2014 manasaUpdateCDSfb timing was off

    

       
            
  
  9586   Wed Jan 29 21:01:03 2014 GabrieleSummaryLSCPRC length measurement analysis [Manasa,
EricQ, Gabriele]
We
 map.pdfscript.zip 
  9585   Wed Jan 29 16:36:37 2014 KojiSummaryGeneralHigh power beam blasting of the aLIGO RFPD [Rich, Jay, Koji]
We blasted the aLIGO RF PD with a
1W IR beam. We did not find any obvious damage.
  
  9584   Tue Jan 28 23:32:12 2014 KojiUpdateGeneralX/Y arm locked with the IR beam[Koji EricQ]
The both arms have been locked
with IR and aligned by ASS.
 good_alignment.png 
  9583   Tue Jan 28 22:24:46 2014 ericq UpdateGeneralFurther Alignment[Masasa, ericq]
Having no luck doing things remotely,
we went into the ITMX chamber and roughly
  
  9582   Tue Jan 28 16:26:40 2014 SteveUpdateVAC vacuum computers are back without safety

    

       
            
 c1vac1_vac2areback.png 
  9581   Tue Jan 28 11:13:50 2014 KojiUpdateVAC vacuum monitor is still blank[Steve Koji]
We
pushed the reset button of c1vac1 and c1vac2
  
  9580   Tue Jan 28 09:51:47 2014 SteveUpdateIOOlow power pointing 
PSL output is stable. 
 IOO4dlowpr.png 
  9579   Mon Jan 27 21:36:35 2014 ericq UpdateGeneralVent so farAfter turning the slow FSS threshold down,
the mode cleaner stays locked enough to do
other things. We were able to align the tip
  
  9578   Mon Jan 27 17:49:46 2014 ranaHowToComputer Scripts / Programssendmail started on nodus: fixing SwiftMail on DokuwikiSince the recent filesystem fracas, the
new accounts could not be created on nodus
/ dokuwiki (for the controls workshop, for
  
  9577   Mon Jan 27 12:26:00 2014 KojiUpdateIOOIOO Slow Actuator Servo threshold changedIn order to activate the slow actuator
servo for the MC locking, 
the threshold level for this servo
  
  9576   Mon Jan 27 09:08:00 2014 SteveUpdateVAC4 days at atmosphere 
 
 day4atm.pngvent76bgTp3d4.png 
  9575   Sat Jan 25 21:09:16 2014 gabrieleHowToLSCProcedure to measure PRC lengthI know the drawing is wrong.
I put random distances, not realistic ones,
and I did not try to get something close
  
  9574   Fri Jan 24 13:10:12 2014 JamieHowToLSCProcedure to measure PRC length

    

       
            
 path.pdf 
  9573   Fri Jan 24 12:44:25 2014 GabrieleHowToLSCProcedure to measure PRC lengthHere is how to measure the PRC length with
a set of distance measurements in the optical
setup. 
 8x 
  9572   Thu Jan 23 23:10:19 2014 ericq UpdateGeneralVent so far[ericq, Manasa, Jenne]
Summary: We opened up the
BS and both ITM chambers today, and put the
  
  9571   Thu Jan 23 13:23:10 2014 SteveUpdateVAC40m IFO is at atmosphere

    

       
            
  
  9570   Thu Jan 23 08:04:04 2014 SteveUpdateVACvacuum control screen is blank 
There is 
 pd76m170d2dRgaOn.png 
  9568   Wed Jan 22 20:00:41 2014 JenneUpdateGeneralVENT GO!Steve, please begin
the vent!!
 IFOstatus_lowPower_preVent.png 
  9567   Wed Jan 22 18:17:46 2014 JenneUpdateCDSfb timing was offSince this morning, the fb's timing has
been off.  Steve pointed it out to me
earlier today, but I didn't have a chance
  
  9566   Wed Jan 22 16:36:45 2014 ericqUpdateElectronicsRF distribution box power button fail

    

       
            
  
  9565   Wed Jan 22 15:24:11 2014 SteveSummaryVACRga scan after reboot

    

       
            
 Rgascan169dwarmingup.pngBlankMedmMustBeFixed.png 
  9564   Wed Jan 22 09:05:42 2014 GabrieleConfigurationLSCREFL11 back Yesterday night I plugged back the
REFL11 RF cable into the corresponding demodulation
board.
  
