  3411   Thu Aug 12 16:52:02 2010 RazibUpdatePhase CameraSideband power measurement (updated)

I made some measurement of the SCR (signal to contrast ratio) from the signal from the EOM and the AOM.

The recipe for that was:

1. Trigger the camera at 20 Hz (from function generator).

2. Take a series of 20 images.

3. Do FFT to take out the DC component.

4. Extract the beat signal out of the FFT'd data.

5. Block the EOM.

6. Take another set of images of the AOM beam.

7. Take more(!) images, but this time of the background (blocking both EOM and AOM).

 

So the SCR is calculated by the ratio of the FFT'd DC and the 5 Hz signal. Using the CCD, I obtained the SCR to be 0.075 ± 0.01. Previously, we expected our SCR to be 0.09 as in the previous e-log entry.

The plot for that is:

SCR.jpg

 After measuring the SCR, I also measured the amplitude of the sideband and made an amplitude profile of the 40 MHz sideband.

The amplitude measurement is done as follows:

We know that the our 5 Hz signal consists of,

Sig = A_r * A_sb    where A_r = amplitude of the reference beam, A_sb= amplitude of the sideband

So, A_sb = Sig / A_r .

But,  A_r = sqrt ( P_AOM - Background),

Thus  A_sb = Sig / sqrt( P_AOM - Background) .

So the amplitude profile is done by taking the 5 Hz beat signal and dividing by the square root of the AOM beam minus the background light.

The plots looks like this:

DC_sig_sideband_profile.jpg

The solo sideband profile looks like this:

sideband_profile.jpg

Next we plan to trigger the camera with a 1 KHz signal and take snaps at n* T/4 (where n=0,1,2,3) of the period of the beat signal. So the plan is to trigger the camera at the point where the red dots appear in following cartoon.

sine_trig.jpg

Some more details of this setup will be posted later.

  

Quote:
 

 

Attachment 4: sine_trig.jpg
sine_trig.jpg
  3412   Thu Aug 12 17:10:07 2010 KojiUpdatePhase CameraSideband power measurement (updated)

This sounds very relieving although this could be a lower bound of the number.
Why didn't you use the output on the PD which just give us the direct observation of your so-called SCR.

Ed: I meant time series of the PD output

Quote:

So the SCR is calculated by the ratio of the FFT'd DC and the 5 Hz signal. Using the CCD, I obtained the SCR to be 0.075 ± 0.01. Previously, we expected our SCR to be 0.09 as in the previous e-log entry. 

 

  3413   Thu Aug 12 17:28:28 2010 RazibUpdatePhase CameraSideband power measurement (updated)

Quote:

This sounds very relieving although this could be a lower bound of the number.
Why didn't you use the output on the PD which just give us the direct observation of your so-called SCR.

Quote:

So the SCR is calculated by the ratio of the FFT'd DC and the 5 Hz signal. Using the CCD, I obtained the SCR to be 0.075 ± 0.01. Previously, we expected our SCR to be 0.09 as in the previous e-log entry. 

 

 The SCR was at first measured using the output of the PD. That was exactly from where we got our 0.09 (previous elog entry). The second measurement was from the CCD.

  50   Thu Nov 1 19:53:02 2007 Andrey RodionovBureaucracyPhotosTobin's picture
Attachment 1: DSC_0053.JPG
DSC_0053.JPG
  51   Thu Nov 1 19:53:34 2007 Andrey RodionovBureaucracyPhotosRobert's photo
Attachment 1: DSC_0068.JPG
DSC_0068.JPG
  52   Thu Nov 1 19:54:22 2007 Andrey RodionovBureaucracyPhotosRana's photo
Attachment 1: DSC_0120.JPG
DSC_0120.JPG
  53   Thu Nov 1 19:55:03 2007 Andrey RodionovBureaucracyPhotosAndrey's photo
Attachment 1: DSC_0055.JPG
DSC_0055.JPG
  54   Thu Nov 1 19:55:59 2007 Andrey RodionovBureaucracyPhotosAndrey, Tobin, Robert - photo
Attachment 1: DSC_0092.JPG
DSC_0092.JPG
  55   Thu Nov 1 19:58:07 2007 Andrey RodionovBureaucracyPhotosSteve and Tobin's picture
Attachment 1: DSC_0023.JPG
DSC_0023.JPG
  56   Thu Nov 1 20:03:00 2007 Andrey RodionovSummaryPhotosProcedure "Drop and Drag" in pictures
Attachment 1: DSC_0072.JPG
DSC_0072.JPG
Attachment 2: DSC_0083.JPG
DSC_0083.JPG
Attachment 3: DSC_0099.JPG
DSC_0099.JPG
Attachment 4: DSC_0100.JPG
DSC_0100.JPG
  210   Fri Dec 21 20:32:25 2007 tobinUpdatePhotosGigE camera
I couldn't resist any longer: I plugged in the Prosilica GC 750 GigE camera and took it for a spin. This is the little CMOS camera which sends out video over gigabit ethernet.

