Entry  Thu Jun 28 00:50:48 2012, yuta, Update, Locking, PRMI work started, commissioning plan POP_1024903948.bmpREFL_1024903929.bmpAS_1024903921.bmp
    Reply  Thu Jun 28 01:44:57 2012, Koji, Update, Locking, PRMI work started, commissioning plan 
    Reply  Thu Jun 28 15:21:02 2012, rana, Update, Locking, PRMI work started, commissioning plan 
       Reply  Thu Jun 28 20:59:28 2012, yuta, Bureaucracy, Locking, vent for PRC check, TOMORROW! 
          Reply  Thu Jun 28 22:08:57 2012, Jenne, Bureaucracy, Locking, vent for PRC check, TOMORROW! 
             Reply  Fri Jun 29 01:49:36 2012, yuta, Bureaucracy, Locking, vent for PRC check, TOMORROW! 
Message ID: 6889     Entry time: Thu Jun 28 20:59:28 2012     In reply to: 6888     Reply to this: 6890
Author: yuta 
Type: Bureaucracy 
Category: Locking 
Subject: vent for PRC check, TOMORROW! 

Koji, Jamie and I talked together and I decided to VENT TOMORROW MORNING. Main purpose of this vent is to see if PRM is flipped or not.

Vent schedule:
June 28 (Thu)
  Prepare for the vent tonight

June 29 (Fri)
  Start vent in the morning
  Look into PRC in the evening. If PRM was flipped, we will correct them. We'll use REFL to align the PRM. If PRM was not flipped, look into PR2,PR3 and other related optics.

June 30 (Sat)
July 1 (Sun)
  Thinking time. I can work if needed.

July 2 (Mon)
  If we need something else to do, do it.
  If not, start pumping.
  July 4th is the Independence Day. So, I need IFO working before July 4th.

Check List:
 We will just open the BS chamber.
  - PRM flipping
  - PR2, PR3 flipping
  - PRC suspensions
  - Cipping check in PRC