Entry  Tue Jul 30 18:56:31 2013, manasa, Update, General, ITMX chamber vented/Closing plan 
    Reply  Wed Jul 31 00:59:58 2013, manasa, Update, General, ITMX chamber vented/Closing plan 
Message ID: 8941     Entry time: Tue Jul 30 18:56:31 2013     Reply to this: 8944
Author: manasa 
Type: Update 
Category: General 
Subject: ITMX chamber vented/Closing plan 

[Koji,Manasa]

We removed the ITMX heavy door to fix the oplev situation. 

My Plan for closing:

Today: I will work on the ITMX oplev situation today and go through the vent close-up checklist as far as I can get.
Tomorrow: We will do the final alignment check tomorrow with the light doors. The access connector and heavy doors should go in place late afternoon.
Thursday: We will start pumping down early in the morning on Thursday.