Status update for the vent preparation:
The punchline is : We can not open the chamber on Monday !
##### Task List for the vent preparation #####
(not yet) Low power MC
(not yet) Measurement of the arm lengths
(not yet) Alignment of the Y green beam (#5066)
(not yet) Measurement of the MC spot positions
(80% done) Estimation of the tolerance of the arm length (#5076)
(done) Preparation of beam dumps (#5047)
(done) Health check of shadow sensors and the OSEM damping gain adjustment (#5061)
(done) Alignment of the incident beam axis (#5073)
(done) Loss measurement of the arm cavities (#5077)
Quote from #5048 |
Quote: |
The vent will start from 1 st of August !
|
|
|