16311
|
Thu Sep 2 20:47:19 2021 |
Koji | Update | CDS | Chiara DHCP restarted |
[Paco, Tega, Koji]
Once chiara's DHCP is back, things got much more straight forward.
c1iscex and c1iscey were rebooted and the IOPs were launched without any hesitation.
Paco ran rebootC1LSC.sh and for the first time in this year we had the launch of the processes without any issue. |
16312
|
Thu Sep 2 21:21:14 2021 |
Koji | Summary | Computers | Vacuum recovery 2 |
Attachment 1:
We are pumping the main volume with TP2. Once P1a reached the pressure ~2.2mtorr, we could open the PSL shutter. The TP2 voltage went up once but came down to ~20V. It's close to nominal now.
We wondered if we should use TP3 or not. I checked the vacuum pressure trends and found that the annulus pressures were going up. So we decided to open the annulus valves.
Attachment 2:
The current vacuum status is as shown in the MEDM screenshot.
There is no trend data of the valve status (sad) |
Attachment 1: Screenshot_2021-09-02_21-20-24.png
|
|
Attachment 2: Screenshot_2021-09-02_21-20-48.png
|
|
16316
|
Wed Sep 8 18:00:01 2021 |
Koji | Update | VAC | cronjobs & N2 pressure alert |
In the weekly meeting, Jordan pointed out that we didn't receive the alert for the low N2 pressure.
To check the situation, I went around the machines and summarized the cronjob situation.
[40m wiki: cronjob summary]
Note that this list does not include the vacuum watchdog and mailer as it is not on cronjob.
Now, I found that there are two N2 scripts running:
1. /opt/rtcds/caltech/c1/scripts/Admin/n2Check.sh on megatron and is running every minute (!)
2. /opt/rtcds/caltech/c1/scripts/Admin/N2check/pyN2check.sh on c1vac and is running every 3 hours.
Then, the N2 log file was checked: /opt/rtcds/caltech/c1/scripts/Admin/n2Check.log
Wed Sep 1 12:38:01 PDT 2021 : N2 Pressure: 76.3621
Wed Sep 1 12:38:01 PDT 2021 : T1 Pressure: 112.4
Wed Sep 1 12:38:01 PDT 2021 : T2 Pressure: 349.2
Wed Sep 1 12:39:02 PDT 2021 : N2 Pressure: 76.0241
Wed Sep 1 12:39:02 PDT 2021 : N2 pressure has fallen to 76.0241 PSI !
Tank pressures are 94.6 and 98.6 PSI!
This email was sent from Nodus. The script is at /opt/rtcds/caltech/c1/scripts/Admin/n2Check.sh
Wed Sep 1 12:40:02 PDT 2021 : N2 Pressure: 75.5322
Wed Sep 1 12:40:02 PDT 2021 : N2 pressure has fallen to 75.5322 PSI !
Tank pressures are 93.6 and 97.6 PSI!
This email was sent from Nodus. The script is at /opt/rtcds/caltech/c1/scripts/Admin/n2Check.sh
...
The error started at 11:39 and lasted until 13:01 every minute. So this was coming from the script on megatron. We were supposed to have ~20 alerting emails (but did none).
So what's happened to the mails? I tested the script with my mail address and the test mail came to me. Then I sent the test mail to 40m mailing list. It did not reach.
-> Decided to put the mail address (specified in /etc/mailname , I believe) to the whitelist so that the mailing list can accept it.
I did run the test again and it was successful. So I suppose the system can now send us the alert again.
And alerting every minute is excessive. I changed the check frequency to every ten minutes.
What's happened to the python version running on c1vac?
1) The script is running, spitting out some error in the cron report (email on c1vac). But it seems working.
2) This script checks the pressures of the bottles rather than the N2 pressure downstream. So it's complementary.
3) During the incident on Sept 1, the checker did not trip as the pressure drop happened between the cronjob runs and the script didn't notice it.
4) On top of them, the alert was set to send the mails only to an our former grad student. I changed it to deliver to the 40m mailing list. As the "From" address is set to be some ligox...@gmail.com, which is a member of the mailing list (why?), we are supposed to receive the alert. (And we do for other vacuum alert from this address).
|
16317
|
Wed Sep 8 19:06:14 2021 |
Koji | Update | General | Backup situation |
Tega mentioned in the meeting that it could be safer to separate some of nodus's functions from the martian file system.
That's an interesting thought. The summary pages and other web services are linked to the user dir. This has high traffic and can cause the issure of the internal network once we crash the disk.
Or if the internal system is crashed, we still want to use elogs as the source of the recovery info. Also currently we have no backup of the elog. This is dangerous.
We can save some of the risks by adding two identical 2TB disks to nodus to accomodate svn/elog/web and their daily backup.
host |
file system or contents |
condition |
note |
nodus |
root |
none or unknown |
|
nodus |
home (svn, elog) |
none |
|
nodus |
web (incl summary pages) |
backed up |
linked to /cvs/cds |
chiara |
root |
maybe |
need to check with Jon/Anchal |
chiara |
/home/cds |
local copy |
The backup disk is smaller than the main disk. |
chiara |
/home/cds |
remote copy - stalled |
we used to have, but stalled since 2017/11/17 |
fb1 |
root |
maybe |
need to check with Jon/Anchal |
fb1 |
frame |
rsync |
pulled from LDAS according to Tega |
|
|
|
|
|
16328
|
Tue Sep 14 17:14:46 2021 |
Koji | Update | SUS | SOS Tower Hardware |
Yup this is OK. No problem.
|
16331
|
Tue Sep 14 19:12:03 2021 |
Koji | Summary | PEM | Excess seismic noise in 0.1 - 0.3 Hz band |
Looks like this increase is correlated for BS/EX/EY. So it is likely to be real.
Comparison between 9/15 (UTC) (Attachment 1) and 9/10 (UTC) (Attachment 2) |
Attachment 1: C1-ALL_393F21_SPECTRUM-1315699218-86400.png
|
|
Attachment 2: C1-ALL_393F21_SPECTRUM-1315267218-86400.png
|
|
16333
|
Wed Sep 15 23:38:32 2021 |
Koji | Update | ALS | ALS ASX PZT HV was off -> restored |
It was known that the Y end ALS PZTs are not working. But Anchal reported in the meeting that the X end PZTs are not working too.
