40m
QIL
Cryo_Lab
CTN
SUS_Lab
TCS_Lab
OMC_Lab
CRIME_Lab
FEA
ENG_Labs
OptContFac
Mariner
WBEEShop
|
40m Log |
Not logged in |
 |
|
Tue Jun 25 19:18:07 2013, gautam, Configuration, endtable upgrade, plan of action for PZT installation
|
Wed Jul 3 21:19:04 2013, gautam, Configuration, endtable upgrade, plan of action for PZT installation 
|
Mon Jul 8 13:45:19 2013, gautam, Configuration, endtable upgrade, Driver board verification
|
Wed Jul 10 22:41:06 2013, gautam, Configuration, endtable upgrade, PZT Driver Board
|
Thu Jul 11 23:50:57 2013, gautam, Configuration, , PZT Driver Board-changes made 
|
Mon Jul 15 11:51:18 2013, gautam, Configuration, endtable upgrade, DAC at 1Y4-Max Output and Power Spectrum    
|
Mon Jul 15 13:51:17 2013, Koji, Configuration, endtable upgrade, DAC at 1Y4-Max Output and Power Spectrum
|
Mon Jul 15 15:54:20 2013, gautam, Configuration, endtable upgrade, DAC at 1Y4- Power Spectrum -with the right units  
|
Mon Jul 15 17:20:43 2013, Jenne, Configuration, endtable upgrade, DAC at 1Y4- Power Spectrum -with the right units
|
Mon Jul 15 17:59:31 2013, gautam, Configuration, endtable upgrade, DAC at 1Y4- Power Spectrum -6.4kHz bandwidth
|
Tue Jul 16 14:51:09 2013, gautam, Configuration, endtable upgrade, AI Board-D000186-Modified notches
|
Thu Jul 18 19:09:08 2013, gautam, Configuration, endtable upgrade, QPD Calibration for PZT Calibration  
|
Thu Jul 18 20:20:52 2013, gautam, Configuration, endtable upgrade, First mirror glued to PZT and mounted in modified mounts
|
Thu Jul 18 23:34:40 2013, gautam, Configuration, endtable upgrade, Coarse adjustment of PZT axes orientation in mount
|
Fri Jul 19 23:35:31 2013, gautam, Configuration, endtable upgrade, Preliminary Calibration of PZT   
|
Tue Jul 23 20:41:40 2013, gautam, Configuration, endtable upgrade, Full range calibration and installation of PZT-mounted mirrors    
|
Mon Aug 5 18:48:44 2013, gautam, Configuration, endtable upgrade, Full range calibration of PZT mounted mirrors for Y-endtable   
|
Fri Jul 19 22:51:40 2013, gautam, Configuration, endtable upgrade, Second mirror glued to PZT and mounted
|
Tue Jul 30 19:44:05 2013, gautam, Configuration, endtable upgrade, Second mirror glued to PZT and mounted
|
Thu Jul 18 21:12:58 2013, gautam, Configuration, endtable upgrade, AI Board-D000186-All channels modified
|
Mon Jul 29 13:39:25 2013, gautam, Configuration, endtable upgrade, PZT Driver Board-further changes 
|
Mon Jul 29 21:57:45 2013, gautam, Configuration, endtable upgrade, Hardware installed at 1X9
|
Tue Jul 30 19:40:47 2013, gautam, Configuration, endtable upgrade, DAC-PZT Driver Board Output Signal Chain Tested
|
|
Message ID: 8935
Entry time: Mon Jul 29 21:57:45 2013
In reply to: 8804
Reply to this: 8942
|
Author: |
gautam |
Type: |
Configuration |
Category: |
endtable upgrade |
Subject: |
Hardware installed at 1X9 |
|
|
The following hardware has been installed on rack 1X9;
- KEPCO high voltage power supply (kept in a plastic box at the bottom of the rack, with the 3m SMA cable carrying 100V running along the inside side wall of the rack). The HV supply has not been connected to the driver board yet.
- AI board D000186 installed in top eurocrate. The board does not seem to fit snugly into the slot, so I used a longish screw to bolt the front panel to the eurocrate.
- PZT driver board D980323 installed in top eurocrate adjacent to the AI board.
- Six 11m SMB-LEMO cables have been laid out from 1X9 to the endtable. I have connected these to the PZT driver board, but the other end (to the PZTs) is left unconnected for now. They have been routed through the top of the rack, and along the cable tray to the endtable. All the cables have been labelled at both ends.
I have also verified that the AI board is functional in the eurocrate by using the LEMO monitoring points on the front panel.
The driver boards remain to be verified, but this cannot be done until we connect the HV supply to the board.
|