  9563   Tue Jan 21 19:41:59 2014 JenneUpdateElectronicsRF distribution box power button failRana, Gabriele and I are trying to measure
the FSR of the PRC (elog about that later),
and we turned off the power to the RF generation
  
  9562   Tue Jan 21 17:26:59 2014 JenneSummaryVACRebooted RGA computer and reset RGA settings[Jenne, Steve]
Steve noticed that the RGA was not
logging data and that not all the correct
  
  9561   Fri Jan 17 11:44:25 2014 GabrieleSummaryLSCMore length measurements, more confusion I analyzed the data taken yesterday. 
The AS11 data in PRMI configuration
is very bad, while the AS55 seems good enough:
 results_as11.pdfresults_as55.pdf 
  9560   Thu Jan 16 21:38:13 2014 ericqUpdateLSCRepeat of PRC length measurement[ericq,Jenne]
Since we don't have agreement between
the measurements we made the other day and
  
  9559   Thu Jan 16 08:19:29 2014 SteveUpdatePEM4.4 and 3.8M local earth quakes

    

       
            
 local4.4eq.pnglocal3.8eq.png 
  9558   Wed Jan 15 18:42:57 2014 JenneUpdateASCPOP ASC QPD offline for a few hours this afternoonI was in the lab, near the south end of
the ITMX oplev table, looking for something,
and I bumped the POP ASC QPD's power supply. 
  
  9557   Wed Jan 15 18:18:15 2014 GabrieleSummaryLSCPRC length measurement analysis I analyzed the data we took yesterday,
both using AS11 and AS55. For each value
of the phase I estimated the Q/P ratio using
 experimental_data_as11.pdfexperimental_data_as55.pdfsimulation_phase_difference.pdf 
  9556   Wed Jan 15 13:05:30 2014 JenneUpdatePEM4.4 EQ in Fontana, CAIt looks like there was a 4.4 magnitude
earthquake near Fontana, CA around 1:30am
today.  This tripped all of the suspension
  
  9555   Tue Jan 14 19:10:51 2014 GabrieleSummaryLSCPRC length measurement [EricQ, Gabriele]
We could carry out the measurement
of PRC length. The AS110 photodiode was plugged
  
  9554   Tue Jan 14 19:05:48 2014 GabrieleSummaryLSCPRMI locked on sideband[Gabriele, EricQ] 
Finally, we managed to lock PRMI
on sidebands:
  
  9553   Tue Jan 14 10:34:57 2014 SteveUpdatePSLgreen transmission measurmentGariLyn is using our green light on the
west side of the PSL table. The green PDA36As
were moved and the HEPA turned up to 60V
 greenPickUp.jpg 
  9552   Tue Jan 14 10:12:12 2014 SteveUpdatePSLlaser drift monitor set up idea

    

       
            
 bad4thday.png 
  9551   Mon Jan 13 19:31:04 2014 GabrieleSummaryLSCPRMI locking[Gabriele, EricQ]
We wanted to try the PRC length measurement,but
we ended up spending all the afternoon to
  
  9550   Mon Jan 13 16:50:55 2014 SteveUpdateVACMaglev controller needs service

    

       
            
  
  9549   Mon Jan 13 11:08:48 2014 SteveUpdatePSL3 good days of IOO pointing Three good days of IOO pointing:
Friday, Sat and Sun    What
was changed?  May be the clamping on
 3gdPSLpointing.png 
  9548   Sun Jan 12 09:57:24 2014 GabrieleSummaryLSCEffect of PRC length mismatch on error signals

    

       
            
  
  9547   Fri Jan 10 15:33:02 2014 SteveUpdatePSLlaser drift monitor set up idea

    

       
            
 2daysDrift.png 