Entry  Tue May 3 21:05:23 2022, yuta, Update, BHD, AS path alignment, removing a lot of green stuff 7x
    Reply  Wed May 4 13:09:42 2022, Anchal, Update, BHD, IMC table balanced again, IMC is locking, YARM is locking 
       Reply  Wed May 4 15:08:59 2022, Tega, Update, BHD, XARM alignment to get flashing IFO_XY_ARMS_Flashing.png
          Reply  Wed May 4 18:52:43 2022, Tega, Update, BHD, POP beam too high at POP SM4 on the ITMX chamber snnp_pr2_pr3_itmy_aligment.png
             Reply  Thu May 5 14:46:22 2022, Anchal, Update, BHD, POP beam height lowered, POP_SM4 raised 
                Reply  Thu May 5 17:05:31 2022, Tega, Update, BHD, IMC & X/Y-arm alignment IFO_aligment_Y_locking_on.png
                Reply  Mon May 9 18:43:03 2022, Anchal, Update, BHD, ITMX table layout corrected 
                   Reply  Mon May 9 18:49:05 2022, Tega, Update, BHD, Relocate green TRX and TRY PDs/cams/optics from PSL table to BS table IMG_20220509_184439943.jpgIMG_20220509_184154722.jpg
                      Reply  Tue May 10 15:46:38 2022, JC, Update, BHD, Relocate green TRX and TRY components from PSL table to BS table IMG_0741.jpegIMG_0753.jpeg
                         Reply  Tue May 10 18:25:43 2022, Paco, Update, BHD, Green Transmission path 
                   Reply  Tue May 10 16:31:14 2022, Tega, Update, BHD, ITMX optlev return beam steered to QPD 
       Reply  Fri May 6 13:48:34 2022, Anchal, Update, BHD, WFS loop instability fixed 
    Reply  Thu May 12 19:55:01 2022, Tega, Update, BHD, AS path alignment AS.JPGOMCchamber.JPG
       Reply  Thu May 12 20:11:18 2022, Anchal, Update, BHD, BHDBS Output beams steered out to ITMY table signal-2022-05-12-201844.jpeg
          Reply  Thu May 12 20:24:29 2022, yuta, Update, BHD, POX and POY investigation POY.JPG
       Reply  Mon May 16 13:22:59 2022, yuta, Update, BHD, REFL and AS paths aligned at AP table REFLPOP.JPGPOPAS.JPG
          Reply  Mon May 16 19:14:17 2022, Anchal, Update, BHD, Camera set on AS path and BHDBS output path 
             Reply  Tue May 17 18:43:38 2022, Anchal, Update, BHD, Placed SRM in ITMY Chamber 
                Reply  Wed May 18 08:30:29 2022, Paco, Update, BHD, SRM OpLev 
                   Reply  Thu May 19 08:51:40 2022, Paco, Update, BHD, SRM OpLev 
                Reply  Wed May 18 09:02:52 2022, Anchal, Update, BHD, WFS1 PD centered 
                Reply  Wed May 18 17:23:15 2022, Anchal, Update, BHD, Placed PRM in BS Chamber 
                   Reply  Thu May 19 18:56:08 2022, yuta, Update, BHD, Current OSEM sensor values with all the suspensions aligned OSEMS.txt
                   Reply  Thu May 19 19:05:59 2022, Anchal, Update, BHD, BS Chamber all work finished, BHD path setup 
                      Reply  Fri May 20 20:03:48 2022, Paco, Update, BHD, ITMY chamber work finished - LO and AS overlapped Screenshot_2022-05-20_20-38-25.pngOSEMs.txt
                         Reply  Mon May 23 13:16:59 2022, Paco, Update, BHD, End of vent - checks OSEMs20220523.txtScreenshot_2022-05-23_13-24-06_IFOaligned_GTRY_still_clipping_but_less.pngPR3position.JPG
                            Reply  Tue May 24 15:21:13 2022, Anchal, Update, BHD, Freeswing tests of new SOS started 
Message ID: 16863     Entry time: Wed May 18 17:23:15 2022     In reply to: 16860     Reply to this: 16865   16866
Author: Anchal 
Type: Update 
Category: BHD 
Subject: Placed PRM in BS Chamber 

[Anchal, Paco, Yuta, JC]

SRM Oplev setup

  • We setup SRM oplev path for the aligned position of SRM.
  • This was bit hard, because the return beam was following almost the same path as the input beam, and the return beam had become about 1 cm in diameter.
  • We replaced one of the in-air steering mirror of SRM op-lev input beam with a 1 inch BS on a non-steeerable mount.
  • The returning oplev beam is picked at transmission from this BS.
  • Note: we are not sure if this BS is actually coated for IR or Visible. We couldn't find a visible BS in the lab. We should order a 2 in diameter visible BS to be placed in this position.
  • Half of the input beam would be used for PRM Oplev input.
  • The returning beam was focused with a 100mm focal length lens. Again, this lens is not verified to be for visible wavelength. We think it might have an AR coating for IR. We should get a visible lens for this position also.

PRM Placement

  • PRM placed in nominal position + 2 cm, East.
  • Currently, PRM SOS tower is blocking BS oplev input beam, this needs to be adjusted.
  • Installed PRMOL at nominal position + 2 cm East (to clear path from TT2)
  • I balanced the table succesfully, first using spirit bubble level and then OSEM levels of BS, SR2, PR3 and LO2.
    • Note, that we need to adjust OSEM positions in many of these SOS before pumping down.
  • Input beam from TT2 is going through center of PRM but the reflction is not coming back from PR2, maybe it is missing PR2 or PR2 alignment needs to be adjusted.