Thu Dec 16 15:04:12 2021, Chub, Update, Electronics, ITMX feedthroughs and in-vac cables installed
|
Thu Dec 16 15:54:08 2021, Koji, Update, Electronics, ITMX feedthroughs and in-vac cables installed
|
Mon Jan 10 15:45:55 2022, Paco, Update, Electronics, ITMY feedthroughs and in-vac cables installed - part I
|
Tue Jan 11 10:23:18 2022, Paco, Update, Electronics, ITMY feedthroughs and in-vac cables installed - part II
|
Tue Jan 11 14:21:53 2022, Paco, Update, Electronics, BS feedthroughs and in-vac cables installed
|
Fri Jan 14 12:01:21 2022, Anchal, Update, Electronics, BS & ITMY feedthroughs labeled and connected to Sat Amps
|
|
Message ID: 16513
Entry time: Thu Dec 16 15:04:12 2021
Reply to this: 16515
16563
|
Author: |
Chub |
Type: |
Update |
Category: |
Electronics |
Subject: |
ITMX feedthroughs and in-vac cables installed |
|
|
The ITMX 10" flange with four DSUB-25 feedthroughs has been install with the cables connected at the in-vac side. See photo; as requested, LO1-1 and LO1-2 are connected to the top row of feedthroughs from left to right respectively and the opposite ends of the cables placed left to right on the laser table. PR2-1 and PR2-2 are connected to the lower row of feedthroughs from left to right respectively, with the opposite ends placed on the surface below the laser from left to right. This seemed the easiest way to keep the cable orientation clear. |
|
|