Message ID: 7584     Entry time: Fri Oct 19 19:26:42 2012     In reply to: 7582     Reply to this: 7587
Author: Jenne 
Type: Update 
Category: VAC 
Subject: vent has started 

Quote:

Quote:

 

 PSL shutter closed, manual block in place, HV turned off. P1 is at 200 Torr now.  Jenne is taking over here.

 Valves closed, 500 torr.  Steve will finish off Monday morning, then we'll take off doors and get to work.