Mon Oct 25 13:23:45 2021, Anchal, Summary, BHD, Before photos of BSC
|
Mon Oct 25 17:37:42 2021, Anchal, Summary, BHD, Part I of BHR upgrade - Removed optics from BSC 
|
Tue Oct 26 16:56:22 2021, Paco, Summary, BHD, Part I of BHR upgrade - Locked PMC and IMC
|
Wed Oct 27 16:27:16 2021, Anchal, Summary, BHD, Part II of BHR upgrade - Prep 
|
Wed Oct 27 16:31:35 2021, Anchal, Summary, BHD, Part III of BHR upgrade - Removal of PR2 Small Suspension
|
Thu Oct 28 16:32:32 2021, Paco, Summary, BHD, Part IV of BHR upgrade - Removal of BSC eastern optics
|
Fri Nov 5 12:21:16 2021, Anchal, Summary, BHD, Part VI of BHR upgrade - Removal of ITMYC optics  
|
Wed Dec 15 16:11:38 2021, Anchal, Summary, BHD, Part VIII of BHR upgrade - Placed LO1
|
Wed Dec 15 17:44:18 2021, Koji, Summary, BHD, Part VIII of BHR upgrade - Placed LO1
|
Thu Jan 6 21:04:41 2022, Anchal, Summary, BHD, Part VIII of BHR upgrade - LO1 OSEMs inserted
|
Mon Jan 10 14:52:51 2022, Anchal, Summary, BHD, LO1 OSEMs roughly calibrated and noise measured 
|
Mon Jan 10 18:36:41 2022, Anchal, Summary, BHD, LO1 free swinging test set to trigger
|
Tue Jan 11 12:19:12 2022, Anchal, Summary, BHD, LO1 Input Matrix Diagonalization performed. 
|
Mon Jan 24 18:53:09 2022, Anchal, Summary, BHD, Part VIII of BHR upgrade - LO2 placed and OSEMs tuned
|
Tue Jan 25 10:55:02 2022, Anchal, Summary, BHD, Part VIII of BHR upgrade - LO2 input matrix diagonalization performed.
|
Tue Jan 25 16:42:03 2022, Anchal, Summary, BHD, Reduced filter gains in all damped new SOS
|
Thu Jan 6 11:54:20 2022, Anchal, Summary, BHD, Part IX of BHR upgrade - Placed AS1 and AS4
|
Fri Jan 7 16:17:42 2022, Anchal, Summary, BHD, Part IX of BHR upgrade - Placed AS1 and AS4 filters
|
Sat Jan 8 16:01:42 2022, Paco, Summary, BHD, Part IX of BHR upgrade - Placed LO2 filters
|
Tue Jan 18 14:26:09 2022, Paco, Summary, BHD, Part IX of BHR upgrade - Placed remaining filters SR2, PR3, PR2
|
Tue Jan 11 18:18:29 2022, Anchal, Summary, BHD, Attempted OSEM installation on AS1
|
Tue Jan 11 18:40:25 2022, Anchal, Summary, BHD, AS1 Sat Amp has a PCB issue
|
Thu Jan 13 09:48:41 2022, Anchal, Summary, BHD, AS1 Sat Amp fixed 
|
Thu Jan 13 12:24:08 2022, Anchal, Summary, BHD, AS1 SD and LR magnets broke
|
Mon Jan 24 21:18:40 2022, Paco, Summary, BHD, Part IX of BHR upgrade - AS1 placed and OSEM tuned
|
Tue Jan 25 11:02:54 2022, Anchal, Summary, BHD, Part IX of BHR upgrade - AS1 free swing test failed
|
Thu Jan 27 08:27:34 2022, Paco, Summary, BHD, Part IX of BHR upgrade - AS1 inspection and correction
|
Wed Feb 2 16:32:02 2022, Anchal, Summary, BHD, Part IX of BHR upgrade - AS1 free swing test still not good 
|
Tue Mar 15 18:42:37 2022, Anchal, Summary, BHD, Part IX of BHR upgrade - AS1 resuspended and OSEMs tuned
|
Tue Mar 15 18:45:12 2022, Anchal, Summary, BHD, Part X of BHR upgrade - BHDBS Path setup
|
Thu Jan 13 12:29:27 2022, Anchal, Summary, BHD, AS4 LR magnet broke
|
Fri Jan 14 18:12:47 2022, Anchal, Summary, BHD, AS4 placed in ITMY Chamber, OSEMs connected
|
Tue Jan 18 18:19:22 2022, Koji, Summary, BHD, AS4 placed in ITMY Chamber, OSEMs connected 
|
Wed Jan 19 12:56:52 2022, Paco, Summary, BHD, AS4 OSEMs installation
|
Thu Jan 20 16:42:55 2022, Paco, Update, BHD, AS4 OSEMs installation - part 2
|
Thu Jan 20 18:16:29 2022, Anchal, Update, BHD, AS4 set to trigger free swing test
|
Fri Jan 21 16:40:10 2022, Anchal, Update, BHD, AS4 Input Matrix Diagonalization performed. 