We went down to the X arm in the afternoon and checked the status. The HV (KEPCO) was off from the mechanical switch. I don't know this KEPCO has the function to shutdown the switch at the power glitch or not.
But anyway the power switch was engaged. We also saw a large amount of misalignment of the X end green. The alignment was manually adjusted. Anchal was able to reach ~0.4 Green TRX, but no more. He claimed that it was ~0.8.
We tried to tweak the SHG temp from 36.4. We found that the TRX had the (local) maximum of ~0.48 at 37.1 degC. This is the new setpoint right now. |
Attachment 1: P_20210915_151333.jpg
|
|
16334
|
Wed Sep 15 23:53:54 2021 |
Koji | Summary | General | Towards the end upgrade |
Ordered compoenents are in.
- Made 36 more Sat Amp internal boards (Attachment 1). Now we can install the adapters to all the 19 sat amp units.
- Gave Tega the components for the sat amp adapter units. (Attachment 2)
- Gave Tega the componennts for the sat amp / coil driver modifications.
- Made 5 PCBs for the 16bit DAC AI rear panel interface (Attachment 3) |
Attachment 1: P_20210915_231308.jpg
|
|
Attachment 2: P_20210915_225039.jpg
|
|
Attachment 3: P_20210915_224341.jpg
|
|
16335
|
Thu Sep 16 00:00:20 2021 |
Koji | Update | General | RIO Planex 1064 Lasers in the south cabinet |
RIO Planex 1064 Lasers in the south cabinet
Property Number C30684/C30685/C30686/C30687 |
Attachment 1: P_20210915_232426.jpg
|
|
16336
|
Thu Sep 16 01:16:48 2021 |
Koji | Update | General | Frozen 2 |
It happened again. Defrosting required. |
Attachment 1: P_20210916_003406_1.jpg
|
|
16341
|
Fri Sep 17 00:56:49 2021 |
Koji | Update | General | Awesome |
The Incredible Melting Man!
|
16342
|
Fri Sep 17 20:22:55 2021 |
Koji | Update | SUS | EQ M4.3 Long beach |
EQ M4.3 @longbeach
2021-09-18 02:58:34 (UTC) / 07:58:34 (PDT)
https://earthquake.usgs.gov/earthquakes/eventpage/ci39812319/executive
- All SUS Watchdogs tripped, but the SUSs looked OK except for the stuck ITMX.
- Damped the SUSs (except ITMX)
- IMC automatically locked
- Turned off the damping of ITMX and shook it only with the pitch bias -> Easily unstuck -> damping recovered -> realignment of the ITMX probably necessary.
- Done.
|
16344
|
Mon Sep 20 14:11:40 2021 |
Koji | Update | BHD | End DAC Adapter Unit D2100647 |
I've uploaded the schematic and PCB PDF for End DAC Adapter Unit D2100647.
Please review the design.
- CH1-8 SUS actuation channels.
- 5CHs out of 8CHs are going to be used, but for future extensions, all the 8CHs are going to be filled.
- It involves diff-SE conversion / dewhitening / SE-diff conversion. Does this make sense?
- CH9-12 PZT actuation channels. It is designed to send out 4x SE channels for compatibility. The channels have the jumpers to convert it to pass through the diff signals.
- CH13-16 are general purpose DIFF/SE channels. CH13 is going to be used for ALS Laser Slow control. The other 3CHs are spares.
The internal assembly drawing & BOM are still coming. |
Attachment 1: D2100647_End_DAC_Adapter.pdf
|
|
16350
|
Mon Sep 20 21:56:07 2021 |
Koji | Update | Computers | Wifi internet fixed |
Ug, factory resets... Caltech IMSS announced that there was an intermittent network service due to maintenance between Sept 19 and 20. And there seemed some aftermath of it. Check out "Caltech IMSS"
|
16376
|
Mon Oct 4 18:00:16 2021 |
Koji | Summary | CDS | c1teststand problems summary |
I don't know anything about mx/open-mx, but you also need open-mx,don't you?
controls@c1ioo:~ 0$ systemctl status *mx*
● open-mx.service - LSB: starts Open-MX driver
Loaded: loaded (/etc/init.d/open-mx)
Active: active (running) since Wed 2021-09-22 11:54:39 PDT; 1 weeks 5 days ago
Process: 470 ExecStart=/etc/init.d/open-mx start (code=exited, status=0/SUCCESS)
CGroup: /system.slice/open-mx.service
└─620 /opt/3.2.88-csp/open-mx-1.5.4/bin/fma -d
● mx_stream.service - Advanced LIGO RTS front end mx stream
Loaded: loaded (/etc/systemd/system/mx_stream.service; enabled)
Active: active (running) since Wed 2021-09-22 12:08:00 PDT; 1 weeks 5 days ago
Main PID: 5785 (mx_stream)
CGroup: /system.slice/mx_stream.service
└─5785 /usr/bin/mx_stream -e 0 -r 0 -w 0 -W 0 -s c1x03 c1ioo c1als c1omc -d fb1:0
|
16378
|
Mon Oct 4 20:46:08 2021 |
Koji | Update | Electronics | Satellite amp box adapters |
Thanks. You should be able to find the chassis-related hardware on the left side of the benchtop drawers at the middle workbench.
Hardware: The special low profile 4-40 standoff screw / 1U handles / screws and washers for the chassis / flat-top screws for chassis panels and lids |
16380
|
Tue Oct 5 17:01:20 2021 |
Koji | Update | Electronics | Sat Amp modifications |
Make sure the inputs for the PD amps are open. This is the current amplifier and we want to leave the input pins open for the test of this circuit.
TP6 is the first stage of the amps (TIA). So this stage has the issue. Usual check if the power is properly supplied / if the pins are properly connected/isolated / If the opamp is alive or not.
For TP8, if TP8 get railed. TP5 and TP7 are going to be railed too. Is that the case, if so, check this whitening stage in the same way as above.
