Thu Jan 11 14:47:11 2018, Steve, Update, PSL, shelf work for tomorrow
|
Fri Jan 12 10:26:24 2018, Steve, Update, PSL, PSL shelf work schedule
|
Tue Jan 16 11:05:51 2018, gautam, Update, PSL, PSL shelf - AOM power connection interrupted
|
Tue Jan 16 16:18:47 2018, Steve, Update, PSL, new PSL shelf in place
|
Tue Jan 16 21:46:02 2018, gautam, Update, PSL, PSL shelf - AOM power connection interrupted
|
|
Message ID: 13538
Entry time: Fri Jan 12 10:26:24 2018
In reply to: 13532
Reply to this: 13549
|
Author: |
Steve |
Type: |
Update |
Category: |
PSL |
Subject: |
PSL shelf work schedule |
|
|
Measurements for good fit were made. The new shelf will be installed on next Tuesday at 2pm
The reference cavity ion pump is in the way so the cavity will be moved 5" westward. The shelf height space will be 10" Under shelf working height 18" to optical table.
Quote: |
I have just received the scheduling of the PSL self work for tomorrow. Gautam and I agreed that if it is needed I will shut the laser off and cover the hole table with plastic.
|
|