Entry  Thu Jan 11 14:47:11 2018, Steve, Update, PSL, shelf work for tomorrow 
    Reply  Fri Jan 12 10:26:24 2018, Steve, Update, PSL, PSL shelf work schedule 
       Reply  Tue Jan 16 11:05:51 2018, gautam, Update, PSL, PSL shelf - AOM power connection interrupted 
          Reply  Tue Jan 16 16:18:47 2018, Steve, Update, PSL, new PSL shelf in place DSC00020.JPG
          Reply  Tue Jan 16 21:46:02 2018, gautam, Update, PSL, PSL shelf - AOM power connection interrupted 
Message ID: 13538     Entry time: Fri Jan 12 10:26:24 2018     In reply to: 13532     Reply to this: 13549
Author: Steve 
Type: Update 
Category: PSL 
Subject: PSL shelf work schedule 

Measurements for good fit were made. The new shelf will be installed on next Tuesday at 2pm

The reference cavity ion pump is in the way  so the cavity will be moved 5" westward. The shelf height space will be 10"  Under shelf working height 18" to optical table.

Quote:

I have just received the scheduling of the PSL self work for tomorrow. Gautam and I agreed that if it is needed I will shut the laser off and cover the hole table with plastic.

 