Fri Dec 18 22:59:12 2020, Jon, Configuration, CDS, Updated CDS upgrade plan 
|
Mon Dec 21 09:28:50 2020, Jamie, Configuration, CDS, Updated CDS upgrade plan
|
Wed Dec 23 23:06:45 2020, gautam, Configuration, CDS, Updated CDS upgrade plan
|
Tue Jan 19 14:05:25 2021, Jon, Configuration, CDS, Updated CDS upgrade plan 
|
Tue Jan 19 15:43:24 2021, gautam, Configuration, CDS, Updated CDS upgrade plan
|
|
Message ID: 15772
Entry time: Tue Jan 19 15:43:24 2021
In reply to: 15771
|
Author: |
gautam |
Type: |
Configuration |
Category: |
CDS |
Subject: |
Updated CDS upgrade plan |
|
|
Not sure if 1Y1 can accommodate both c1sus2 and c1bhd as well as the various electronics chassis that will have to be installed. There may need to be some distribution between 1Y1 and 1Y3. Does Koji's new wiring also specify which racks hold which chassis?
Some minor improvements to the diagram:
- The GPS receiver in 1X7 should be added. All the timing in the lab is synced to the 1pps from this.
- We should add hyperlinks to the various parts datasheets (e.g. Dolphin switch, RFM switch, etc etc) so that the diagram will be truly informative and self-contained.
- Megatron and nodus, but especially chiara (NFS server), should be added to the diagram.
|