If the problem is only in the TP5 and/or TP7 it is the differential driver issue. Check the final stage as above. Replacing the opamp could help.
|
16387
|
Thu Oct 7 02:04:19 2021 |
Koji | Update | Electronics | Satellite amp adapter chassis |
The 4 units of Satellite Amp Adapter were done:
- The ears were fixed with the screws
- The handles were attached (The stock of the handles is low)
- The boards are now supported by plastic stand-offs. (The chassis were drilled)
- The front and rear panels were fixed to the chassis
- The front and rear connectors were fixed with the low profile 4-40 stand-off screws (3M 3341-1S)
|
Attachment 1: P_20211006_205044.jpg
|
|
16397
|
Tue Oct 12 23:42:56 2021 |
Koji | Summary | CDS | Connected c1sus2 to martian network |
Don't you need to add the new hosts to /diskless/root/etc/rtsystab at fb1? --> There looks many elogs talking about editing "rtsystab".
controls@fb1:/diskless/root/etc 0$ cat rtsystab
#
# host list of control systems to run, starting with IOP
#
c1iscex c1x01 c1scx c1asx
c1sus c1x02 c1sus c1mcs c1rfm c1pem
c1ioo c1x03 c1ioo c1als c1omc
c1lsc c1x04 c1lsc c1ass c1oaf c1cal c1dnn c1daf
c1iscey c1x05 c1scy c1asy
#c1test c1x10 c1tst2
|
16404
|
Thu Oct 14 18:30:23 2021 |
Koji | Summary | VAC | Flange/Cable Stand Configuration |
Flange Configuration for BHD
We will need total 5 new cable stands. So Qty.6 is the number to be ordered.
Looking at the accuglass drawing, the in-vaccum cables are standard dsub 25pin cables only with two standard fixing threads.
https://www.accuglassproducts.com/sites/default/files/PDF/Partpdf/110070_3.pdf
For SOSs, the standard 40m style cable bracket works fine. https://dcc.ligo.org/D010194-x0
However, for the OMCs, we need to make the thread holes available so that we can mate DB25 male cables to these cables.
One possibility is to improvise this cable bracket to suspend the cables using clean Cu wires or something. I think we can deal with this issue in situ.
Ha! The male side has the 4-40 standoff (jack) screws. So we can hold the male side on the bracket using the standoff (jack) screws and plug the female cables. OK! The issue solved!
https://www.accuglassproducts.com/sites/default/files/PDF/Partpdf/110029_3.pdf |
Attachment 1: 40m_flange_layout_20211014.pdf
|
|
16408
|
Fri Oct 15 17:17:51 2021 |
Koji | Summary | General | Vent Prep |
I took over the vent prep: I'm going through the list in [ELOG 15649] and [ELOG 15651]. I will also look at [ELOG 15652] at the day of venting.
- IFO alignment: Two arms are already locking. The dark port beam is well overlapped. We will move PRM/SRM etc. So we don't need to worry about them. [Attachment 1]
scripts>z read C1:SUS-BS_PIT_BIAS C1:SUS-BS_YAW_BIAS
-304.7661529521767
-109.23924626857811
scripts>z read C1:SUS-ITMX_PIT_BIAS C1:SUS-ITMX_YAW_BIAS
15.534616817500943
-503.4536332290159
scripts>z read C1:SUS-ITMY_PIT_BIAS C1:SUS-ITMY_YAW_BIAS
653.0100945988496
-478.16260735781225
scripts>z read C1:SUS-ETMX_PIT_BIAS C1:SUS-ETMX_YAW_BIAS
-136.17863332517527
181.09285307121306
scripts>z read C1:SUS-ETMY_PIT_BIAS C1:SUS-ETMY_YAW_BIAS
-196.6200333695437
-85.40819256078339
- IMC alignment: Locking nicely. I ran WFS relief to move the WFS output on to the alignment sliders. All the WFS feedback values are now <10. Here is the slider snapshots. [Attachment 2]
- PMC alignmnet: The PMC looked like it was quite misaligned -> aligned. IMC/PMC locking snapshot [Attachment 3]
Arm transmissions:
scripts>z avg 10 C1:LSC-TRX_OUT C1:LSC-TRY_OUT
C1:LSC-TRX_OUT 0.9825591325759888
C1:LSC-TRY_OUT 0.9488834202289581
- Suspension Status Snapshot [Attachment 4]
- Anchal aligned the OPLEV beams [ELOG 16407]
I also checked the 100 days trend of the OPLEV sum power. The trend of the max values look flat and fine. [Attachment 5] For this purpose, the PRM and SRM was aligned and the SRM oplev was also aligned. The SRM sum was 23580 when aligned and it was just fine (this is not so visible in the trend plot).
- The X and Y green beams were aligned for the cavity TEM00s. Y end green PZT values were nulled. The transmission I could reach was as follows.
>z read C1:ALS-TRX_OUTPUT C1:ALS-TRY_OUTPUT
0.42343354488901286
0.24739624058377277
It seems that these GTRX and GTRY seemed to have crosstalk. When each green shutters were closed the transmissino and the dark offset were measured to be
>z read C1:ALS-TRX_OUTPUT C1:ALS-TRY_OUTPUT
0.41822833190834546
0.025039383697636856
>z read C1:ALS-TRX_OUTPUT C1:ALS-TRY_OUTPUT
0.00021112720155274818
0.2249448773499293
Note that Y green seemed to have significant (~0.1) of 1st order HOM. I don't know why I could not transfer this power into TEM00. I could not find any significant clipping of the TR beams on the PSL table PDs.
- IMC Power reduction
Now we have nice motorized HWP. sitemap -> PSL -> Power control
== Initial condition == [Attachment 6]
C1:IOO-HWP_POS 38.83
Measured input power = 0.99W
C1:IOO-MC_RFPD_DCMON = 5.38
== Power reduction == [Attachment 7]
- The motor was enabled upon rotation on the screen
C1:IOO-HWP_POS 74.23
Measured input power = 98mW
C1:IOO-MC_RFPD_DCMON = 0.537
- Then, the motor was disabled
- Went to the detection table and swapped the 10% reflector with the 98% reflector stored on the same table. [Attachments 8/9]
After the beam alignment the MC REFL PD received about the same amount of the light as before.
C1:IOO-MC_RFPD_DCMON = 5.6
There is no beam delivered to the WFS paths.
