Jamie has arranged for phase map measurements this afternoon, so I will take the 6 dichroic LaserOptik optics over to Downs at 1:15 this afternoon.
Team Jamie+Nic will lead the effort to clamp down dog clamps as placement markers for all 4 in-vac passive TTs, and then pull all 4 TTs out of the chambers. They plus Den will move the TTs to the Cleanroom, and will start to install the new pitch alignment hardware.
When I return with the optics, we will install them in the TTs and re-balance them. Then we can put them back in the chambers and get back to work on alignment.
After we re-install the TTs, we will need to check the leveling of all 3 corner tables, just to be sure. |