Fri Oct 29 14:39:37 2021, Anchal, Summary, BHD, 1Y1 cleared. IY3 ready for C1SUS2 I/O and FE.  
|
Tue Nov 2 16:42:00 2021, Paco, Summary, BHD, 1Y1 rack work
|
Tue Nov 2 18:54:41 2021, Anchal, Paco, Update, BHD, Optical fibres laid for BHD upgrade
|
Thu Nov 4 15:03:43 2021, Koji, Summary, BHD, 1Y1 rack work
|
Mon Nov 8 10:13:52 2021, Paco, Summary, BHD, 1Y1 rack work; Sorensens removed
|
Mon Nov 8 13:13:00 2021, Koji, Summary, BHD, 1Y1 rack work; Sorensens removed
|
Mon Nov 8 15:29:05 2021, Paco, Summary, BHD, 1Y1 rack work; New power for cameras
|
Mon Nov 8 18:42:38 2021, Koji, Summary, BHD, Rack Layout / Power Strips
|
Tue Nov 9 19:02:47 2021, Anchal, Summary, BHD, 1Y0 Populated and 1Y1,1Y0 powered
|
|
Message ID: 16453
Entry time: Mon Nov 8 10:13:52 2021
In reply to: 16448
Reply to this: 16454
|
Author: |
Paco |
Type: |
Summary |
Category: |
BHD |
Subject: |
1Y1 rack work; Sorensens removed |
|
|
[Paco, Chub]
Removed all sorensen power supplies from this rack except for 12 VDC one; that one got pushed to the top of the rack and is still powering the cameras. |