Entry  Thu Mar 10 16:29:32 2016, gautam, Update, endtable upgrade, Inventory check Inventory_check.pdfDoubler_comparison.pdf
    Reply  Thu Mar 10 16:32:45 2016, rana, Update, endtable upgrade, Inventory check 
       Reply  Mon Mar 14 22:42:23 2016, gautam, Update, endtable upgrade, Inventory check 
       Reply  Mon Mar 28 10:43:18 2016, Steve, Update, endtable upgrade, ETMX 4'x2' optical table pictures ETMX4x2Layout.jpgETMX_4x2.JPGETMXopt_4x2.JPG
          Reply  Wed Mar 30 17:38:52 2016, gautam, Update, endtable upgrade, X end table proposed layout  ETMX_3x2.JPGlayout_details_20160328.pdfETMX_proposed_layout.pdf
             Reply  Thu Mar 31 09:38:41 2016, Steve, Update, endtable upgrade, Y end 4x3 existing layout ETMY4x3layout.jpg
                Reply  Thu Mar 31 19:49:31 2016, gautam, Update, endtable upgrade, proposed layout v2 ETMX_proposed_layout_v2.pdf
                   Reply  Mon Apr 4 10:59:12 2016, gautam, Update, endtable upgrade, proposed layout v3 ETMX_proposed_layout_v3.pdfIR_modematch.pdfGreen_modematch.pdfXendALaMode.zipETMX_proposed_layout_dimensions.dwg
                      Reply  Mon Apr 4 15:04:14 2016, gautam, Update, endtable upgrade, COMPONENT REMOVAL 
                         Reply  Tue Apr 5 11:42:17 2016, gaericqutam, Update, endtable upgrade, TABLE REMOVAL 
                            Reply  Wed Apr 6 17:52:21 2016, gautam, Update, endtable upgrade, First contact cleaning commenced 
                               Reply  Thu Apr 7 12:51:24 2016, gautam, Update, endtable upgrade, Beam height differences 
                                  Reply  Thu Apr 7 14:30:58 2016, Steve, Update, endtable upgrade, ETMX table height ETMXbrs.pngETMX.jpgIMG_0618.JPGETMX.jpgETMXwc.jpg
                                     Reply  Fri Apr 8 09:13:20 2016, Steve, Update, endtable upgrade, ETMX-T beam height ETMXalignedT.pngETMXF.jpg
Message ID: 12029     Entry time: Thu Mar 10 16:29:32 2016     Reply to this: 12030
Author: gautam 
Type: Update 
Category: endtable upgrade 
Subject: Inventory check 

I did a quick sweep of the lab to find out what hardware has already been acquired for the X-end table upgrade. The attached PDF is an inventory check in the spirit of this elog.

Some things we have to decide:

  • Are we okay with using the old green coloured faraday mount for the IR faraday? I have in hand a piece identical to the one used at the Y-end for the green faraday, that is red in colour, so I guess we can switch this out.
  • The way in which the doubling oven is currently mounted at the X-end is using some posts cobbled together. The Y-end looks to have a custom mount machined for it (see Attachment #2). Do we want to go ahead and get something like this done?
  • I suppose it is okay to reuse all the old optics (mirrors, lenses, harmonic separators) and PDs? It may be that we need to order som extra mirrors/lenses/posts (this will become clear once I do the layout)

I have not gotten around to planning the layout or doing drawings. I will try and first work through a mode-matching solution to make sure we have all the required lenses. It may be that we need some 1" or 2" mirrors as well. The beam from the lightwave NPRO is quite elliptical, but we have a number of cylindrical lenses in hand already if we decide we want to use these, so I guess we don't have to worry about this...

This is quite a preliminary list, and I will add/update over the coming days as I do more detailed planning, but have I missed out anything obvious?

Attachment 1: Inventory_check.pdf  37 kB  | Show | Hide all | Show all
Attachment 2: Doubler_comparison.pdf  9.329 MB  | Hide | Hide all | Show all
Doubler_comparison.pdf