There were no difficulties at all in getting it running. I just plugged in the power, plugged in ethernet, and put on a lens from Steve's collection. I downloaded the "Sample Viewer" from the Prosilica website and it worked immediately.

It turns out that "Kirk's" computer has not only a gigabit ethernet card, but a little gigabit ethernet switch. I plugged the camera into this switch. The frame rate is amazing. With the camera under fluorescent lights I thought I saw some wacky automatic gain control, but I think this ~10Hz flicker is aliasing of the 60 Hz room lighting.

I put the camera on the PSL table briefly and tried viewing the image from a laptop over the (54mbs) wireless network. This didn't work so well: you could get a couple frames out of the camera, but then the client software would complain that it had lost communications. It appeared that scattered 1064nm light did show up brightly on the camera image. There is a green ethernet cable currently stashed on the roof of the PSL that appears unused. We can try mounting the gigE CMOS cable in place of one of the CCD video cameras.

I did not try the Linux software.

The camera is currently set up at Kirk's desk, using the cool little tripod Rana got from CyberGuys.

This camera looks very promising! Also, in the test image attached below, a very unusual condition has been documented.
Attachment 1: robs_desk.png
robs_desk.png
  243   Wed Jan 16 19:57:49 2008 tobinConfigurationPhotosISCT_EX
Here's a photo of the ISCT_EX table, for the purpose of planning our auxiliary laser arm locking scheme. Note the (undumped!) beam from the beamsplitter before QPDX (the leftmost gold-colored box); perhaps we could inject there.
Attachment 1: trx-annotated-small.jpg
trx-annotated-small.jpg
  413   Thu Apr 3 19:27:50 2008 AndreySummaryPhotosTour for prospective grad students
Last Friday (March 28), there was a tour of 40-meter lab for prospective graduate students.

Rana showed to the prospective students the interferometer. See pdf-attachment with pictures (two pictures of Rana with undergraduates (I took them) and two old pictures which I discovered on the memory card of Nikon d-40, it was not me who took those two last pictures).
Attachment 1: Rana_Lecturing.pdf
Rana_Lecturing.pdf Rana_Lecturing.pdf Rana_Lecturing.pdf Rana_Lecturing.pdf
  505   Thu May 29 16:49:49 2008 steveBureaucracyPhotosYoichi has arrived
Yoichi had his first 40m meeting. We welcomed him and Tobin, who is visiting, by sugar napoleons that
Bob made.
Attachment 1: yoichi.png
yoichi.png
Attachment 2: bobsn.png
bobsn.png
  549   Fri Jun 20 08:30:27 2008 stivUpdatePhotos40m summer line up 2008
atm1: John, Alberto, Yoichi, Koji, Masha, and Sharon

atm2: surf students Max of CIT, Sharon of MIT, Masha of Harvard, Eric of CIT not shown
Attachment 1: P1020559.png
P1020559.png
Attachment 2: P1020560.png
P1020560.png
  652   Wed Jul 9 15:04:22 2008 steveMetaphysicsPhotosSURFs helping hands
Surf students are helping out with baffle cleaning.
Attachment 1: surfjob.png
surfjob.png
  792   Mon Aug 4 16:20:20 2008 DmassConfigurationPhotosITMX magnet position relative to OSEMS
We have vented, and taken the following pics of the magnets to document their position before we ruin everything.
Attachment 1: DSC_0151.JPG
DSC_0151.JPG
Attachment 2: DSC_0150.JPG
DSC_0150.JPG
  819   Sun Aug 10 16:57:02 2008 ranaSummaryPhotosPhotos from Vent 8/4 - 8/8
http://www.ligo.caltech.edu/~rana/40m/VentAug08/

I've added the D40 pictures from last week to this web page. I have done some cropping and
rotating to make things look better.

