We need to do the following things: Images of optics in DRMI chain, place black glass beam dumps, make sure pickoff beams get out, align IP POS/ANG.
Black glass: behind MMT1, behind IPPOSSM3, forward-going POP beam.
Images and pickoff stuff should happen at the end of each vent.
Images need to be taken of the following optics (with ruler edge at center of optic):
* PZT1
* MMT1
* MMT2
* PZT2
* PRM
* PR2
* PR3
* BS (front and back?)
* ITMX
* ITMY
* SR3
* SR2
* SRM
* OM1
* OM2
* OM3
* OM4=PZT3
* OM5=PZT4
* OMPO
* OM6
* Viewport as AS beam leaves chamber
* POYM1 (check no clipping on edge of mount)
* POXM1 (check no clipping on edge of mount)
Pickoff / aux beams:
* REFL path
* POX
* POY
* POP
* IPPOS
* IPANG |