Entry  Thu Jan 13 14:21:13 2011, josephb, Update, CDS, Webview of front end model files automated 
Entry  Tue Jan 11 18:41:43 2011, Jenne, Update, IOO, Put MC PZT offset onto MC board, instead of on awkward cart D040180-B.pdf
    Reply  Wed Jan 12 01:38:52 2011, Koji, Update, IOO, Put MC PZT offset onto MC board, instead of on awkward cart 
       Reply  Wed Jan 12 22:39:16 2011, Suresh, Update, IOO, Put MC PZT offset onto MC board, instead of on awkward cart P1120508.JPGP1120509.JPGD040180-B_with_5V_offset.pdf
Entry  Wed Jan 12 17:50:21 2011, josephb, Update, CDS, Worked on c1lsc, MC2 screens 
    Reply  Wed Jan 12 22:33:24 2011, kiwamu, Update, CDS, MC2 dewhitening are healthy except for UR 
Entry  Wed Jan 12 22:19:54 2011, Koji, Update, IOO, MC flakiness solved 
Entry  Wed Jan 12 17:22:47 2011, Suresh, Configuration, Locking, MC demod phase adjusted to minimise the I output TEK00000.PNG
Entry  Wed Jan 12 02:41:19 2011, kiwamu, Update, General, daytime tasks for tomorrow 
Entry  Tue Jan 11 01:05:29 2011, kiwamu, Update, LSC, obtained Xarm PDH signal 
    Reply  Wed Jan 12 01:39:49 2011, kiwamu, Update, LSC, locked X arm 
Entry  Tue Jan 11 21:08:19 2011, Joonho, Summary, Cameras, CCD cables upgrade plan. CCD_Cable_Upgrade_Plan_Jan11_2011.pdf
Entry  Tue Jan 11 17:08:43 2011, Suresh, Configuration, PSL, replaced the pzt-steering mirror on PSL 
Entry  Tue Jan 11 16:04:17 2011, josephb, Update, CDS, Script to update web views of models for all installed front ends 
Entry  Tue Jan 11 14:05:11 2011, josephb, Update, Computers, Martian host table updated daily 
Entry  Tue Jan 11 11:39:45 2011, steve, Update, VAC, RGA is turned on pd70d22.jpg
Entry  Tue Jan 11 11:19:13 2011, josephb, Summary, CDS, Storing FE harddrives down Y arm 
Entry  Mon Jan 10 16:47:08 2011, josephb, alex, rolf, Update, CDS, Fixed c1lsc dolphin reflected memory 
Entry  Mon Jan 10 16:39:36 2011, josephb, alex, rolf, Update, CDS, New Time server for frame builder and 1PPS 
Entry  Sun Jan 9 15:50:55 2011, rana, HowTo, PSL, Setting the PMC gain Untitled.png
Entry  Sat Jan 8 23:18:03 2011, rana, Update, Computers, network table 
Entry  Wed Dec 8 12:26:56 2010, josephb, Update, CDS, megatron set up - as a test front end 
    Reply  Sat Jan 8 21:12:12 2011, rana, Update, CDS, Megatron is back megatron.jpgsysinfo.text
Entry  Fri Jan 7 15:17:37 2011, steve, Update, Cameras, ITMX video monitor has tower wide view 
Entry  Fri Jan 7 12:01:39 2011, Osamu, Update, Computers, c1lsc running 
Entry  Fri Jan 7 00:49:16 2011, Jenne, Update, Green Locking, Recovered Xarm Green Lock, Preparation for Beat Note Measurement 
Entry  Fri Jan 7 00:14:36 2011, kiwamu, Update, IOO, EOM triple resonant box is working 
Entry  Sat Dec 18 06:24:49 2010, rana, Update, elog, restarted 
    Reply  Sat Dec 18 23:33:06 2010, Koji, Update, elog, restarted 
       Reply  Sun Dec 19 11:19:42 2010, Koji, Update, elog, restarted 
          Reply  Sun Dec 19 22:45:28 2010, rana, Update, elog, restarted 
          Reply  Wed Jan 5 10:45:51 2011, Koji, Update, elog, restarted 
             Reply  Thu Jan 6 10:47:11 2011, Koji, Update, elog, ELOG fixed (re: restarted) 
Entry  Wed Jan 5 23:22:00 2011, Jenne, Update, Cameras, Aligned the Xarm, no big deal DSC_2822.JPGKiwamuJenne_5Jan2011_Xarm_Aligned.png
    Reply  Wed Jan 5 23:37:12 2011, rana, Update, Cameras, Aligned the Xarm, no big deal 
       Reply  Wed Jan 5 23:45:33 2011, Jenne, Update, Cameras, Aligned the Xarm, no big deal 
          Reply  Thu Jan 6 00:03:05 2011, Koji, Update, Cameras, Aligned the Xarm, no big deal 
          Reply  Thu Jan 6 00:06:01 2011, Jenne, Update, IOO, Magical absorbing PZT mirror 
Entry  Wed Jan 5 00:23:30 2011, rana, Summary, DAQ, FrameBuilder fails in a new way 
    Reply  Wed Jan 5 16:00:11 2011, rana, alex, Summary, DAQ, FrameBuilder fails in a new way 
       Reply  Wed Jan 5 22:14:41 2011, rana, Summary, DAQ, FrameBuilder fails in a new way Screen_shot_2011-01-05_at_10.13.21_PM.png
Entry  Wed Jan 5 21:19:29 2011, Zach, Update, elog, restarted 
