Action Items:
IFO:
Arm cavity sweeps, mode scan - JENNE
Align AS OSA (others?) - JENNE
Investigate PRMI glitches, instability (take PRM oplev spectra locked, unlocked, to see if PRM is really moving) - KOJI, JENNE, DEN
Connect up beatbox for Xarm use - KOJI with JENNE
TT:
Prepare electronics for TTs (coil drivers) - JAMIE
In-air TT testing to confirm we can control / move TTs before we vent (starting in ~2 weeks) - SURESH
Connect TTs to digital system and controls, lay cables if needed - JAMIE with SURESH
OAF:
OAF comparison plot, both online and offline, comparing static, adaptive and static+adaptive - DEN
Static-only OAF noise budget (Adaptive noise budget as next step) - DEN
Build amplifiers for new small microphones - DEN
SLC:
Black glass: to clean&bake - KOJI
Scattered light measurement at the end stations: design / confirmation of the mechanical parts/optics/cameras - JAN
MM:
IPPOS beam measurement - SURESH with JENNE
AS beam measurement (if beam is bright enough) - SURESH and JENNE
Mode matching calculations, sensitivity to MC waist measurement errors, PRM position - JENNE
Think up diagnostic measurement to determine mode matching to PRC while chambers are open, while we tweak MMT - JAMIE, JENNE, KOJI, SURESH
Computers:
Upgrade Rossa, Allegra to Ubuntu, make sure Dataviewer and DTT work - JAMIE
|