On page 3, there are some over head shots of the Michelson area so that one can use screw holes
to judge what the spacing between the suspensions is and also possibly the cavity lengths. Lets
also remember to measure the ITM-BS distance accurately using a tape measure or ruler while we
have the thing open.
  1094   Mon Oct 27 11:23:10 2008 steveUpdatePhotosnew Olympus camera with IR vision
The IR blocker was removed from our new Olympus camera
SP 570UZ camera.
It has image stabilization, zoom 26-520 mm (20x optical)
and 10.7 Mpixel
Attachment 1: IRisin.JPG
IRisin.JPG
  1717   Tue Jul 7 15:08:49 2009 KojiSummaryPhotos40 high school students visited 40M

Alan and Alberto conducted a tour of 40 high-school students.
It may be the same tour that Rana found a spare PMC during the tour explanation as far as I remember...

Attachment 1: IMG_1848.jpg
IMG_1848.jpg
  1931   Thu Aug 20 09:16:32 2009 steveHowToPhotosControl Room Workstation desks lowered to human height

Quote:

There were no injuries...Now we need to get some new chairs.

 The control room desk tops heights on the east side were lowered by 127 mm

 

Attachment 1: P1040788.png
P1040788.png
Attachment 2: P1040782.png
P1040782.png
Attachment 3: P1040786.png
P1040786.png
Attachment 4: P1040789.png
P1040789.png
Attachment 5: P1040785.png
P1040785.png
  1998   Thu Sep 24 19:35:20 2009 ranaHowToPhotos40m Google account

I've created a 40m Google account. Please post all the 40m related photos to this site. If you don't already have it, download Picasa to make this easier.

40m Installation Photos">

the password is in the usual password place.

  2242   Wed Nov 11 18:43:57 2009 rana, kojiHowToPhotosIlluminated Paintbrush Technique

IMG_0215.JPGIMG_0214.JPG

1/4" exposure, standard room lights                                                                              3" exposure, slowly moving LED bar light from ~60 cm distance

Note:
Because of the light behind, the focus was attracted by the far objects...
Evenso the magnet ball looks better in the right picture.

The technique is as follows:
Use longer exposure time, move the LED bar illumination through the area like painting the light everywhere.
It is supposed to provide a picture with more uniform light and the diminished shadow.

(KA)

  2465   Tue Dec 29 13:57:20 2009 Rana, Kiwamu, and HaixingUpdatePhotosPhotos of video switch box

Before we installed the video switch box, we also took some photos of it. We uploaded them onto the 40m Picasa.

Video Matrix

The first photo is the an entire view of the switch box. The following four photos are the details of the switch matrix.

 The slideshow below is a dump of the last several months of photos from the Olympus. The originals have been deleted.

  2956   Thu May 20 12:10:44 2010 kiwamuUpdatePhotosETMY end table

 I updated the photo of ETMY end table on the wiki.

http://lhocds.ligo-wa.caltech.edu:8000/40m/Optical_Tables

Attachment 1: ETMY_s.png
ETMY_s.png
  3093   Mon Jun 21 14:21:34 2010 Jenne, KiwamuUpdatePhotosInspection of Magnets for the TTs

Some pictures of "magnet inspection" from Picasa.

The coating of some magnets are chipped...

  3095   Mon Jun 21 20:11:21 2010 KojiUpdatePhotosInspection of Magnets for the TTs

Were these magnets chipped before the Ni plating?

RA: Yes, it looks like this is the case. We also smashed some of the magnets against a metal surface and saw that a black grime was left. We should hold the magnets with a clean teflon clamp to measure the Gauss. Then we have to wipe the magnets before installing. I share Jenne's concern about the press-fit damaging the plating and so we need to consider using using glue or the ole magnetic attachment method. We should not rely on the structural integrity of the magnets at all.