|
Mon Jan 24 17:12:27 2022, rana, Update, BHD, AS4 Input Matrix Diagonalization performed.
|
Mon Jan 24 20:48:48 2022, Anchal, Update, BHD, AS4 Input Matrix Diagonalization performed.
|
Tue Jan 18 15:19:49 2022, Paco, Summary, BHD, Part IV of BHR upgrade - Replaced old SR3 with SOS SR2. OSEM tuning attemtped. 
|
Tue Jan 18 18:16:28 2022, Anchal, Summary, BHD, Part IV of BHR upgrade - SR2 Sat Amp Box inspection
|
Wed Jan 19 12:50:10 2022, Anchal, Summary, BHD, Part IV of BHR upgrade - SR2 OSEM tuning progress.
|
Thu Jan 20 17:03:36 2022, Anchal, Summary, BHD, Part IV of BHR upgrade - SR2 OSEM tuned.
|
Thu Jan 20 18:41:55 2022, Anchal, Summary, BHD, SR2 set to trigger free swing test
|
Fri Jan 21 11:24:42 2022, Anchal, Summary, BHD, SR2 Input Matrix Diagonalization performed. 
|
Thu Oct 28 17:01:54 2021, Anchal, Summary, BHD, Part III of BHR upgrade - Adding temp fixed flat mirror for PR2
|
Thu Jan 27 17:57:35 2022, Anchal, Summary, BHD, Part III of BHR upgrade - Replaced small suspended PR3 with new SOS PR3 and OSEM tuning
|
Thu Jan 27 18:03:36 2022, Paco, Summary, BHD, Part III of BHR upgrade - Install PR2, balance, and attempt OSEM tuning
|
Thu Jan 27 20:46:38 2022, Koji, Summary, BHD, Part III of BHR upgrade - Install PR2, balance, and attempt OSEM tuning 
|
Fri Jan 28 10:37:59 2022, Paco, Summary, BHD, Part III of BHR upgrade - PR2 OSEM finalized, reinsall LO1 OSEMs
|
Fri Jan 28 11:30:52 2022, Koji, Summary, BHD, Part III of BHR upgrade - PR2 OSEM finalized, reinsall LO1 OSEMs
|
Fri Jan 28 16:35:18 2022, Anchal, Summary, BHD, AS1, PR2 and PR3 set to trigger free swing test
|
Wed Feb 2 16:22:00 2022, Anchal, Summary, BHD, Part III of BHR upgrade - PR2 inpute matrix diagonalized 
|
Wed Feb 2 16:27:57 2022, Anchal, Summary, BHD, Part III of BHR upgrade - PR3 inpute matrix diagonalized 
|
Wed Oct 27 16:38:02 2021, Anchal, Summary, BHD, Part II of BHR upgrade - Relocation of TT2 and MMT1/2 alignment
|
Wed Oct 27 18:11:37 2021, Koji, Summary, BHD, Part II of BHR upgrade - Relocation of TT2 and MMT1/2 alignment
|
Wed Oct 27 18:16:45 2021, Koji, Summary, BHD, Part II of BHR upgrade - Relocation of TT2 and MMT1/2 alignment
|
Thu Mar 17 17:23:22 2022, Anchal, Summary, BHD, Part IIa of BHR upgrade - Green laser alignment
|
Mon Mar 21 18:24:07 2022, Anchal, Summary, BHD, Part IIa of BHR upgrade - Green laser alignment on Yarm
|
Thu Mar 24 19:20:28 2022, Anchal, Summary, BHD, Part IIa of BHR upgrade - Green laser alignment on Yarm
|
Fri Mar 25 18:20:28 2022, Anchal, Summary, BHD, Part IIa of BHR upgrade - Green laser alignment on Yarm
|
Sat Mar 26 13:04:38 2022, Paco, Summary, BHD, Part IIa of BHR upgrade - Green laser alignment on Yarm
|
Thu Mar 31 18:58:16 2022, Ian MacMillan, Summary, BHD, Part IIa of BHR upgrade - IR laser alignment on Xarm
|
Tue Apr 5 18:15:06 2022, Anchal, Summary, BHD, Part IIa of BHR upgrade - IR laser alignment on Xarm
|
Wed Apr 6 01:20:48 2022, Koji, Summary, BHD, Part IIa of BHR upgrade - IR laser alignment on Xarm   
|
Wed Apr 6 22:51:47 2022, Koji, Summary, BHD, Part IIa of BHR upgrade - IR laser alignment on Xarm 
