Wed Aug 31 11:37:56 2011, steve, Update, Green Locking, shutter in place at east end
|
Wed Oct 19 16:28:35 2011, steve, Update, Green Locking, ETMY mechanical shutter is working
|
Wed Oct 19 17:33:07 2011, kiwamu, Update, Green Locking, ETMY mechanical shutter : fully functional
|
|
Message ID: 5701
Entry time: Wed Oct 19 16:28:35 2011
In reply to: 5328
Reply to this: 5704
|
Author: |
steve |
Type: |
Update |
Category: |
Green Locking |
Subject: |
ETMY mechanical shutter is working |
|
|
Quote: |
Uniblitz mechanical shutter installed in the green beam path at ETMY-ISCT The remote control cable has not been connected.
|
The ETMY shutter can be remotely switched from medm screen POY of mechanical shutters.
The new cable from ETMY controller goes to east vertex EV-ISCT where it is connected to POY shutter hook up BNC cable. |