Quote: |
The vent will start from 1 st of August !
|
++++ Task List for the vent preparation ++++
+ Preparation of beam dumps (Jamie / Steve)
+ Health check of shadow sensor and measurement of the cross-coupling (Steve)
+ Measurement of the arm Lengths and estimation of the required precision (Kiwamu)
+ Alignment of the Y green beam (Suresh)
+ Alignment of the incident beam axis (Jenne)
+ Measurement of the MC spot positions (Suresh)
+ Loss measurement of the arm cavities (Kiwamu / volunteers)
++++ Task List for the post-vent activity ++++
+ 3f RFPDs (Koji / Rana)
+ EOM resonant circuit (Kiwamu)
+ Sophistication of the LSC model (Yoichi)
+ DRMI commissioning (Keiko / Anamaria)
|