Entry  Thu Jul 29 12:31:09 2010, Koji, Summary, General, Lab Schedule PSL_work_schedule.pdf
    Reply  Fri Jul 30 14:53:09 2010, steve, Update, General, PSL table leg upgrade psllegs.PDF
Message ID: 3333     Entry time: Fri Jul 30 14:53:09 2010     In reply to: 3318
Author: steve 
Type: Update 
Category: General 
Subject: PSL table leg upgrade 

Quote:

July
29 Thu BS chamber work: Move cable towers / green steering mirrors / (2 TTs with TT charactrization) / Put the heavy door by 5PM.
30 Fri Pumping down
31 Sat WFS work by Nancy

Aug
1 Sun - 5 Thu WFS work by Nancy
5 Thu PSL Table prep
6 Fri PSL Table prep / Likely to shut down the PSL

9 Mon PSL Table prep / shutting down of the PSL (optional)
10 Tue PSL box Frame lifting
12 Thu PSL table tapping

16 Mon - 17 Tue concrete pouring preparation
19 Thu - 23 Fri Tripod placement
24 Tue - 26 Thu concrete pouring

The PSL table height will be raised to the level of the AP table. This will be done using 6 TMC's Rigid Damped Tripod legs. Their planed positions shown below.

The legs will be grouted to the floor with concrete.

 http://www.techmfg.com/products/floorplatforms/rigiddampedtripod.htm

Attachment 1: psllegs.PDF  70 kB  Uploaded Fri Jul 30 16:20:56 2010  | Hide | Hide all
psllegs.PDF