CAUTION: IF THE POWER IS INCREASED TO THE NOMINAL WITH THIS CONFIGURATION, MC REFL PD WILL BE DESTROYED.
- The IMC can already be locked with this configuration. But for the MC Autolocker, the MCTRANS threshold for the autolocker needs to be reduced as well.
This was done by swapping a line in /opt/rtcds/caltech/c1/scripts/MC/AutoLockMC.init
# BEFORE
/bin/csh ./AutoLockMC.csh >> $LOGFILE
#/bin/csh ./AutoLockMC_LowPower.csh >> $LOGFILE
--->
# AFTER
#/bin/csh ./AutoLockMC.csh >> $LOGFILE
/bin/csh ./AutoLockMC_LowPower.csh >> $LOGFILE
Confirmed that the autolocker works a few times by toggling the PSL shutter. The PSL shutter was closed upon the completion of the test
- Walked around the lab and checked all the bellows - the jam nuts are all tight, and I couldn't move them with my hands. So this is okay according to the ancient tale by Steve.
|
Attachment 1: Screenshot_2021-10-15_17-36-00.png
|
|
Attachment 2: Screenshot_2021-10-15_17-39-58.png
|
|
Attachment 3: Screenshot_2021-10-15_17-42-20.png
|
|
Attachment 4: Screenshot_2021-10-15_17-46-13.png
|
|
Attachment 5: Screenshot_2021-10-15_18-05-54.png
|
|
Attachment 6: Screen_Shot_2021-10-15_at_19.45.05.png
|
|
Attachment 7: Screen_Shot_2021-10-15_at_19.47.10.png
|
|
16409
|
Fri Oct 15 20:53:49 2021 |
Koji | Summary | General | Vent Prep |
From the IFO point of view, all look good and we are ready for venting from Mon Oct 18 9AM |
16410
|
Mon Oct 18 10:02:17 2021 |
Koji | Update | VAC | Vent Started / Completed |
[Chub, Jordan, Anchal, Koji]
- Checked the main volume is isolated.
- TP1 and TP2 were made isolated from other volumes. Stopped TP1. Closed V4 to isolate TP1 from TP2.
- TP3 was made isolated. TP3 was stopped.
- We wanted to vent annuli, but it was not allowed as VA6 was open. We closed VA6 and vented the annuli with VAVEE.
- We wanted to vent the volume between VA6, V5, VM3, V7 together with TP1. So V7 was opened. This did not change the TP1 pressure (P2 = 1.7mmTorr) .
- We wanted to connect the TP1 volume with the main volume. But this was not allowed as TP1 was not rotating. We will vent TP1 through TP2 once the vent of the main volume is done.
- Satrted venting the main volume@Oct 18, 2021 9:45AM PDT
- We started from 10mTorr/min, and increased the vent speed to 200mTorr/min, 700mTorr/min, and now it is 1Torr/min @ 20Torr
- 280Torr @11:50AM
- 1atm @~2PM
We wanted to vent TP1. We rerun the TP2 and tried to slowly introduce the air via TP2. But the interlock prevents the action.
Right now the magenta volume in the attachment is still ~1mTorr. Do we want to open the gate valves manually? Or stop the interlock process so that we can bypass it? |
Attachment 1: Screen_Shot_2021-10-18_at_14.52.34.png
|
|
Attachment 2: Screenshot_2021-10-18_15-08-59.png
|
|
16412
|
Tue Oct 19 10:59:09 2021 |
Koji | Update | VAC | Vent Started / Completed |
[Chub, Jordan, Yehonathan, Anchal, Koji]
North door of the BS chamber opened
|
16413
|
Tue Oct 19 11:30:39 2021 |
Koji | Update | VAC | How to vent TP1 |
I learned that TP1 was vented through the RGA room in the past. This can be done by opening VM2 and a manual valve ("needle valve")
I checked the setup and realized that this will vent RGA. But it is OK as long as we turns of the RGA during vent and bake it once TP1 is back.
Additional note:
- It'd be nice to take a scan for the current background level before the work.
- Turn RGA EM and filament off, let it cool down overnight.
- Vent with clean N2 or clean air. (Normal operating temp ~80C is to minimize accumulation of H-C contaminations.)
- There is a manual switch and indicators on the top of the RGA amp. It has auto protection to turn filament off if the pressure increase over ~1e-5. |
Attachment 1: Screen_Shot_2021-10-18_at_14.52.34.png
|
|
16415
|
Tue Oct 19 23:43:09 2021 |
Koji | Summary | CDS | c1sus2 DAC to ADC test |
(Because of a totally unrelated reason) I was checking the electronics units for the upgrade. And I realized that the electronics units at the test stand have not been properly powered.
I found that the AA/AI stack at the test stand (Attachment 1) has an unusual powering configuration (Attachment 2).
- Only the positive power supply was used / - The supply voltage is only +15V / - The GND reference is not connected to anywhere.
For confirmation, I checked the voltage across the DC power strip (Attachments 3/4). The positive was +5.3V and the negative was -9.4V. This is subject to change depending on the earth potential.
This is not a good condition at all. The asymmetric powering of the circuit may cause damages to the opamps. So I turned off the switches of the units.
The power configuration should be immediately corrected.
- Use both positive and negative supply (2 power supply channels) to produce the positive and the negative voltage potentials. Connect the reference potential to the earth post of the power supply.
https://www.youtube.com/watch?v=9_6ecyf6K40 [Dual Power Supply Connection / Serial plus minus electronics laboratory PS with center tap]
- These units have DC power regulator which produces +/-15V out of +/-18V. So the DC power supplies are supposed to be set at +18V.
|
Attachment 1: P_20211019_224433.jpg
|
|
Attachment 2: P_20211019_224122.jpg
|
|
Attachment 3: P_20211019_224400.jpg
|
|
Attachment 4: P_20211019_224411.jpg
|
|
16418
|
Wed Oct 20 15:58:27 2021 |
Koji | Update | VAC | How to vent TP1 |
Probably the hard disk of c0rga is dead. I'll follow up in this elog later today.
Looking at the log in /opt/rtcds/caltech/c1/scripts/RGA/logs , it seemed that the last RGA scan was Sept 2, 2021, the day when we had the disk full issue of chiara.
