Entry  Mon Nov 19 14:59:48 2018, Chub, Update, VAC, Vent 81 
    Reply  Mon Nov 19 17:09:00 2018, Steve, Update, VAC, Vent 81 beforeVent82.pngvent81completed.png
       Reply  Mon Nov 19 22:01:50 2018, gautam, Update, VAC, Loose nut on valve IMG_7171.JPG
          Reply  Tue Nov 20 13:13:01 2018, gautam, Update, VAC, IMC alignment is okay 
       Reply  Mon Nov 26 15:58:48 2018, Steve, Update, VAC, Vent 81 
          Reply  Mon Nov 26 17:16:27 2018, gautam, Update, SUS, EY chamber work IMG_5251.JPG
          Reply  Thu Dec 20 10:28:43 2018, gautam, Update, VAC, Heavy doors back on for pumpdown 82 
Message ID: 14310     Entry time: Tue Nov 20 13:13:01 2018     In reply to: 14307
Author: gautam 
Type: Update 
Category: VAC 
Subject: IMC alignment is okay 

I checked the IMC alignment following the vent, for which the manual beam block placed on the PSL table was removed. The alignment is okay, after minor touchup, the MC Trans was ~1200 cts which is roughly what it was pre-vent. I've closed the PSL shutter again.