Message ID: 15709     Entry time: Fri Dec 4 19:23:40 2020
Author: Koji 
Type: Update 
Category: Electronics 
Subject: AA/AI board testing ongoing 

I have the setup built for the AA/AI board testing around the PD testing area. Please let me leave it like that for a week or so.

12/4 TF Tested 5 PCBs
12/6 TF Tested 19 PCBs (12min/PCB) - found 1 failure (S2001479 CH1) -> Fixed 12/11
12/8 TF Tested 16 PCBs (12min/PCB)
       PSD Tested 4 PCBs (11min/PCB)
12/11 TF Tested 10 PCBs + 1 fixed channel (All channels checked)
       PSD Tested 10 PCBs (11min/PCB)
12/14 PSD Tested 4 PCBs (6.5min/PCB) fixed noise issue of 2 ch, TF issue of 1 ch
12/15 PSD Tested 32 PCBs (6.5min/PCB) fixed noise issue of 1ch
Temp dependence measurement
Crosstalk measurement
 

 