I could not login to c0rga from control machines.
I was not aware of the presence for c0rga until today, but I could locate it in the X arm.
The machine was not responding and it was rebooted, but could not restart. It made some knocking sound. I am afraid that the HDD failed.
I think we can
- prepare a replacement linux machine for the python scripts
or
- integrate it with c1vac |
16428
|
Tue Oct 26 14:53:24 2021 |
Koji | Update | Electronics | Rack |
1. We have a rack at the 40m storage. We are free to take it to the lab. If there is a tag, tell the info to Liz. Let's move it to the lab tomorrow right after the meeting.
2. We have a few racks in WB B1 (Attachment 1). Liz and I checked a rack which looks suitable for us. 46U height. Caltech transport will move it to the lab. |
Attachment 1: P_20211026_143814.jpg
|
|
16434
|
Wed Oct 27 18:11:37 2021 |
Koji | Summary | BHD | Part II of BHR upgrade - Relocation of TT2 and MMT1/2 alignment |
Closed the PSL shutter @18:11
During the vent, we want to keep the cavity unlocked if not necessary.
|
16435
|
Wed Oct 27 18:16:45 2021 |
Koji | Summary | BHD | Part II of BHR upgrade - Relocation of TT2 and MMT1/2 alignment |
- Moving the MMT2 south by a cm is fine. This will give you ~0.5cm at TT1 without changing the other alignment much.
- IMC mode is moving because of your presence + HEPA blow.
- 2cm at Faraday is plenty for the beam diameter of a few mm.
|
16436
|
Wed Oct 27 19:34:52 2021 |
Koji | Summary | Electronics | New electronics racks |
1. The rack we cleaned today (came from West Bridge) will be placed between 1X3 and 1X4, right next to 1X4 (after removing the plastic boxes). (Attachment 1)
For easier work at the side of the 1X4, the side panel of the 1X4 should be removed before placing the new rack. Note that this rack is imperial and has 10-32 threads
2. In terms of the other rack for the Y arm, we found the rack in the storage is quite dirty. Anchal pointed out that we have a few racks standing along the Y arm (as the storage of the old VME/Euro card electronics) (Attachments 2/3)
They are not too dirty and also doing nothing there. Let's vacate one of them (the one right next to the optics preparation table). Use this space as a new storage area placing a wire shelving rack for something.
BTW, I thought it is good to have the rack at the vertex side of 1Y1 (as 1Y0?), but the floor has "KEEP OUT" marking. I have no idea why we have this marking. Is this for crane operation??? Does any one know? |
Attachment 1: P_20211027_180737.jpg
|
|
Attachment 2: P_20211027_180443.jpg
|
|
Attachment 3: P_20211027_180408.jpg
|
|
Attachment 4: P_20211027_180139.jpg
|
|
16442
|
Mon Nov 1 14:51:34 2021 |
Koji | Update | General | Checking the vent plan |
The vent team described a detailed vent plan (and reports where the actions have been performed)
https://wiki-40m.ligo.caltech.edu/vent/Fall2021
- [Sec.4] We should decide the final PR2 mirror through table-top measurements.
- [Sec 6] BS alignment is probably "unknown" now. So it'd be better to use the ITMY spot as the reference, then align BS for ITMX. For temporary alignment, it's OK though.
- [Sec 9-11] RIght now there is no mounts to place LO3/LO4/AS2/AS3/BHDBS. But we probably want to test something before the installation of the BHD? Just place the BHDBS on a optics mount so that we get an interfered beam on ITMY?
At this point we are supposed to have all the electronics all the CDS necessary for the new SOS control. Otherwise, they are just swinging and the alignment work will just be impossible.
- [Sec 15] The OPLEV mirrors can be freely moved as long as it does not block the main IR beams. Moving ITMXOL1 makes the reflection blocked by ITMXOL2. And moving ITMXOL2 would make the IR beams clipped. Consider replacing the mounts with a fixed mount. (The OPLEV mirrors are 1.5" in dia. It is not common vacuum compatible 1.5inch mounts. If 1" Al mirror is sufficient, we can use it.
https://wiki-40m.ligo.caltech.edu/vent/Fall2021/FinalAlignment
- The arms are the most strict alignment requirement. Everything else will follow the arm alignment. So start from the arms and propagate the alignment to Michelson / PRMI / SRMI.
- We reestablish arm alignment using the end green beams.
- Then recover IR arm alignment. Consider using ASS if possible |
16446
|
Tue Nov 2 22:50:30 2021 |
Koji | Update | BHD | SOS assembly |
2.5Hz is surprising. Can you move it down to sub 1Hz by adding a socket cap screw at the top instead of the set screw for the Teflon piece? How much mass do you need to add? |
16448
|
Thu Nov 4 15:03:43 2021 |
Koji | Summary | BHD | 1Y1 rack work |
I have visited the binder file for the 40m wiring file in the control room.
The 12V power supply on 1Y1 is for the CCD cameras. So we still want to keep the 12V 0.8A power and the side connections for these. It is not necessary to be Sorensen. Can we replace it with an AC-DC adapter with +12V/1A for example? BTW, the video matrix and quads are AC-powered.
The mysterious thick cables and cross-connects (green wires) on the side panel (labeled AP1/AP2/SP/IMCREFL) are for "EO shutters". It was meant for the protection of the PDs from bright beams.
I don't think they have been used. And we don't need them. |
16452
|
Fri Nov 5 20:35:10 2021 |
Koji | Update | BHD | Feedthru / Optical Mounts |
- New feedthrus [4xDB25 Qty 4 / 8xDB25 Qty 1] are placed on the wire shelf at the entrance -> Jordan, please clean them.
- There are plenty of 2" DLC mounts. There are also many 1.5" mounts but they are less useful.
We need at least 3 1" moounts and 1 1" or 2" lens mount (and the lens). Let's purchase them on Thorlabs. I'll work on the order. |
Attachment 1: P_20211105_200817.jpg
|
|
16454
|
Mon Nov 8 13:13:00 2021 |
Koji | Summary | BHD | 1Y1 rack work; Sorensens removed |
Updated the rack layout. Now there is an issue.
We were supposed to have 1U space at the top, but it was occupied by the 12V.
