Entry  Wed Apr 13 00:56:07 2016, gautam, Update, endtable upgrade, X endtable repopulation 
    Reply  Wed Apr 13 11:00:28 2016, Steve, Update, endtable upgrade, X endtable repopulation 
       Reply  Wed Apr 13 18:25:07 2016, gautam, Update, endtable upgrade, Lightwave health check 
          Reply  Fri Apr 15 18:38:12 2016, gautam, Update, endtable upgrade, Lightwave health check - NO IMPROVEMENT 
             Reply  Tue Apr 19 18:37:29 2016, gautam, Update, endtable upgrade, Laser swap + optical layout IR_modematch_19April2016_2.pdf
                Reply  Thu Apr 21 14:25:52 2016, gautam, Update, endtable upgrade, Green light recovered IMG_6567.JPGIMG_6568.JPGCVI_reflectivity.jpeg
                Reply  Tue Apr 26 15:22:35 2016, Steve, Update, endtable upgrade, Cleaning ETMX vacuum dirty window ETMX-Tvp.jpgETMX-TvpDetail.jpg
                   Reply  Tue Apr 26 23:19:42 2016, gautam, Update, endtable upgrade, Green aligned to arm - high order mode flashes seen IMG_2219.JPGIMG_2220.JPG
                      Reply  Thu Apr 28 00:41:08 2016, gautam, Update, endtable upgrade, more progress - Transmon PD installed 
                         Reply  Fri Apr 29 00:55:46 2016, gautam, Update, endtable upgrade, green PDH locked to Xarm 
                            Reply  Mon May 2 19:14:18 2016, gautam, Update, endtable upgrade, Optical layout almost complete ETMX_wedge.pdf
                               Reply  Thu May 5 03:05:37 2016, gautam, Update, endtable upgrade, ALS status update ALS_noiseSpec_5May2016_2.pdfCoherence_5May2016.pdfimage.jpeg
                                  Reply  Thu May 5 04:05:03 2016, ericq, Update, LSC, Aux X PDH checks nom_noise.pngnom_olg.png
                                     Reply  Thu May 5 14:03:52 2016, ericq, Update, LSC, Further Aux X PDH tweaks 2016-05-05_newals.pdf
                                  Reply  Thu May 5 14:05:01 2016, rana, Update, endtable upgrade, ALS status update 
                                  Reply  Thu May 5 21:28:44 2016, gautam, Update, endtable upgrade, Innolight PZT capacitance 
                               Reply  Thu May 19 16:29:20 2016, Steve, Update, endtable upgrade, Optical layout almost complete ETMX_4x3_closed.jpgsealedETMXenclosure.jpg
                                  Reply  Fri Sep 30 19:53:07 2016, gautam, Update, endtable upgrade, X end IR pickoff fiber coupled 
                                     Reply  Wed Oct 5 16:28:10 2016, gautam, Update, endtable upgrade, EX laser power monitor PD installed 
                   Reply  Wed Apr 27 15:04:47 2016, Steve, Update, endtable upgrade, Cleaning ETMX vacuum dirty window 1cETMX-Tcmp.jpg
                      Reply  Fri Apr 29 16:05:23 2016, gautam, Update, endtable upgrade, Cleaning ETMX vacuum dirty window IMG_0755.JPG
Message ID: 12079     Entry time: Fri Apr 15 18:38:12 2016     In reply to: 12075     Reply to this: 12083
Author: gautam 
Type: Update 
Category: endtable upgrade 
Subject: Lightwave health check - NO IMPROVEMENT 

I re-measured the power levels today.

We have ~205mW out of the NPRO, and ~190mW after the Faraday. It doesn't look like the situation is going to improve dramatically. I'm going to work on a revised layout with the Innolight as soon as I've profiled the beam from it, and hopefully, by Monday, we can decide that we are going ahead with using the Innolight.