  3105   Wed Jun 23 12:52:35 2010 kiwamuUpdatePhotosBS chamber before cleaning up

  3421   Fri Aug 13 15:29:35 2010 AidanFrogsPhotosHere's the 40m team
Attachment 1: 40m_team.JPG
40m_team.JPG
  3424   Mon Aug 16 13:33:06 2010 ZachFrogsPhotosHere's the 40m team

 One day I'll get to be part of the krew

  3682   Fri Oct 8 17:36:16 2010 steveFrogsPhotosvisiting undergrads

Prof Alan Weistein guided the 24 student through the 40m. His performance was rated as  an enthusiastic 9.5

Attachment 1: P1060916.JPG
P1060916.JPG
Attachment 2: P1060921.JPG
P1060921.JPG
Attachment 3: P1060922.JPG
P1060922.JPG
Attachment 4: P1060915.JPG
P1060915.JPG
  3683   Sun Oct 10 16:44:59 2010 KojiOmnistructurePhotosKepco Tube HV supply
Attachment 1: IMG_3637.jpg
IMG_3637.jpg
Attachment 2: IMG_3640.jpg
IMG_3640.jpg
  3987   Fri Nov 26 16:37:29 2010 kiwamuUpdatePhotospictures on PIcasa

 I uploaded some pictures taken in the last and this week. They are on the Picasa web albums.

 in vac work [Nov. 18 2010]

 in vac work [Nov 23 2010]

 CDS work [Nov 24 2010]

 DSC_2657_ss.jpg

  4257   Mon Feb 7 19:21:32 2011 Beard PapaMetaphysicsPhotosThe Adventures of Dr Stochino and Beard Papa

  4430   Wed Mar 23 09:54:46 2011 steveOmnistructurePhotosLSC visitors

The 40m lab was visited by  ~ 30 LSC members  the end of last week.

Attachment 1: P1070467.JPG
P1070467.JPG
Attachment 2: P1000414.jpg
P1000414.jpg
  4447   Mon Mar 28 16:19:23 2011 steveFrogsPhotosvisithing 5th graders

Suresh is captivating his audience with gravity waves on last Friday, March 25

Attachment 1: P1070475.JPG
P1070475.JPG
  4597   Mon May 2 13:43:05 2011 steveFrogsPhotosbirthday boys

.....Happy.... Birthday.... to.... Joseph... and... Jamie...Happy....Birthday..... to.... You............sing with us........Happy Birthday.....to you

Attachment 1: P1070622.JPG
P1070622.JPG
  4615   Tue May 3 15:59:22 2011 steveFrogsPhotosX-mas comes early

The little red all terrain cargo wagon 40" x 18"  has just arrived on pneumatic wheels.

Model #29, 200 lbs max load at 26 PSI,  minimum age requirement 1.5 years

Attachment 1: P1070634.JPG
P1070634.JPG
  4722   Sun May 15 19:55:15 2011 kiwamuUpdatePhotosETMY optical bench

Just for a record. This is the latest picture of the ETMY optical bench.

I will upload this picture on the wiki after the wiki gets up.

ETMY_ss.jpg

  4723   Sun May 15 21:27:51 2011 JenneUpdatePhotosETMY optical bench

I didn't notice it the other day when I was working on putting in the trans QPD, but do we need to switch the mirror mount for the first turning mirror of the IR trans beam, which the green transmits through to go into the cavity?  It seems like we've set ourselves up for potential clipping.

Quote:

Just for a record. This is the latest picture of the ETMY optical bench.

I will upload this picture on the wiki after the wiki gets up.

ETMY_ss.jpg

 

  4724   Mon May 16 10:05:02 2011 kiwamuUpdatePhotosRe:ETMY optical bench

You are right. We should change or rotate the mirror mount.

Actually when Suresh and I were putting the mirror we rotated the mount  by 90 deg such that the fat side of the mount is at left had side.

It was because the fat side had been clipping the oplev beam when the fat side is at right.

At that moment we were blocking the green beam to only see the faint IR beam with a sensor card, so we haven't checked the green beam.

Anyway the mount is apparently not good for the green beam.

Quote from #4723

I didn't notice it the other day when I was working on putting in the trans QPD, but do we need to switch the mirror mount for the first turning mirror of the IR trans beam, which the green transmits through to go into the cavity?  It seems like we've set ourselves up for potential clipping.

