Message ID: 5110     Entry time: Wed Aug 3 14:40:32 2011
Author: kiwamu 
Type: Summary 
Category: General 
Subject: minutes of 40m meeting : plan tomorrow 

Tomorrow's main goal is : let the both X and Y green light come out from the chambers.

 

Plan of the in-vac work for tomorrow :

    - Removal of the access connector and the BS north door, starting from 9:00 AM. (requires 6 people)

   - If necessary, align ITMs and ETMs to get the green light nicely flashing / locked.

   - Take pictures of the BS and IOO table before installing / repositioning some optics.

   - Repositioning of the green periscope in the BS chamber to let the Y green light go through it.

   - Steer some green mirrors on the IOO table to let the Y green light come out from the chamber.

   - Steer some green mirrors on the BS table to let the X green light come out from the chamber.

   - Put some beam traps on the BS table

   - Leveling of the BS table. (Do we need to level the IOO table ? it will change the spot positions on the MC mirrors somewhat)

   - Take pictures again.

   - Extra jobs : if we still have some more times, lock MC and check the beam clearance at the Faraday. Also check some possible beam clippings for the IR beam.

   - Close the chamber with the light doors.

   - Softball game at 6:30 PM.