Tue Sep 20 23:59:53 2011, Koji, Summary, LSC, Plan to update the LSC code for multiple lock-ins
|
Wed Sep 21 14:28:25 2011, Koji, Summary, LSC, The LSC code/screen modification for LSC LOCKINs
|
Thu Sep 22 18:33:01 2011, Koji, Summary, LSC, The LSC screen modification
|
Thu Sep 22 23:18:51 2011, Koji, Summary, LSC, The LSC screen modification
|
|
Message ID: 5492
Entry time: Tue Sep 20 23:59:53 2011
Reply to this: 5498
|
Author: |
Koji |
Type: |
Summary |
Category: |
LSC |
Subject: |
Plan to update the LSC code for multiple lock-ins |
|
|
DRMI team needs to use at least three lockins on LSC
Increase the number of the lockin matrix done
Duplicate lockin modules in the LSC code done
modify the main LSC screen done
modify the lockin screen done
modify the lockin matrix screen done
|