Entry  Tue Aug 8 17:04:26 2017, Steve, Update, VAC, unintended pump down pumping_down.png
    Reply  Tue Aug 8 17:44:11 2017, Steve, Update, VAC, unintended pump down stopped_pumping.png
       Reply  Wed Aug 9 11:59:51 2017, Steve, Update, VAC, unintended pump down at vacuum normal pdc.pngpd80b@vacnormal.png
          Reply  Thu Aug 10 15:45:34 2017, Steve, Update, VAC, accidental vent to 17 Torr Mag_UPS.jpgUPSbatteryPack.jpgclosing_V1.jpg
             Reply  Mon Aug 21 16:35:48 2017, gautam, Update, VAC, UPS checkup 
                Reply  Wed Aug 23 10:11:46 2017, Steve, Update, VAC, vacuum valve specifications 
                   Reply  Tue Aug 29 15:35:19 2017, Steve, Update, VAC, vacuum pump specifications & manuals 1759489_995814a9-55c1-4fa1-b333-f446d272c1cc.jpg
Message ID: 13171     Entry time: Tue Aug 8 17:04:26 2017     In reply to: 0     Reply to this: 13172
Author: Steve 
Type: Update 
Category: VAC 
Subject: unintended pump down 

IFO pressure 2 Torr,    PSL  shutter closed.  I'm pumping down with 2 roughing pumps with ion pump gate valves open and annulosses at atm.

The vacuum envelope was vented to 17 Torr while I was replacing the USP battery stack. More about this later.....

Do not plan on using the interferrometer tonight.  I will complete the pumpdown tomorrow morning.

 

Attachment 1: pumping_down.png  24 kB  | Hide | Hide all
pumping_down.png