Entry  Mon Feb 7 09:00:26 2022, Paco, Update, General, Scheduled power outage recovery 
    Reply  Mon Feb 7 15:32:48 2022, Yehonathan, Update, General, Y End laser controller 
    Reply  Mon Feb 7 16:53:02 2022, Koji, Update, General, Scheduled power outage recovery PXL_20220208_001646282.jpgPXL_20220208_001657871.jpg
       Reply  Wed Feb 9 11:56:24 2022, Anchal, Update, General, Bringing back CDS Screenshot_2022-02-09_12-11-33.png
          Reply  Wed Feb 9 13:55:05 2022, Koji, Update, General, Bringing back CDS 
       Reply  Wed Feb 9 16:43:35 2022, Paco, Update, General, Scheduled power outage recovery - Locking mode cleaner(s) 
          Reply  Thu Feb 10 15:41:00 2022, Anchal, Update, General, Scheduled power outage recovery - Locking mode cleaner(s) 
             Reply  Thu Feb 10 17:57:48 2022, Anchal, Update, General, Scheduled power outage recovery - Locking mode cleaner(s) PXL_20220211_021509819.jpg
                Reply  Thu Feb 10 19:03:23 2022, Koji, Update, General, Scheduled power outage recovery - Locking mode cleaner(s) 
                   Reply  Thu Feb 10 19:46:37 2022, Koji, Update, General, Scheduled power outage recovery - Locking mode cleaner(s) 
                      Reply  Thu Feb 10 21:10:43 2022, Koji, Update, General, Video Mux setting reset Screenshot_2022-02-10_21-11-21.pngScreenshot_2022-02-10_21-11-54.png
             Reply  Fri Feb 11 16:09:11 2022, Anchal, Update, General, Scheduled power outage recovery - Input power increased 
                Reply  Mon Feb 14 18:31:50 2022, Paco, Update, General, Scheduled power outage recovery - IMC recovery progress 
                   Reply  Tue Feb 15 19:32:50 2022, Koji, Update, General, Scheduled power outage recovery - IMC recovery progress PXL_20220216_001731377.jpgScreen_Shot_2022-02-15_at_16.18.16.pngPXL_20220216_001727465.jpgScreen_Shot_2022-02-15_at_16.22.16.pngPXL_20220216_002229572.jpg
                      Reply  Tue Feb 15 19:40:02 2022, Koji, Update, General, IMC locking 
                         Reply  Wed Feb 16 15:19:41 2022, Anchal, Update, General, Reconfigured MC reflection path for low power 
                            Reply  Wed Feb 23 15:08:57 2022, Anchal, Update, General, Removed extra beamsplitter in MC WFS path 
                               Reply  Thu Feb 24 14:32:57 2022, Anchal, Update, General, MC RFPD DCMON channel got stuck to 0 
                                  Reply  Thu Feb 24 19:26:32 2022, Anchal, Update, General, IMC Locking 
                                     Reply  Sun Feb 27 00:37:00 2022, Koji, Update, General, IMC Locking Recovery PXL_20220226_093809056.jpgPXL_20220226_093854857.jpgPXL_20220226_100859871.jpgScreenshot_2022-02-26_01-56-31.pngScreenshot_2022-02-26_01-56-47.png
                                        Reply  Sun Feb 27 01:12:46 2022, Koji, Update, General, IMC manual alignment procedure PXL_20220226_100859871.jpg
    Reply  Fri Feb 11 11:17:00 2022, Anchal, Update, General, Scheduled power outage recovery 
       Reply  Mon Feb 14 21:03:25 2022, Koji, Update, General, Scheduled power outage recovery PXL_20220215_025325118.jpg
Message ID: 16672     Entry time: Tue Feb 15 19:32:50 2022     In reply to: 16669     Reply to this: 16673
Author: Koji 
Type: Update 
Category: General 
Subject: Scheduled power outage recovery - IMC recovery progress 

Reduced the IMC power to 100mW

Setup: The power meter was placed right before the final aperture (Attachment 1)

Before the adjustment: Initial position of the HWP was 37.29deg and the input power was 987mW (Attachments 2/3)

After the adjustment: Initial position of the HWP was 74.00deg and the input power was 100mW (Attachments 4/5)

This made the MCREFL reading 0.549.

The MC refl path optics has not been modified.

Attachment 1: PXL_20220216_001731377.jpg  3.167 MB  | Hide | Hide all
PXL_20220216_001731377.jpg
Attachment 2: Screen_Shot_2022-02-15_at_16.18.16.png  156 kB  | Hide | Hide all
Screen_Shot_2022-02-15_at_16.18.16.png
Attachment 3: PXL_20220216_001727465.jpg  456 kB  | Hide | Hide all
PXL_20220216_001727465.jpg
Attachment 4: Screen_Shot_2022-02-15_at_16.22.16.png  155 kB  | Hide | Hide all
Screen_Shot_2022-02-15_at_16.22.16.png
Attachment 5: PXL_20220216_002229572.jpg  436 kB  | Hide | Hide all
PXL_20220216_002229572.jpg