 

  4814   Tue Jun 14 09:24:36 2011 steveConfigurationPhotosSUS binary IO chassis 2 and 3 moved from 1X5 to 1X4

Quote:

While preping 1X4 for installation of c1lsc, we removed some old VME crates that were no longer in use.  This freed up lots of space in 1X4.  We then moved the SUS binary IO chassis 2 and 3, which plug into the 1X4 cross-connect, from 1X5 into the newly freed space in 1X4.  This makes the cable run from these modules to the cross connect much cleaner.

 Are we keeping these?

Attachment 1: P1070891.JPG
P1070891.JPG
Attachment 2: P1070893.JPG
P1070893.JPG
  4891   Mon Jun 27 16:57:06 2011 steveUpdatePhotosHaixing is back

He has moved the levitation stuff for his surf student to Jan's lab in W-Bridge.

Attachment 1: P1070914.JPG
P1070914.JPG
  5329   Wed Aug 31 14:50:18 2011 kiwamuUpdatePhotospictures of OSEMs

The pictures that we took are now on the Picasa web site. Check it out.

Quote from #5280

Also, we took photos (to be posted on Picasa in a day or two) of all the main IFO magnet-in-OSEM centering, as best we could.  SRM, BS, PRM all caused trouble, due to their tight optical layouts.  We got what we could.

  5792   Wed Nov 2 22:02:39 2011 JenneUpdatePhotosNew screen snapshot script written!

After lots of trial and error, and a little inspiration from Koji, I have written a new script that will run when you select "update snapshot" in the yellow ! button on any MEDM screen. 

Right now, it's only live for the OAF_OVERVIEW screen.  View snapshot and view prev snapshot also work. 

Next on the list is to make a script that will create the yellow buttons for each screen, so I don't have to type millions of things in by hand.

The script lives in:  /cvs/cds/rtcds/caltech/c1/scripts/MEDMsnapshots, and it's called....wait for it....... "updatesnap".

 

  5793   Thu Nov 3 13:00:52 2011 JenneUpdatePhotosFormatting of MEDM screen names

Quote:

After lots of trial and error, and a little inspiration from Koji, I have written a new script that will run when you select "update snapshot" in the yellow ! button on any MEDM screen. 

Right now, it's only live for the OAF_OVERVIEW screen.  View snapshot and view prev snapshot also work. 

Next on the list is to make a script that will create the yellow buttons for each screen, so I don't have to type millions of things in by hand.

The script lives in:  /cvs/cds/rtcds/caltech/c1/scripts/MEDMsnapshots, and it's called....wait for it....... "updatesnap".

 Currently the update snapshot script looks at the 3 letters after "C1" to determine what folder to put the snapshots in.  (It can also handle the case when there is no C1, ex. OAF_OVERVIEW.adl still goes to the c1oaf folder).  If the 3 letters after C1 are SYS, then it puts the snapshot into /opt/rtcds/caltech/c1/medm/c1sys/snap/MEDM_SCREEN_NAME.adl

Mostly this is totally okay, but a few subsystems seem to have incongruous names.  For example, there are screens called "C1ALS...." in the c1gcv folder.  Is it okay if these snapshots go into a /c1als/snap folder, or do I need to figure out how to put them in the exact same folder they currently exist in?  Or, perhaps, why aren't they just in a c1als folder to begin with? It seems like we just weren't careful when organizing these screens.

Another problem one is the C1_FE_STATUS.adl screen.  Can I create a c1gds folder, and rename that screen to C1GDS_FE_STATUS.adl?  Objections?

 

  6184   Tue Jan 10 09:17:23 2012 steveUpdatePhotosstrawman's visiters
Attachment 1: P1080491.JPG
P1080491.JPG
Attachment 2: P1080492.JPG
P1080492.JPG
  6904   Mon Jul 2 18:28:09 2012 JenneUpdatePhotosMany photos taken

Many photos were taken by many different people....most of the fuzzy ones are by yours truely (doing a reach-around to get to hard-to-reach places), so sorry about that.

I put all the photos from yesterday and today into 6 new albums on Picasa:  https://picasaweb.google.com/foteee

The album titles are generally descriptive, and I threw in a few comments where it seemed prudent.

Big note:  The tip tilt on the ITMX table does, in fact, have the arrow pointing in the correct direction.  Photo is in the TT album from today.

