Entry  Thu Aug 5 00:17:41 2010, Koji, Update, PSL, PSL preparation work 
    Reply  Thu Aug 5 22:36:11 2010, Koji, Update, PSL, PSL preparation work 
       Reply  Fri Aug 6 08:09:15 2010, steve, Update, PSL, PSL preparation work 
       Reply  Fri Aug 6 20:00:03 2010, Koji, Update, PSL, PSL preparation work PSL_cable_map.pdf
Message ID: 3364     Entry time: Thu Aug 5 00:17:41 2010     Reply to this: 3370
Author: Koji 
Type: Update 
Category: PSL 
Subject: PSL preparation work 

We start the work on the cables at around the PSL table.

Aug 5th 10am-4pm?: (Kiwamu, Alberto, Koji)
- Removal of the unused cables around the PSL table and the control room
- Removal of the cable ties on the PSL frame

- Removal of the big nuts at the side of the PSL table

Aug 6th 10am-4pm?: (Kiwamu, Alberto, Koji, Jenne (~noon) )
- Labeling of the cables
- Planning of the disconnection

Aug 9th  9am-5pm: (Steve, Jenne, Alberto, Koji)
- Shutting down of the PSL
- Disconnection of the cables
- Draining of the cooling water
- Removal of the accelerometers
- Removal of the PSL chamber
- Sealing of the table with the plastic sheets