Entry  Tue Jan 4 21:21:57 2011, kiwamu, Update, IOO, PZTs are connected to c1iscaux Screenshot20110104.png
    Reply  Wed Jan 5 16:11:17 2011, kiwamu, Summary, IOO, temporary PZT connection PZTconnection.png
Entry  Tue Jan 4 02:58:53 2011, Jenne, Update, IOO, Power into Mode Cleaner increased 
    Reply  Tue Jan 4 11:06:32 2011, Koji, Update, IOO, Power into Mode Cleaner increased 
       Reply  Tue Jan 4 13:57:48 2011, kiwamu, Update, IOO, incident mirror changed from 45deg to 0 deg 
          Reply  Wed Jan 5 03:06:02 2011, kiwamu, Update, IOO, beam spots on MC mirrors 
       Reply  Tue Jan 4 18:37:18 2011, Jenne, Update, IOO, MCWFS aligned 
Entry  Tue Jan 4 15:12:33 2011, Suresh, Update, IOO, MC Trans Mon QPD gain decreased by 10 
Entry  Wed Dec 29 18:53:11 2010, rana, Summary, elog, found hung - restarted 
    Reply  Mon Jan 3 10:32:27 2011, kiwamu, Summary, elog, found hung - restarted 
Entry  Wed Dec 8 14:51:09 2010, josephb, Update, CDS, c1pem now recording data 
    Reply  Sat Jan 1 19:13:40 2011, rana, Update, CDS, c1pem now recording data Untitled.png
Entry  Sat Jan 1 16:36:16 2011, rana, Configuration, SUS, rampdown.pl was not running 
Entry  Thu Dec 23 22:13:50 2010, Koji, Update, General, PZT HV turned on 
    Reply  Fri Dec 31 12:41:02 2010, rana, Update, General, IR flashes Untitled.png
Entry  Fri Dec 24 09:01:33 2010, josephb, Update, CDS, Borrowed ADC 
Entry  Thu Dec 23 12:19:43 2010, kiwamu, Update, Green Locking, installed doubling oven base at PSL table DSC_2820_ss.jpgDSC_2814_ss.jpgDSC_2815_ss.jpg
    Reply  Thu Dec 23 18:51:37 2010, rana, Update, Green Locking, installed doubling oven base at PSL table 
Entry  Wed Dec 22 17:24:50 2010, steve, Configuration, VAC, slow pumpdown at 12 hours slowpd12h.jpg
    Reply  Wed Dec 22 21:38:47 2010, kiwamu, Configuration, VAC, Re:slow pumpdown at 12 hours 
    Reply  Thu Dec 23 13:30:09 2010, steve, Configuration, VAC, slow pumpdown complete slow2dpd.jpg
Entry  Thu Dec 23 08:54:32 2010, Suresh, Update, elog, the delhi univ syndrome 
Entry  Tue Dec 21 08:26:08 2010, rana, Update, elog, elogd is getting killed by Suresh 
    Reply  Wed Dec 22 06:50:19 2010, rana, Update, elog, elogd is getting killed by Suresh 
       Reply  Thu Dec 23 03:15:11 2010, Koji, Update, elog, elogd is getting killed by Suresh 
Entry  Wed Dec 22 15:47:22 2010, Koji, Update, VAC, Tank closing procedure 
Entry  Wed Dec 22 15:30:47 2010, Osamu, Update, ASC, ETMY oplev fixed 
Entry  Wed Dec 22 11:24:23 2010, haixing, Update, SUS, measurement of imbalance in quadrant maglev protope config_2x2.png
Entry  Tue Dec 21 16:34:42 2010, kiwamu, Summary, VAC, All the test masses have been wiped 
Entry  Tue Dec 21 16:20:09 2010, steve, Configuration, VAC, pumpdown has started 
Entry  Tue Dec 21 11:52:58 2010, josephb, Update, Computers, RGA scripts fixed, c0rga fixed 
Entry  Mon Dec 20 10:47:29 2010, Koji, Update, IOO, Plan for closing the vacuum chambers 
    Reply  Mon Dec 20 16:57:58 2010, steve, Update, IOO, checking out & closing the vacuum chambers 
       Reply  Mon Dec 20 23:32:58 2010, kiwamu, Update, IOO, Re:checking out & closing the vacuum chambers 
    Reply  Mon Dec 20 22:56:20 2010, Jenne, Update, IOO, Plan for closing the vacuum chambers 
Entry  Mon Dec 20 23:10:25 2010, Jenne, Update, SUS, Pretty much ready for pump-down. A few final things.... 
Entry  Thu Dec 16 15:10:18 2010, josephb, kiwamu, Update, CDS, ETMY working at the expense of ETMX 
    Reply  Fri Dec 17 02:22:06 2010, kiwamu, Update, CDS, ETMY damping: not good 
       Reply  Mon Dec 20 10:06:36 2010, kiwamu, Update, CDS, ETMY damped 2010Dec18.png
Entry  Fri Dec 17 00:55:30 2010, Koji, Update, IOO, The dark port beams reached the AP table 
    Reply  Sat Dec 18 01:17:04 2010, kiwamu, Update, IOO, some more alignments 
Entry  Fri Dec 17 00:30:05 2010, Koji, Update, IOO, ITMY / SRM / BS / PRM OPLEVs aligned 
    Reply  Fri Dec 17 03:37:47 2010, rana, Update, SUS, ITMY / SRM / BS / PRM OPLEVs aligned 
Entry  Thu Dec 16 10:52:42 2010, josephb, Update, Cameras, New PoE digital cameras basler.jpg