  13501   Wed Jan 3 18:00:46 2018 gautamUpdatePonderSqueezeplan of action

Notes of stuff we discussed @ today's meeting, and afterwards, towards measuring ponderomotive squeezing at the 40m.

  1. Displacement noise requirements
    • Kevin is going to see if we can measure any kind of squeezing on a short timescale by tuning various parameters.
    • Specifically, without requiring crazy ultra low current noise level for the coil driver noise.
  2. Investigate how much actuation range we need for lock acquisition and maintaining lock.
    • Specifically, for DARM.
    • We will measure this by having the arms controlled with ALS in the CARM/DARM basis.
    • Build up a noise budget for this, see how significant the laser noise contribution is.
  3. RC folding mirrors
    • In the present configuration, these are introducing ~2.5% RT loss in the RCs.
    • This affects PRG, and on the output side, measurable squeezing.
    • We want to see if we can relax the requirements on the RC folding mirrors such that we don't have to spend > 20 k$.
    • Specifically, consider spec'ing the folding mirror coatings to only have HR @1064 nm, and take what we get at 532 nm.
    • But still demand tolerances on RoC driven by mode-matching between the RCs and the arm cavities.
  4. ALS with Beat Mouth
    • Use the fiber coupled light from the ends to make the ALS signals.
    • Gautam will update diagram to show the signal chain from end-to-end (i.e. starting at AUX laser, ending at ADC input).
    • Make a noise budget for the same - preliminary analysis suggests a sensing noise floor of ~10 mHz/rtHz.

RXA:

  • For the ALS-DARM budget the idea is that we can do lock acquisition better, so we don't need to care about the acquisition reqs. i.e. we just need to set the ETM coil driver current range based on the DARM in-lock values.
    • To get the coil driver noise to be low enough to detect squeezing we need to use a ~10-15 kOhm series resistor.
    • We assume that all DAC and coil driver input noises can be sufficiently filtered.
    • We are assuming that we don't change the magnet sizes or the number of coil windings in the OSEMs.
    • The noise in the ITMs doesn't matter because we don't use them for any locking activity, so we can easily set the coil driver series resistors to 15 kOhm.
    • We will do the bias for the ETMs and ITMs using some HV circuit (not the existing ones on the coil driver boards) and doing the summation after the main coil driver series resistor. This HV bias module needs to handle the ~ (2 V / 400 Ohm) = 5 mA which is now used. This would require (5 mA) x (15 kOhm) = 60+ V drivers.
  • IF we can get away with doing the ALS beat note with just red (still using GREEN light from the end laser to lock to the arms from the ends), we will not have any requirements for the 532 nm transmission of any optics in the DRMI area.
    • Get some quotes for the new PR/SR mirrors having tight RoC tolerance, high R for 1064, and no spec for 532.
    • Check that the 1-way fiber noise for 1064 nm is < 100 mHz/rHz in the 50-1000 Hz band. If its more, explore putting better acoustic foam around the fiber run.
    • Improve the mode-matching of the IR beam into the fibers at the ends. We want >80% to reduce the noise do to scattering; we don't really care about the amount of light available in the PSL - this is just to reduce the IR-ALS noise.
  13508   Sat Jan 6 05:18:12 2018 KevinUpdatePonderSqueezeDisplacement requirements for short-term squeezing

I have been looking into whether we can observe squeezing on a short timescale. The simulations I show here say that we can get 2 dBvac of squeezing at about 120 Hz using extreme signal recycling.

The parameters used here are

  • 100 ppm transmissivity on the folding mirrors giving a PRC gain of 40.
  • 10 kΩ series resistance for the ETMs; 15 kΩ series resistance for the ITMs.
  • 1 W incident on the back of PRM.
  • PD quantum efficiency 0.88.

The first attachment shows the displacement noise. The red curve labeled vacuum is the standard unsqueezed vacuum noise which we need to beat. The second attachment shows the same noise budget as a ratio of the noise sources to the vacuum noise.

This homodyne angle and SRC detuning give about the maximum amount of squeezing. However, there's quite a bit of flexibility and if there are other considerations, such as 100 Hz being too low, we should be able to optimize these angles (even with more pessimistic values of the above parameters) to see at least 0.2 dBvac around 400 Hz.

Attachment 1: displacement_noise.pdf
displacement_noise.pdf
Attachment 2: noise_budget.pdf
noise_budget.pdf