Fri Oct 29 14:39:37 2021, Anchal, Summary, BHD, 1Y1 cleared. IY3 ready for C1SUS2 I/O and FE.  
|
Tue Nov 2 16:42:00 2021, Paco, Summary, BHD, 1Y1 rack work
|
Tue Nov 2 18:54:41 2021, Anchal, Paco, Update, BHD, Optical fibres laid for BHD upgrade
|
Thu Nov 4 15:03:43 2021, Koji, Summary, BHD, 1Y1 rack work
|
Mon Nov 8 10:13:52 2021, Paco, Summary, BHD, 1Y1 rack work; Sorensens removed
|
Mon Nov 8 13:13:00 2021, Koji, Summary, BHD, 1Y1 rack work; Sorensens removed
|
Mon Nov 8 15:29:05 2021, Paco, Summary, BHD, 1Y1 rack work; New power for cameras
|
Mon Nov 8 18:42:38 2021, Koji, Summary, BHD, Rack Layout / Power Strips
|
Tue Nov 9 19:02:47 2021, Anchal, Summary, BHD, 1Y0 Populated and 1Y1,1Y0 powered
|
|
Message ID: 16440
Entry time: Fri Oct 29 14:39:37 2021
Reply to this: 16444
|
Author: |
Anchal |
Type: |
Summary |
Category: |
BHD |
Subject: |
1Y1 cleared. IY3 ready for C1SUS2 I/O and FE. |
|
|
[Anchal, Paco]
We cleared 1Y1 rack today removing the following items. This stuff is sitting on the floor about 2 meters east of 1Y3 (see attachment 1):
- A VME crate: We disconnected it's power cords from the side bus.
- A NI PXIe-1071 crate with some SMA multiplexer units on it.
We also moved the power relay ethernet strip from the middle of the rack to the bottom of the rack clearing the space marked clear in Koji's schematics. See attachment 2.
There was nothing to clear in 1Y3. It is ready for installing c1sus2 I/O chassis and FE once the testing is complete.
We also removed some orphaned hanging SMA RG-405 cables between 1Y3 and 1Y1. |
|
|
|
|
|
|