Tomorrow's main goal is : let the both X and Y green light come out from the chambers.
Plan of the in-vac work for tomorrow :
- Removal of the access connector and the BS north door, starting from 9:00 AM. (requires 6 people)
- If necessary, align ITMs and ETMs to get the green light nicely flashing / locked.
- Take pictures of the BS and IOO table before installing / repositioning some optics.
- Repositioning of the green periscope in the BS chamber to let the Y green light go through it.
- Steer some green mirrors on the IOO table to let the Y green light come out from the chamber.
- Steer some green mirrors on the BS table to let the X green light come out from the chamber.
- Put some beam traps on the BS table
- Leveling of the BS table. (Do we need to level the IOO table ? it will change the spot positions on the MC mirrors somewhat)
- Take pictures again.
- Extra jobs : if we still have some more times, lock MC and check the beam clearance at the Faraday. Also check some possible beam clippings for the IR beam.
- Close the chamber with the light doors.