Entry  Mon Feb 18 18:28:01 2013, yuta, Bureaucracy, Alignment, we are going to pump down 
    Reply  Tue Feb 19 02:23:40 2013, yuta, Bureaucracy, General, action items for PRFPMI 
       Reply  Mon Feb 25 22:30:40 2013, Jenne, Bureaucracy, General, action items for PRFPMI 
          Reply  Fri Mar 8 16:05:56 2013, yuta, Bureaucracy, General, action items for PRMI / ALS-FPMI 
Message ID: 8099     Entry time: Mon Feb 18 18:28:01 2013     Reply to this: 8103
Author: yuta 
Type: Bureaucracy 
Category: Alignment 
Subject: we are going to pump down 

We will start preparing for pumping down. Main goal for this is to demonstrate PRFPMI using ALS.
Here are to-dos before we pump down.

Feb 18 eveing
- check input beam and Y arm alignment again
- IPPOS/IPANG alignment
- check all oplevs

Feb 19 morning
- open ETMX chamber heavy door
- align BS to X end
- adjust OSEM values (added by YM)
- center beam on all AS optics
- make sure AS/REFL is clear
- take picture of flipped PR2 (added by YM)
- make sure green is not clipped by new PRM oplev mirrors  (added by YM)
- center all oplevs

Feb 19 afternoon - Feb 20 morning
- close PSL shutter
- close all heavy doors and put the access connector back
- start pumping down

Feb 20 evening
- start aligning IFO