|
Wed Apr 6 12:03:51 2022, Anchal, Summary, BHD, Part IIa of BHR upgrade - IR laser alignment on Yarm
|
Thu Apr 7 17:59:51 2022, Anchal, Summary, BHD, Part IIa of BHR upgrade - IR laser alignment on Yarm
|
Fri Apr 8 17:21:31 2022, Ian MacMillan, Summary, BHD, Part IIa of BHR upgrade - IR laser alignment on Yarm
|
Mon Apr 11 21:13:21 2022, Paco, Summary, BHD, Part IIa of BHR upgrade - POY11 debugging
|
Mon Apr 11 21:44:14 2022, Koji, Summary, BHD, Part IIa of BHR upgrade - POY11 debugging  
|
Thu Apr 14 11:52:57 2022, yehonathan, Summary, BHD, Part IIa of BHR upgrade - POY11 debugging 
|
Thu Apr 14 18:39:13 2022, Paco, Summary, BHD, Part IIa of BHR upgrade - POY11 debugging
|
Mon Apr 18 17:53:45 2022, Paco, Summary, BHD, Part IIa of BHR upgrade - POY11 debugging
|
|
Message ID: 16425
Entry time: Mon Oct 25 17:37:42 2021
In reply to: 16424
Reply to this: 16429
|
Author: |
Anchal |
Type: |
Summary |
Category: |
BHD |
Subject: |
Part I of BHR upgrade - Removed optics from BSC |
|
|
[Anchal, Paco, Ian]
Clean room etiquettes
- Two people in coverall suits, head covers, masks and AccuTech ultra clean gloves.
- One person in just booties to interact with outside "dirty" world.
- Anything that comes in chamber, first cleaned outside with clean cloth and IPA. Then cleaned by the "clean" folks. We followed this for allen keys, camera and beam finder card.
- Once the chamber cover has been removed, cover the annulus with donut. We forgot to do this :(
Optics removal and changes
We removed the following optics from the BSC table and stored them in X-end flowbench with fan on. See attachment 1 and 2.
- IPPOS SM2
- GRX SM2
- PRM OL1
- PRMOL4
- IPPOS SM3
- IPANG SM1
- PRM OL2
- Unidentified optic inbetween IPPOS45P and IPPOS SM3
- Beam block behing PR3
- Beam block behind GR PBS
- GR PBS
- GRPERI1L (Periscope)
- PRMOL3
- IPPOS45P
- Cylindrical counterweight on North-west end of table.
- Cheap rectangular mirror on South west end of table (probably used for some camera, but not in use anymore)
- IPANGSM2
We also changed the direction of clamp of MMT1 to move it away from the center of the able (where PRM will be placed)
We screwed in the earthquake stops on PRM and BS from front face and top.
We unscrewed the cable post for BS and PRM oplevs and loved it in between SR3 and BS and screwed it lightly.
We moved the PRM, turned it anti-clockwise 90 degrees and brought it in between TT2 and BS. Now there is a clear line of sight between TT2 and PR2 on ITMY table.
Some next steps:
- We align the input beam to TT2 by opening the "Injection Chamber" (formerly known as OMC chamber). While doing so, we'll clear unwanted optics from this table as well.
- We open ITMX chamber, clear some POP optics. If SOS are ready, we would replace PR2 with SOS and put it in a new position.
- Then we'll replace PR3 with an SOS and align the beam to BS.
These are next few days of work. We need atleast one SOS ready by Thursday.
Photos after today's work: https://photos.app.goo.gl/EE7Mvhw5CjgZrQpG6 |
|
|
|
|