Entry  Fri Oct 18 20:21:33 2019, shruti, Update, ALS, AM measurement attempt at X end 
    Reply  Thu Nov 7 17:46:10 2019, shruti, Update, ALS, AM measurement at X end AMTF20191107.png
Message ID: 14979     Entry time: Fri Oct 18 20:21:33 2019     Reply to this: 15020
Author: shruti 
Type: Update 
Category: ALS 
Subject: AM measurement attempt at X end 

[Shruti, Rana]

- At the X end, we set up the network analyzer to begin measurement of the AM transfer function by actuation of the laser PZT.

- The lid of the PDH optics setup was removed to make some checks and then replaced.

- From the PDH servo electronics setup the 'GREEN_REFL' and 'TO AUX-X LASER PZT' cables were removed for the measurement and then re-attached after.

- The signal today was too low to make a real measurement of the AM transfer function, but the GPIB scripts and interfacing was tested. 