We need to either lower the c1sus2 and IO chassis 1U or move the Sorensen at the bottom. |
Attachment 1: 40m_BHD.png
|
|
16458
|
Mon Nov 8 18:42:38 2021 |
Koji | Summary | BHD | Rack Layout / Power Strips |
Rack |
# of units that
requires +18V |
Power Source |
1X3 (new rack) |
15 |
1X3 U1/2 |
1X4 |
13 |
1X3 U1/2 |
1X5 |
8 or 9 (OL AA) |
1X5 U40/41 |
1Y0 |
17 |
1Y0 U1/2 |
1Y1 |
15 |
1Y0 U1/2 |
1Y3 |
12 |
1Y3 U39/40 |
1X9 |
9 |
1X9 U38/39 |
1Y4 |
9 |
1Y4 U39/40
|
Notes:
- There are 8 racks and there is only 7x 18V power strips. 1X5 could be the one without the power strip and to parasite with 1X3/4. Otherwise we need to modify some of the 24V power strips (no plan to use) into 18V by replacing the connectors.
- We need total ~100 18V cables / We ordered 60x 3ft / 60x 3ft / 30x 10ft. Hopefully these are enough for our depand... I haven't checked the delivered number.
- All the acromags are supposed to be powered with one voltage. I think they are supposed to run with +18V.
- I didn't check the distribution of Sorensens through the lab. (i.e. how many we have / how many we need / ...)
|
Attachment 1: rack_plan.pdf
|
|
16464
|
Thu Nov 11 00:11:39 2021 |
Koji | Summary | SUS | 2" to 3" sleeve issue |
Yehonathan and Tega found that the new PR3 and SR3 delivered in 2020 is in fact 3/4" in thickness (!). Digging the past email threads, it seems that the spec was 10mm but the thickness was increased for better relieving the residual stress by the coatings.
There are a few issues.
1. Simply the mirror is too thick for the ring. It sticks out from the hole. And the mirror retainers (four plastic plates) are too far from the designed surface, which will make the plates tilted.
2. The front side of the mirror assembly is too heavy and the pitch adjustment is not possible with the balance mass.
Some possible solutions:
- How about making the recess deeper?
In principle this is possible, but the machining is tricky because the recess is not a simple round hole but has "pads" where the mirror sits. And the distance of the retainer to the thread is still far.
And the lead time might become long.
- How about making new holes on the ring to shift the clamp?
Yes it is possible. This will shift the mirror assembly by a few mm. Let's consider this.
- How about modifying the wire blocks?
Yes it is equivalent to shift the holes on the ring. Let's consider this too.
1. How to hold the mirror with the retainer plates
[Attachment 1] The expected distance between the retainer plate and the threaded hole is 13.4mm. We can insert a #4-40 x L0.5" stand off (McMaster-Carr 91197A150, SUS316) there. This will make the gap down to 0.7mm. With a washer, we can handle this gap with the plate. Note that we need to use vented & silver plated #4-40 screws to hold the plates.
[Attachment 2] How does this look like when the CoM is aligned with the wire plane? Oh, no... the lower two plates will interfere with the EQ stops and the EQ stop holders. We have to remove them. [Attachment 3]
We need to check with the suspension if the EQ stop screws may hit the protruded optics and can cause chipping/cracking.
2. Modifying the wire block
[Attachment 4] The 4x thru holes of the wire block were extended to be +/-0.1" slots. The slots are too long to form ovals and produce thin areas. With the nominal position of the balance mass, the clamp coordinates are y=1.016 (vertical) and z=-2.54mm (longitudinal).
==> The CoM is 0.19mm backside (magnet side) and 0.9134 mm lower from the wire clamping points. This looks mathematically doable, but the feasibility of the manufacturing is questionable.
[Attachment 5] Because the 0.1" shift of the CoM is large, we are able to make new #2-56 thread holes right next to the original ones. The clamp coordinates are y=1.016 (vertical) and z=-2.54mm (longitudinal).
==> The CoM is 0.188mm backside (magnet side) and 0.9136 mm lower from the wire clamping points. With the given parameters, the expected pitch resonant frequency is 0.756Hz
My Recommendation
- Modify the metal ring to shift the #2-56 threads by 0.1"
- The upper two retainer plates will have #4-40 x 0.5" stand off. Use vented Ag-coated #4-40 screws.
- The lower two are to be removed.
- Take care of the EQ stops.
- Of course, the best solution is to redesign the holder for 3/4" optics. Can we ask Protolab for rapid manufacturing???
|
Why did we need to place the mass forward to align the 1/4" thick optic?
We were supposed to adjust the CoM not to have too much adjustment. But we had to move the balance mass way too front for the proper alignment with a 1/4" thick optic. Why...?
This is because the ring was designed for a 3/8" thick optic... It does not make sense because the depth of the thread holes for the retainer plate was designed for 1/4" optics...
When the balance mass is located at the neutral position, the CoM coordinate is
x 0.0351mm (x+: left side at the front view)
y 0.0254mm (y+: vertical up)
z 0.4493mm (z+: towards back)
So, the CoM is way too behind. When the balance mass was stacked and the moved forward (center of the axis was moved forward by 0.27"), the CoM coordinate is (Attachment 6)
x 0.0351mm
y 0.0254mm
z 0.0011mm
This makes sens why we had to move the balance mass a lot for the adjustment. |
Attachment 1: Screenshot_2021-11-11_001050.png
|
|
Attachment 2: Screenshot_2021-11-11_010405.png
|
|
Attachment 3: Screenshot_2021-11-11_010453.png
|
|
Attachment 4: Screenshot_2021-11-11_012213.png
|
|
Attachment 5: Screenshot_2021-11-11_011336.png
|
|
Attachment 6: Screenshot_2021-11-10_235100.png
|
|
16471
|
Tue Nov 16 18:28:53 2021 |
Koji | Update | BHD | SOS assembly |
Yehonathan told me that the wires are touching between the clamps! I went back to the CAD and confirmed it is really happening. Sad.
The distance of the wires at the upper clamp is 17.018mm.
