Mon Dec 17 20:22:07 2012, Jamie, Update, General, Vent plan: WE VENT TOMORROW
|
Mon Dec 17 21:33:45 2012, Manasa, Update, General, Vent plan: WE VENT TOMORROW
|
Tue Dec 18 07:03:40 2012, Manasa, Update, General, Vent plan: WE VENT TOMORROW
|
Tue Dec 18 10:43:20 2012, Steve, Update, VAC, vent has completed  
|
Wed Dec 19 11:53:23 2012, Steve, Update, VAC, AC removed
|
Thu Jan 24 14:40:09 2013, Steve, Update, VAC, RGA backgroung
|
Mon Feb 11 16:16:27 2013, Steve, Update, VAC, 55 days at atmoshere
|
|
Message ID: 7939
Entry time: Thu Jan 24 14:40:09 2013
In reply to: 7849
|
Author: |
Steve |
Type: |
Update |
Category: |
VAC |
Subject: |
RGA backgroung |
|
|
RGA background with VM2 open to Maglev at day 37
Note: The PAN gauge of the annulos is at atm. Please do not vent this 200 ft long annulos line when you venting the annulos of a chamber. The chamber annulos should be closed off to this long 2" OD. pipe before you vent the annulos of a chamber.
|
|
|