Subject: pre-construction inspection 

The Central Plant building will be undergoing seismic upgrades in the near future.  The adjoining north wall along the Y arm will be the first to have this work done, from inside the Central Plant.  Project manager Eugene Kim has explained the work to me and also noted our concerns.  He assured me that the seismic noise from the construction will be minimized and we will always be contacted when the heaviest construction is to be done.

Tomorrow at 11am, I will bring Mr. Kim and a few others from the construction team to look at the wall from inside the lab.  If you have any questions or concerns that you want to have addressed, please email them to me or contact Mr. Kim directly at x4860 or through email at eugene.kim@caltech.edu . 