Entry  Thu Dec 16 15:04:12 2021, Chub, Update, Electronics, ITMX feedthroughs and in-vac cables installed ITMX_feedthrough_install_12-16-21.jpg
    Reply  Thu Dec 16 15:54:08 2021, Koji, Update, Electronics, ITMX feedthroughs and in-vac cables installed PXL_20211216_235056582.jpg
    Reply  Mon Jan 10 15:45:55 2022, Paco, Update, Electronics, ITMY feedthroughs and in-vac cables installed - part I 
       Reply  Tue Jan 11 10:23:18 2022, Paco, Update, Electronics, ITMY feedthroughs and in-vac cables installed - part II 
          Reply  Tue Jan 11 14:21:53 2022, Paco, Update, Electronics, BS feedthroughs and in-vac cables installed 
             Reply  Fri Jan 14 12:01:21 2022, Anchal, Update, Electronics, BS & ITMY feedthroughs labeled and connected to Sat Amps 
Message ID: 16586     Entry time: Fri Jan 14 12:01:21 2022     In reply to: 16574
Author: Anchal 
Type: Update 
Category: Electronics 
Subject: BS & ITMY feedthroughs labeled and connected to Sat Amps 

I labeled all the newly installed flanges and connected the in-air cables (40m/16530) to appropriate ports. These cables are connected to the CDS system on 1Y1/1Y0 racks through the satellite amplifiers. So all new optics now can be damped as soon as they are placed. We need to make more DB9 plugs for setting "Acquire" mode on the HAM-A coil drivers since our Binary input system is not ready yet. Right now, we only have 2 such plugs which means only one optic and be damped at a time.

 