The distance of the lower clamps is 74.168mm
The vertical drop of the wire is 251mm
--> The wire angle from the vertical line is 0.114 rad
The lower wire block has a step of 1.016mm with the vertical extension of the piece by 11.684mm
--> The angle clearance of the lower clamp is 0.087 rad
So the clearance was not enough.
If we cut the top center of the wire block more than 2.77mm, we can make the wires free.
For safety, we can cut 0.25" = 6.35mm. This will give 0.4mm clearance between the block and the wire at the closest point.
I did this modification on the 3D model and modified the 2D drawing too, so that we can find the machine shop to do it quickly. |
Attachment 1: D2100546_Wire_Block.pdf
|
|
Attachment 2: D2100546_Wire_Block.png
|
|
16473
|
Wed Nov 17 11:53:27 2021 |
Koji | Update | General | wire clamp plate mod |
Of course, we remove the magnet-dumbbell for machining. After that the part will be cleaned/baked again. And Yehonathan is going to glue the magnet-dumbbell again. |
16475
|
Thu Nov 18 14:29:01 2021 |
Koji | Summary | BHD | BHD invac optics / opto-mechanics |
I went through the optics list (in the BHD procurement google spreadsheet) and summarized how to build them.
The red ones are what we need to purchase. Because of the strange height of the LMR mounts, the post needs to have none half-integer inch heights.
They need to be designed as the usual SS posts are not designed to be vac compatible (not because of the material but the design like screw hole venting).
We also need to check how many clean forks we have.
-> The components were ordered except for the custom posts.
ssome partssss
Name |
Optic |
Mount |
Mount OH |
Post |
Post OH |
Fork / Base |
Base OH |
Total Height |
Notes |
POP_SM5 |
Previous POYM1 / 2" Y1-2037-0 |
LMR2V Thorlabs |
1.36 |
Custom Post |
4.14 |
SS Fork |
0 |
5.5 |
|
POP_SM4 |
New CM254-750-E03 Thorlabs |
LMR1V Thorlabs |
0.87 |
Newport 9953+PLS-T238 |
3.88 |
BA1V / BA2V |
0.75 |
5.5 |
|
BSOL1 |
New 2" VIS BB2-E02 |
LMR2V Thorlabs |
1.36 |
Custom Post |
4.14 |
SS Fork |
0 |
5.5 |
|
ITMYOL1 |
New 2" VIS BB2-E02 |
LMR2V Thorlabs |
1.36 |
Custom Post |
4.14 |
SS Fork |
0 |
5.5 |
|
ITMYOL2 |
New 2" VIS BB2-E02 |
LMR2V Thorlabs |
1.36 |
Custom Post |
4.14 |
SS Fork |
0 |
5.5 |
|
SRMOL1 |
New 2" VIS BB2-E02 |
LMR2V Thorlabs |
1.36 |
Custom Post |
4.14 |
SS Fork |
0 |
5.5 |
|
ASL |
LA1779-C Thorlabs or KPX217AR.33 Newport |
LMR2V Thorlabs |
1.36 |
Custom Post |
4.14 |
SS Fork |
0 |
5.5 |
|
GRY_SM1 |
Y2-2037-0 (in hand) |
DLC |
|
DLC Post |
|
DLC Fork |
|
5.5 |
|
BHDBS |
CVI (In hand) |
DLC |
2 |
DLC Post |
|
DLC Fork |
|
5.5 |
(3" post for BHD) |
LO3 |
Lambda (in hand) |
POLARIS-K1-2AH Thorlabs |
1 |
Custom Post |
4.5 |
SS Fork |
0 |
5.5 |
(3" post for BHD) |
LO4 |
Lambda (in hand) |
POLARIS-K1-2AH Thorlabs |
1 |
Custom Post |
4.5 |
SS Fork |
0 |
5.5 |
(3" post for BHD) |
AS3 |
Lambda (in hand) |
POLARIS-K1-2AH Thorlabs |
1 |
Custom Post |
4.5 |
SS Fork |
0 |
5.5 |
(3" post for BHD) |
OMC1R3 |
Y1-1025-45P (in hand) |
POLARIS-K1-2AH Thorlabs |
1 |
Custom Post |
4.5 |
SS Fork |
0 |
5.5 |
(3" post for BHD) |
OMC1R4 |
Y1-1025-45P (in hand) |
POLARIS-K1-2AH Thorlabs |
1 |
Custom Post |
4.5 |
SS Fork |
0 |
5.5 |
(3" post for BHD) |
OMC2R3 |
Y1-1025-45P (in hand) |
POLARIS-K1-2AH Thorlabs |
1 |
Custom Post |
4.5 |
SS Fork |
0 |
5.5 |
(3" post for BHD) |
OMC2R4 |
Y1-1025-45P (in hand) |
POLARIS-K1-2AH Thorlabs |
1 |
Custom Post |
4.5 |
SS Fork |
0 |
5.5 |
(3" post for BHD) |
|
|
|
|
|
|
|
|
|
|
OMC1R1 |
Y1-1025-45P (in hand) |
LMR1V Thorlabs |
0.87 |
Custom Post |
4.63 |
SS Fork |
0 |
5.5 |
(3.13" post for BHD) |
OMC2R1 |
NB1-K14 Thorlabs |
LMR1V Thorlabs |
0.87 |
Custom Post |
4.63 |
SS Fork |
0 |
5.5 |
(3.13" post for BHD) |
|
16490
|
Mon Dec 6 14:26:52 2021 |
Koji | Update | VAC | Pumping down the RGA section |
Jordan reported that the RGA section needs to be pumped down to allow the analyzer to run at sufficiently low pressure (P<1e-4 torr).
The RGA section was pumped down with the TP2/TP3. The procedure is as listed below.
If the pressure go up to P>1e-4 torr, we need to keep the pump running until the scan is ready.
