Mon Dec 20 10:47:29 2010, Koji, Update, IOO, Plan for closing the vacuum chambers
|
Mon Dec 20 16:57:58 2010, steve, Update, IOO, checking out & closing the vacuum chambers
|
Mon Dec 20 23:32:58 2010, kiwamu, Update, IOO, Re:checking out & closing the vacuum chambers
|
Mon Dec 20 22:56:20 2010, Jenne, Update, IOO, Plan for closing the vacuum chambers
|
|
Message ID: 4076
Entry time: Mon Dec 20 10:47:29 2010
Reply to this: 4077
4078
|
Author: |
Koji |
Type: |
Update |
Category: |
IOO |
Subject: |
Plan for closing the vacuum chambers |
|
|
Monday
- Place the bars on the in-vac tables to mark the positions of the test mass suspensions. (ITMX/ITMY/ETMX/ETMY)
- Check the table leveling again (ITMX/ITMY/ETMX/ETMY/BSC)
- Align the whole interferometer.
- Check the OPLEV spots by either QPDs or apertures
- Check the OSEM values (MC1/2/3, BS, PRM, SRM, ITMX, ITMY, ETMX, ETMY)
- Energize OMC PZTs.
- We have removed the cards at the back of the HV driver.
- Insert the card and check the connection.
- Adjust the DC values at the middle of the range.
-> They have an internal bias circuit to provide +75V at the outputs. (D060287).
The actual voltages confirmed.
- Adjust the physical knobs of the PZTs such that we can see the spots at the OMCR cam
- If everything is fine, attach the access connector.
- If still everythig is fine, put the BS heavy door.
Tuesday
- Do the following list for all of the testmass chambers.
- Check if the OSEMs and the OPLEV are still fine.
- Inspect the surface of the mirror with a laser pointer or a fiber coupled halogen light.
- Blow the mirrors by the ionization gun.
- Inspect the mirror surface again.
- Move the suspension tower close to the door.
- Make a single drag-wipe with iso
- Move the SOS tower at the original place.
- Check the OSEMs and the OPLEVs. Adjust the alignment.
- Put the heavy door.
- Start slow pumping |