Kiwamu and Koji
Last night we have released PRM from the gluing fixture. All of the six magnets are successfully released from the fixture.
We put SRM on the fixuture and glued a side magnet which we had failed at the last gluing.
We let it cure in the Al house. This should be the last magnet gluing until ETMs are delivered.
[Current status]
ITMX (ITMU03): all of magnets/guiderod/standoffs glued, mirror baked; balance to be confirmed
ITMY (ITMU04): all of magnets/guiderod/standoffs glued, balance confirmed, mirror baked
SRM (SRMU03): magnets/guiderod/standoff glued; a side magnet gluing in process, balance to be confirmed, last stand off to be glued, mirror to be baked
PRM (SRMU04): magnets/guiderod/standoff glued; balance to be confirmed, last stand off to be glued, mirror to be baked
TT: magnets/guiderod/standoff glued; balance to be confirmed, last stand off to be glued, mirror to be baked |