----
### Monitor / Control screen setup ###
1. On c1vac: cd /cvs/cds/caltech/target/c1vac/medm
2. medm -x C0VAC_MONITOR.adl&
3. RGA section (P4) 3.6e-1 torr / P3/P2 still atm.
4. medm -x C0VAC_CONTROL.adl
### TP2/TP3 backing ###
5. Turn on AUX RP with the circuit breaker hanging on the AC.
6. Open manual valve for TP2/3/ backing / PTP2/3 ~ 8torr
### TP2/TP3 starting ###
7. Turned on TP2/TP3 with the Standby OFF
### Pump down the pump spool ###
8. Connect manual RP line (Quick Connect)
9. Turned on RP1/RP3 -> quickly reached 0.4 torr
10. Open V6 for pump spool pumping -> Immediately go down to sufficiently low pressure for TP2/TP3.
(10.5 I had to close V6 at this point)
11. Open V5 to start pumping pump spool with TP3 (TP2 still stand by) -> P3 immediately goes down below 1e-4 torr. This automatically closed V6 because of the low pressure of P3 (interlocking)
### Pump down the RGA section ###
12. Open VM3 to pump down RGA section -> P4 goes down to <1e-4 torr
13. P2 is still 2e-3. So decided to open V4 to use TP2 (now it's ready) too. -> Saturated at 1.7e-3
### Shutting down ###
14. Close VM3
15. Close V4/V5 to isolate TP2/TP3
16. Stop TP2/TP3 -> Slowing down
17. Stop RP1/RP3
18. Close the manual valves for TP2/3/ backing
19. Stop AUX RP with the circuit breaker hanging on the AC. |
16493
|
Tue Dec 7 13:12:50 2021 |
Koji | Update | VAC | Pumping down the RGA section |
So that Jordan can run the RGA scan this afternoon, I ran TP3 and started pumping down the RGA section.
Procedure:
- Same 1~4
- Same 5
- 6 Opened only the backing path for TP3
- 7 Turned on TP3 only
- TP3 reached the nominal full speed @75kRPM
- 11 Opened V5 to pump the pump spool -> Immediately reached P3<1e-4
- 12 Opened VM3 to pump the RGA section -> Immediately reached P4<1e-4
The pumps are kept running. I'll come back later to shut down the pumps.
=> Jordan wants to heat the filament (?) and to run the scan tomorrow.
So we decided to keep TP3 running overnight. I switched TP3 to the stand-by mode (= lower rotation speed @50kRPM)
|
16501
|
Fri Dec 10 19:22:01 2021 |
Koji | Update | VAC | Pumping down the RGA section |
The scan result was ~x10 higher than the previously reported scan on 2020/9/15 (https://nodus.ligo.caltech.edu:8081/40m/15570), which was sort of high from the reference taken on 2018/7/18.
This just could mean that the vacuum level at the RGA was x10 high.
We'll just go ahead with the vacuum repair and come back to the RGA once we return to "vacuum normal".
Meanwhile, I asked Jordan to turn off the RGA to make it cool down. I shut off RGA section and turned TP2 off. |
16502
|
Fri Dec 10 21:35:15 2021 |
Koji | Summary | SUS | Vertex SUS DAC adapter ready |
4 units of Vertex SUS DAC adapter (https://dcc.ligo.org/LIGO-D2100035) ready.
https://dcc.ligo.org/LIGO-S2101689
https://dcc.ligo.org/LIGO-S2101690
https://dcc.ligo.org/LIGO-S2101691
https://dcc.ligo.org/LIGO-S2101692
The units are completely passive right now and has option to extend to have a dewhitening board added inside.
So the power switch does nothing.
Some of the components for the dewhitening enhancement are attached inside the units.
|
Attachment 1: PXL_20211211_053155009.jpg
|
|
Attachment 2: PXL_20211211_053209216.jpg
|
|
Attachment 3: PXL_20211211_050625141-1.jpg
|
|
16510
|
Wed Dec 15 17:44:18 2021 |
Koji | Summary | BHD | Part VIII of BHR upgrade - Placed LO1 |
If ITMX already has another side magnet, we can migrate the side OSEM of ITMX to the other side. This way, the interference of the OSEMs can be avoided. |
16515
|
Thu Dec 16 15:54:08 2021 |
Koji | Update | Electronics | ITMX feedthroughs and in-vac cables installed |
Thanks for the installation.
With regard to the connector convention, let's use the attached arrangement so that it will be consistent with the existing flange DSUB configuration. Not a big deal.
|
Attachment 1: PXL_20211216_235056582.jpg
|
|
16516
|
Thu Dec 16 17:41:12 2021 |
Koji | Update | BHD | Coil driver test failed for S2100619-v1 |
Good catch. It turned out that the both + and - side of the output stages for CH2 were oscillating at ~600kHz. If I use a capacitance sticks to touch arbitrarily around the components, it stops their oscillation and they stay calm.
It means that the phase margin becomes small while the circuit starts up.
I decided to increase the capacitances C6 and C20 (WIMA 150pF) to 330pF (WIMA FPK2 100V) and the oscillation was tamed. 220pF didn't stop them. After visually checked the signal behavior with an oscilloscope, the unit was passed to Anchal for the TF test.
The modification was also recorded in the DCC S2100619 |
Attachment 1: PXL_20211217_001735762.jpg
|
|
Attachment 2: PXL_20211217_001719345.jpg
|
|
Attachment 3: PXL_20211217_005344828.jpg
|
|
Attachment 4: PXL_20211217_010131027.PORTRAIT.jpg
|
|
Attachment 5: PXL_20211217_011423823.jpg
|
|
Attachment 6: HAMA_Driver_V4.pdf
|
|
16519
|
Fri Dec 17 12:32:35 2021 |
Koji | Update | SUS | Remaining task for 2021 |
Anything else? Feel free to edit this entry.
- SUS: AS1 hanging
- SUS: PR3/SR2/LO2 3/4" thick optic hanging
v Electronics chain check (From DAC to the end of the in-air cable / From the end of the in-air cable to the ADC)
[ELOG 16522]
- Long cable installation (4x 70ft)
- In-air cable connection to the flange
- In-vac wiring (connecting LO1 OSEMs)
- LO1 OSEM insertion/alignment
- LO1 Damping test
|
16521
|
Fri Dec 17 19:16:45 2021 |
Koji | Update | BHD | SOS assembly |
We @40m do the convention of the arrow at the thinnest side & pointing the HR side, but nobody says Lambda does the same.
We can just remount the mirror without breaking the wires and adjust the pitching if you do it carefully.
Does this mean that the LO1 also likely to have the wedge pointing up? Or did you rotate the mirror to have the wedge reflection to be as horizontal as possible? |